MONTHYEARCNL-22-031, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-03-22022 March 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML19029A1542018-12-17017 December 2018 Permanently Defueled Emergency Action Level Technical Bases LIC-17-0041, Independent Spent Fuel Storage Installation - Revision to Emergency Plan Update2017-04-0707 April 2017 Independent Spent Fuel Storage Installation - Revision to Emergency Plan Update LIC-17-0002, Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Update2017-02-14014 February 2017 Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Update LIC-16-0091, Forward Emergency Plan Update2016-09-27027 September 2016 Forward Emergency Plan Update ML16243A1302016-08-17017 August 2016 Emergency Planning Changes LIC-16-0057, Emergency Planning Changes2016-07-15015 July 2016 Emergency Planning Changes LIC-16-0017, Submittal of Emergency Planning Implementing Procedure and Index. Includes Emergency Plan Implementing Procedure Change EPIP-TSC-2, Rev 182016-02-10010 February 2016 Submittal of Emergency Planning Implementing Procedure and Index. Includes Emergency Plan Implementing Procedure Change EPIP-TSC-2, Rev 18 LIC-16-0002, Transmittal of Emergency Planning Implementing Procedure and Index, Revision 49 to EPIP-EOF-6, Offsite Dose Assessment Using the Unified RASCAL Interface2016-01-0404 January 2016 Transmittal of Emergency Planning Implementing Procedure and Index, Revision 49 to EPIP-EOF-6, Offsite Dose Assessment Using the Unified RASCAL Interface LIC-15-0146, Emergency Planning Implementing Procedure and Index2015-12-21021 December 2015 Emergency Planning Implementing Procedure and Index LIC-15-0138, Transmittal of Emergency Planning Implementing Procedure and Index, Including Revision 49 to EPIP-EOF-6, Revision 63 to EPIP-OSC-2, and Revision 20 to RERP Section F2015-12-0404 December 2015 Transmittal of Emergency Planning Implementing Procedure and Index, Including Revision 49 to EPIP-EOF-6, Revision 63 to EPIP-OSC-2, and Revision 20 to RERP Section F LIC-14-0098, License Amendment Request 14-06 to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors2014-12-26026 December 2014 License Amendment Request 14-06 to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors LIC-12-0156, OPPD Communications Assessment Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 9.3, Emergency Preparedness, of the Near-Term Task Force Review of Insights2012-10-31031 October 2012 OPPD Communications Assessment Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 9.3, Emergency Preparedness, of the Near-Term Task Force Review of Insights fro LIC-04-0060, Transmittal of Changes to Emergency Plan Implementing Procedures2004-04-29029 April 2004 Transmittal of Changes to Emergency Plan Implementing Procedures LIC-04-0048, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2004-04-14014 April 2004 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-04-0041, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2004-03-17017 March 2004 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-04-0037, Transmittal of Changes to Emergency Plan Implementing Procedures2004-03-15015 March 2004 Transmittal of Changes to Emergency Plan Implementing Procedures LIC-03-0155, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2003-11-21021 November 2003 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-03-0151, Revision 15 to TSC-8, Core Damage Assessment and Revised EPIP Index Page 1 and 22003-11-0606 November 2003 Revision 15 to TSC-8, Core Damage Assessment and Revised EPIP Index Page 1 and 2 LIC-03-0128, Transmittal of Changes to Emergency Implementing Procedures (EPIP)2003-09-15015 September 2003 Transmittal of Changes to Emergency Implementing Procedures (EPIP) LIC-03-0125, Transmittal of Changes to Emergency Plan Implementing Procedures2003-09-0505 September 2003 Transmittal of Changes to Emergency Plan Implementing Procedures LIC-03-0115, Revision of Cover Letter to Previously Transmitted Changes to Emergency Plan Implementing Procedures (EPIP)2003-08-14014 August 2003 Revision of Cover Letter to Previously Transmitted Changes to Emergency Plan Implementing Procedures (EPIP) LIC-03-0111, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) for Fort Calhoun2003-08-0606 August 2003 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) for Fort Calhoun LIC-03-0102, Transmittal of Changes to Emergency Plan Implementing Procedures2003-07-25025 July 2003 Transmittal of Changes to Emergency Plan Implementing Procedures LIC-03-0098, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2003-07-14014 July 2003 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-03-0096, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2003-07-0909 July 2003 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-03-0087, Transmittal of Changes to Emergency Plan Implementing Procedures2003-06-13013 June 2003 Transmittal of Changes to