L-MT-05-024, February 2005 Monthly Operating Report for Monticello Nuclear Generating Plant

From kanterella
Jump to navigation Jump to search
February 2005 Monthly Operating Report for Monticello Nuclear Generating Plant
ML050670160
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 03/04/2005
From: Thomas J. Palmisano
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-MT-05-024
Download: ML050670160 (4)


Text

Monticello Nuclear Generating Plant Operated by Nuclear Management Company, LLC 2807 West County Road 75

  • Monticello, Minnesota 55362-9637 March 4, 2005 L-MT-05-024 Technical Specification 6.7.A.3 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Monticello Nuclear Generating Plant Docket 50-263 License No. DPR-22 Monticello Monthly Operating Report In accordance with Technical Specification 6.7.A.3, attached is the Monthly Operating Report for February 2005 for the Monticello Nuclear Generating Plant. This letter makes no new commitments or changes to any existing commitments.

Thomas J. Palmisano Site Vice President, Monticello Nuclear Generating Plant Nuclear Management Company, LLC Enclosure cc:

Administrator, Region III, USNRC Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Telephone: 763-295-5151

  • Fax: 763-295-1454

ENCLOSURE MONTICELLO OPERATING DATA REPORT AND UNIT SHUTDOWNS FEBRUARY 2005 2 pages follow

DOCKET NO. 50-263 UNIT NAME Monticello DATE March 1, 2005 COMPLETED BY J. I. Helland TELEPHONE 763-295-1333 OPERATING DATA REPORT REPORTING PERIOD: February 2005

1. Design Electrical Rating (MWe-Net) 600.0
2. Maximum Dependable Capacity (MWe-Net) 578.1 MONTH YEAR TO DATE CUMULATIVE
3. Number of Hours the Reactor Was Critical 672.0 1,416.0 247,001.8
4. Number of Hours the Generator Was On Line 672.0 1,416.0 243,494.4
5. Unit Reserve Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWHe) 363,285 799,518 126,592,404

UNIT SHUTDOWNS DOCKET NO.

50-263 Monticello UNIT NAME DATE 03 05 COMPLETED BY J. I. Helland REPORTING PERIOD:

February 2005 TELEPHONE 763-295-1333 No.

(Year

- to -

date)

Date Type F:Forced S:Scheduled Duration (hours)

Reason (1)

Method of Shutting Down (2)

Cause/Corrective Actions Comments None 1

F 2

Reason:

Method:

A Equipment Failure (Explain) 1 Manual B

Maintenance or Test 2

Manual Scram C

Refueling 3

Automatic Trip/Scram D

Regulator Restriction 4

Continuation E

Operator Training & Licensing Examination e

5 Other (Explain)

Administrativ G

Operational Error (Explain)

H Other (Explain)

SUMMARY

The plant operated continuously with the following power reductions: one planned thermal power reduction and EOC22 coastdown continuation. The planned reduction had a minimum power value of ~75% with a duration of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> 30 minutes on the 19th/20th due to an MSIV Quarterly surveillance. EOC 22 Coastdown continued through the entire month.