Forward Emergency Plan Update
ML16274A029
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 09/27/2016
From: Blome B
Omaha Public Power District
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML16277A416 List:
References
LIC-16-0091
Download: ML16274A029 (1)


Text

Omaha Public Power District September 27, 2016 LIC-16-0091 U.S. Nuclear Regulatory Commission A TIN: Document Control Desk Washington, DC 20555 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285

Reference:

10 CFR 50.54(q) 10 CFR 50.4(b)

1. Letter from OPPD (S. Marik) to USNRC (Document Control Desk), "Emergency Planning Changes," dated July 15, 2016. (LIC-16-0057) (ML16209A248)

SUBJECT:

Emergency Plan Update In accordance with 10 CFR 50.54(q), 10 CFR 50, Appendix E, Section V, and 10 CFR 50.4(b)(5), please find the procedures: RERP-EP-FC-1001 Revision 0, EP-FC-1001Addendum1 Revision 0, EP-FC-1001Addendum2 Revision 0, EP-FC-1001 Addendum 3 revision 1 enclosed for the Document Control Desk (holder of Copy 165) and the NRC Region IV Branch 1 Secretary (holder of Copies 154 and 155). The RERP was reformatted to reflect the Exelon Fleet process along with some administrative changes. A summary of changes was previously submitted in Reference 1.

REMOVE SECTION INSERT SECTION RERP Appendix A - Appendix D; Section A - Section P EP-FC-1001 Rev. O issued 06/26/2016 FCS On-Shift Staffing Technical Basis EP-FC-1001 Addendum 1 Rev.a issued 06/16/2016 ETE for FCS Plume Exposure Pathway EPZ EP-FC-1001Addendum2 Rev. 0 issued 06/16/2016 EPIP-OSC-1 and Associated TBD's EP-FC-1001 Addendum 3 Rev. 1 issued 06/16/2016 This change was reviewed and does not constitute a decrease in effectiveness. No commitments are made in this letter. If you have any questions regarding the previous transmittal, please contact Mr.

Eric Plautz at 402-533-7308.

sti~

Braaley H. Blome Manager - Site Regulatory Assurance BHB/cac c:

NRC Region IV Plant Support Branch 1 Secretary (2 sets)

C.F. Lyon, NRC Project Manager (w/o enclosures)

S. M. Schneider, NRC Senior Resident Inspector (w/o enclosures)

Emergency Planning Department (w/o enclosures)

Fort Calhoun Station, PO Box 550 Fort Calhoun, NE 68023/9610 Power Lane, Blair, NE 68008