Emergency Plan Implementing Procedures LIC-03-0082, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2003-05-23023 May 2003 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-03-0065, Transmittal of Changes to Emergency Plan Implementing Procedures & to Emergency Planning Forms2003-04-28028 April 2003 Transmittal of Changes to Emergency Plan Implementing Procedures & to Emergency Planning Forms LIC-03-0058, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) and to Radiological Emergency Response Plan (RERP)2003-04-14014 April 2003 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) and to Radiological Emergency Response Plan (RERP) LIC-03-0041, Transmittal of Omaha Public Power District, Changes to Radiological Emergency Response Plan for Fort Calhoun2003-03-24024 March 2003 Transmittal of Omaha Public Power District, Changes to Radiological Emergency Response Plan for Fort Calhoun LIC-03-0015, Transmittal of Changes to Emergency Plan Implementing Procedure & Emergency Planning Forms2003-02-0606 February 2003 Transmittal of Changes to Emergency Plan Implementing Procedure & Emergency Planning Forms LIC-02-0149, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2002-12-20020 December 2002 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-02-0135, Transmittal of Changes to Emergency Plan Implementing Procedure2002-11-21021 November 2002 Transmittal of Changes to Emergency Plan Implementing Procedure LIC-02-0126, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)2002-11-0404 November 2002 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) LIC-02-0112, Transmittal of Changes to Emergency Planning Forms (Epf) and Radiological Emergency Response Plan (RERP)2002-09-23023 September 2002 Transmittal of Changes to Emergency Planning Forms (Epf) and Radiological Emergency Response Plan (RERP) LIC-02-0086, Transmittal of Changes to Emergency Plan Implementing Procedures2002-07-30030 July 2002 Transmittal of Changes to Emergency Plan Implementing Procedures LIC-02-0068, Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) and Emergency Planning Forms (Epf)2002-05-22022 May 2002 Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP) and Emergency Planning Forms (Epf) LIC-02-0069, Omaha Public Power District Transmittal of Changes to Emergency Plan Implementing Procedure (EPIP)2002-05-22022 May 2002 Omaha Public Power District Transmittal of Changes to Emergency Plan Implementing Procedure (EPIP) ML0207406432002-02-14014 February 2002 Radiological Emergency Response Plan LIC-02-0015, Transmittal of Fort Calhoun Revised Emergency Plan Implementing Procedures FC-EPF Index Page 1 of 2 Issued 01/15/2002, FC-EPF-14 R10 Issued 01/15/2002, EPIP Index Page 1 of 2 Issued 01/23/2002, EPIP-EOF-6 R32 Issued 01/23/20022002-02-0707 February 2002 Transmittal of Fort Calhoun Revised Emergency Plan Implementing Procedures FC-EPF Index Page 1 of 2 Issued 01/15/2002, FC-EPF-14 R10 Issued 01/15/2002, EPIP Index Page 1 of 2 Issued 01/23/2002, EPIP-EOF-6 R32 Issued 01/23/2002 2022-03-22
[Table view] Category:Letter type:LIC
MONTHYEARLIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update LIC-18-0030, Request for Partial Site Release Phase 22018-11-12012 November 2018 Request for Partial Site Release Phase 2 LIC-18-0028, Letter of Intent to Submit Request for Additional Partial Site Release2018-10-18018 October 2018 Letter of Intent to Submit Request for Additional Partial Site Release LIC-18-0027, Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2018-10-0303 October 2018 Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update LIC-18-0003, License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool2018-09-28028 September 2018 License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool LIC-18-0025, Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 20192018-07-19019 July 2018 Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 2019 LIC-18-0023, Fort Calhoun Station, Unit 1 Request for Partial Site Release2018-06-29029 June 2018 Fort Calhoun Station, Unit 1 Request for Partial Site Release LIC-18-0021, Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan)2018-06-0606 June 2018 Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan) LIC-18-0017, Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy2018-04-26026 April 2018 Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy 2023-08-24
[Table view] |
Text
Omaha Public Power District 444 South 16th Street Mall Omaha NE 68102-2247 July 9, 2003 LIC-03-0096 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Reference:
Docket No. 50-285
SUBJECT:
Transmittal of Changes to Emergency Plan Implementing Procedures (EPIP)
In accordance with 10 CFR 50.54(q), 10 CFR 50, Appendix E, Section V, and 10 CFR 50.4(b)(5), please find EPIP packages enclosed for the Document Control Desk (holder of Copy 165) and the NRC Region IV Plant Support Branch Secretary (holder of Copies 154 and 155).
