LIC-12-0019, Omaha Public Power District, Notification If Response to Special Inspection Report by March 15, 2012

From kanterella
Jump to navigation Jump to search
Omaha Public Power District, Notification If Response to Special Inspection Report by March 15, 2012
ML12058A071
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 02/24/2012
From: Bannister D
Omaha Public Power District
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-11-246, LIC-12-0019, NRC-12-0012
Download: ML12058A071 (1)


Text

Omaha Public Power District 444 South 1fjh Street Mall Omaha, NE 68102-2247 February 24, 2012 LlC-12-0019 U.S. Nuclear Regulatory Commission ATTN : Document Control Desk Washington, D.C. 20555

References:

1. Docket No. 50-285
2. Letter from NRC (A. Vegel) to OPPD (D. J. Bannister), "NRC Inspection Report 05000285/2011406; Preliminary Greater Than Green Findings, Fort Calhoun Station,"

dated February 14, 2012 (NRC-12-0012) (EA 11-246)

Subject:

Response to Special Inspection Report The Omaha Public Power District (OPPD) received two apparent violations that are being considered for escalated enforcement in Reference 2. Reference 2 also provided the following options to address the apparent violations :

1. Attend a Regulatory Conference, or
2. Submit in writing OPPD's position on the findings to the Nuclear Regulatory Commission (NRC) within 30 days.

Mr. Mike Hay, Chief, Plant Support Branch 1, Division of Reactor Safety, was notified that OPPD has elected to submit in writing OPPD's position to the NRC on the apparent violations by March 15, 2012.

Should you have questions or comments, please contact Ms. Susan Baughn at 402-533-7215.