The document update instructions and summary of changes are included on the Confirmation of Transmittal form (Form EP-1) attached to each controlled copy change package. Please return the Confirmation of Transmittal forms by August 18, 2003.
The revised documents included in the enclosed package are:
EPIP Index 1 Page issued 6/19/03 EPIP-TSC-1 R24 issued 6/19/03 If you have any questions regarding the enclosed changes, please contact Mr. Carl Simmons at (402) 533-6430.
Sincerely, R. L. Phelps Division Manager Nuclear Engineering RLP/ckf Enclosures C: NRC Region IV Plant Support Branch Secretary (2 sets)
Alan Wang, NRC Project Manager (w/o enclosures)
J. G. Kramer, NRC Senior Resident Inspector (w/o enclosures)
Emergency Planning Department (w/o enclosures) 74 )(C5 Employment with Equal Opportunity
FORM EP-1 Rev. 6 (04/29/99)
OMAHA PUBLIC POWER DISTRICT Confirmation of Transmittal for Emergency Planning Documentsfinformation D Radiological Emergency Response Plan (RERP)
Z Emergency Plan Implementing Procedures r-1 Emergency Planning i'_i Forms (EPF)
(EPIP)
D Emergency Planning Department Manual I0 Other Emergency Planning Document(sy (EPDM) Information Transmitted to:
Name: Document Control Desk COPy No: 165 Date:
Division of Reactor Safetv Coov No: 154 Attn: Senior Emergency Preparedness Inspector Division of Reactor Safety Copy No: 155 Attn: Senior Emergency Preparedness Inspector The following document(s) / Information are forwarded for your manual:
REMOVE SECTION INSERT SECTION EPIP Index page 1 of 3 Issued 05/28103 EPIP Index page 1of 3 Issued 06/19/03 EPIP TSC-1 R23 issued 10/29/02 EPIP TSC-1 R24 Issued 06/19/03 Summary of Changes:
EPIP TSC-1 was revised to add instructions to card In on accountability reader to ensure accountability.
Supervisor - Emergency Planning I hereby acknowledge receipt of the above documents/information and have Included them In my assigned manuals.
Signature: Date:_
Please sign above and return by 08115103 to: Beth Nagel Fort Calhoun Station, FC-2-1 Omaha Public Power District 444 South 16h Street Mall Omaha. NE 68102-2247 NOTE: If the document(s)rinformation contained Inthis transmittal is no longer requested or needed by the recipient, or has been transferred to another Individuals, please fill out the Information below.
o Document(s)/Information No Longer Requested/Needed O Document(s)/Information Transferred to:
Name: Mailing Address:
Fort Calhoun Station Emergency Plan IniplenMenting Procedure Index Page of 3 EPIP Document Document Title RevisionlDate EPIP-OSC-1 Emergency Classification R35 05-02-02 EPIP-OSC-2 Command and Control Position Actions/Notifications R42 05-28-03 EPIP-OSC-9 Emergency Team Briefings R7 12-09-99 EPIP-OSC-15 Communicator Actions R22 10-24-00a EPIP-OSC-21 Activation of the Operations Support Center R12 10-29-02a EPIP-TSC-1 Activation of the Technical Support Center R24 06-19-03 EPIP-TSC-2 Catastrophic Flooding Preparations R3 01-23-03 (R0 03-22-95) DELETED (05-09-95)
REINSTATED EPIP-TSC-8 Core Damage Assessment R14 01-19-01 EPIP-EOF-1 Activation of the Emergency Operations Facility R13 10-29-02 EPIP-EOF-3 Offsite Monitoring R18 11-12-02 EPIP-EOF-6 Dose Assessment R32 01-23-02a EPIP-EOF-7 Protective Action Guidelines R14 04-15-03 EPIP-EOF-10 Warehouse Personnel Decontamination Station R10 01-13-OOa Operation EPIP-EOF-1 1 Dosimetry Records, Exposure Extensions and R19 04-03-03 Habitability June 19,2003 8:51:33am
WP10 Fort Calhoun Station Unit No. 1 EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE
Title:
ACTIVATION OF THE TECHNICAL SUPPORT CENTER
"-' FC-68 Number: EC 32588 Reason for Change: Add instructions to card in on accountability reader, to ensure accountability.
Requestor: M. Reller Preparer: M. Reller ISSUED: 06-19-03 3:00 pm4 R24
FORT CALHOUN STATION EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE PAGE 1 OF 6 ACTIVATION OF THE TECHNICAL SUPPORT CENTER NON-SAFETY RELATED
- 1. PURPOSE 1.1 This procedure provides a checklist to provide guidance for activation and deactivation of the Technical Support Center (TSC).
- 2. REFERENCES/COMMITMENT DOCUMENTS None
- 3. DEFINITIONS 3.1 Activated - minimum staffing and basic setup requirements have been attained to allow the TSC to provide limited-support to the-Gontrol Reom.
3.2 Augmented - A facility is augmented when all augmenting and minimum staffing positions are filled.
- 4. PREREQUISITES None
- 5. PROCEDURE NOTE: The Site Director or TSC Director is responsible for completion of this procedure. They may assign this task to other members of the TSC staff.
5.1 Upon reporting to the TSC, activate the TSC using Attachment 6.1.
5.2 Upon event termination, deactivate the TSC per Attachment 6.2.
- 6. ATTACHMENTS 6.1 Checklist for Activation of the TSC 6.2 Checklist for Deactivation of the TSC 6.3 Activation/Deactivation of the TSC Air and Area Radiation Monitors 6.4 Operation of the TSC HVAC System R24
FORT CALHOUN STATION EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE PAGE 2 OF 6 Attachment 6.1 - Checklist For Activation of the TSC Page 1 of 2 NOTE: It is the goal of Omaha Public Power District (OPPD) to activate the TSC within one hour following declaration of an Alert or higher classification. In the event of adverse weather and/or other conditions that may limit or slow response, either manmade or natural, it is understood that staffing time may exceed this goal.
L:t l ' ' INITITIME
- 1. Contact the Control Room to determine if there is a toxic gas threat in the vicinity of Fort Calhoun Station.
1.1 If YES, secure the TSG HVAc system per Attachment 6.4 -
Step 3.
1.2 If NO, place the TSC HVAC System in the FILTERED MODE
- 'per Attachment 6.4; Step 1.
- 2. Verify the following minimum staffing positions are available.
- Protective Measures Coordinator
- Reactor Safety Coordinator l
- 3. Ensure that the volume buttons on both Gai-tronics are turned up. /
- 4. Using the Gai-Tronics, announce the following message: -
4.1 "Attention all personnel.. Attention all personnel. .. This is (Insert name and position) , all'Emergency Response personnel ensure that you have picked up your TLD, carded into the Accountability Card Reader and signed in on the Accountability Roster for your facility."
4.2 Repeat the message above.
l
- 5. Open all TSC room doors.
- 6. Post "NO EATING/DRINKING/SMOKING OR CHEWING" signs in the TSC Room 115 and near the entrance door.
- 7. In Room 118, unlock the aperture card file using the key from the key box, and turn on the aperture card reader/printer.
R24
FORT CALHOUN STATION EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE PAGE 3 OF 6 Attachment 6.1 (continued) Page 2 of 2 INIT/TIME
- 8. When Steps 2 through 7 are complete, make the following announcement on the TSC PA system:
This is (insert name and position) the TSC is activated.
Command and Control for the emergency is in the name of facility at this time. No eating, drinking, smoking. or chewing is allowed in the TSC until further notice. /
- 9. Notify the Control Room, OSC and EOF that the TSC is activated. /
- 10. Verify radiological habitability per EPIP-EOF-1 1. /
- 11. Initiate operation of the-TSC Air Monitor and Area Radiation Monitor-per Attachment 6.3. /
- 12. Within one hour of the initial emergency declaration, verify the following augmenting staff are present:
- Field Teams (2 Technicians, 2 Drivers)
- I&C/Electrical Systems Engineer
- 13. After one hour determine TSC positions are filled.
13.1 If any positions are not filled, based on the nature of the emergency determine if that position-is required.
13.2 Request assistance from. the TSC staff -in contacting additional staff. /
R24
FORT CALHOUN STATION EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE PAGE 4 OF 6 Attachment 6.2'- Checklist for Deactivation of the TSC Upon termination of emergency activities, the following actions should be completed to restore the TSC:
INITflTIME'
- Place emergency kits in the Emergency Gear Locker. /
- Properly restore all computer systems to their standby mode.
- Turn off the writeboard system. -
... . . ._/
- Deactivate the TSC Air Monitor and Area Radiation Monitor per Attachment 6.3. I
- Place the TSC HVAC Syster i the NORMAL MODE-per Attachment 6.4, Step 2.
- Remove all posted signs within the TSC -1
- Turn in all logs, paperwork, procedures, etc. to the Administrative I Logistics Coordinator."
,/.
- Turn off the aperture card reader/printer, and relock the aperture card file. " '
- Restock all Emergency Kits l
- Relock all room doors. ' ' -
.: ., " 1. - : . --. . I ,
'..I ; : ..
I ....
. . :- I - I I
R24
FORT CALHOUN STATION EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE - PAGE 5 OF 6 Attachment 6.3 - Activation/Deactivation of the TSC Air and Area Radiation Monitors L/) INIT/TIME
- 1. To activate the Air and Area Radiation Monitors, perform the following:
1.1 Enter Room 109 (the ERF computer system room).
1.2 Plug in and turn on the Area Radiation Monitor as necessary.
1.3 Plug in and turn on the PING Monitor as necessary.
1.4 Allow the PING to stabilize for several minutes, clearing the initial alarms as necessary.
1.5 Check both units on a routine basis during the emergency to ensure habitability is being maintained.
1.6 If either monitor alarms at any time during startup or operation, perform the following:
1.6.1 Reset the alarm by pressing the reset/acknowledge button.
1.6.2 If alarm resounds, read the affected meter and call a Radiation Protection Technician for further instructions.
- 2. To deactivate the Air and Area Radiation Monitors, perform the following:
2.1 Obtain permission from the Radiological Operations Coordinator to secure this equipment.
2.2 If permission is granted, unplug both units.
2.3 If permission is not granted, leave equipment operating and inform the Control Room.
R24
FORT CALHOUN STATION EPIP-TSC-1 EMERGENCY PLAN IMPLEMENTING PROCEDURE PAGE 6 OF 6 Attachment 6.4 - Operation of the TSC HVAC System Page 1 of 1 (ia INIT/TIME
- 1. Placing the TSC HVAC in the FILTERED MODE.
1.1 On panel Al-200A (in TSC Room 109) ensure the Air Handler, VA-1 07 is ON as indicated by the red light above the VA-1 07, TSC Ventilation Unit Fan StarttStop Pushbuttons. If VA-107 is not ON, start VA-107 with the START push button.
1.2 Ensure the VA-109, Charcoal Filter Fan Selector Switch, HCNA-1 09, is in AUTO.
1.3 Place the TSC Ventilation Filtered Air Mode Switch, SSNA-1 09 is in the ON position. /
- 2. Placing the TSC HVAC in the NORMAL MODE.
2.1 On panel Al-200A (in TSC Room 109), place the TSC Ventilation Filtered Air Mode Switch, SSNA-1 09 in OFF.
2.2 Verify VA-1 09, Charcoal Filter Fan Selector Switch, HCNA-109, is in AUTO and VA-107 in ON as indicated by red light above VA-1 07, TSC Ventilation Fan Unit Start/Stop Pushbuttons. I
- 3. Securing the TSC HVAC System.
3.1 On panel Al-200A (in TSC Room 109), ensure or place the TSC Ventilation Filtered Air Mode Switch, SSNA-1 09, in the OFF position.
3.2 Place the Air Handler, VA-1 07 in OFF by pushing the VA-1 07, TSC Ventilation Unit Fan Stop pushbutton AND verify the red light above the VA-1 07, TSC Ventilation Unit Fan Start/Stop pushbuttons is off. /
R24