L-MT-03-051, June 2003 Monthly Operating Report for Monticello

From kanterella
Jump to navigation Jump to search
June 2003 Monthly Operating Report for Monticello
ML032110366
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 07/11/2003
From: Denise Wilson
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-MT-03-051
Download: ML032110366 (4)


Text

Monticello Nuclear Generating Plant Comtted to NuearExce2 Operated by Nuclear Management Company, LLC L-MT-03-051 July 11, 2003 Technical Specification 6.7.A.3 US Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 MONTICELLO NUCLEAR GENERATING PLANT DOCKET 50-263 LICENSE No. DPR-22 MONTICELLO MONTHLY OPERATING REPORT FOR JUNE 2003 In accordance with Monticello Technical Specification 6.7.A.3, the report of operating statistics for Monticello Nuclear Generating Plant for the month of June is attached.

Please contact John Fields at 763-271-1663 if you require further information.

David L.Wilson Site Vice President Monticello Nuclear Generating Plant CC Regional Administrator - III, NRC NRR Project Manager, NRC Sr. Resident Inspector, NRC Minnesota Dept. of Commerce Attachment 2807 West County Road 75

Telephone: 763-295-5151

  • Fat 763-295-1454

ATTACHMENT I NUCLEAR MANAGEMENT COMPANY, LLC MONTICELLO NUCLEAR GENERATING PLANT DOCKET 50-263 MONTICELLO MONTHLY OPERATING REPORT FOR JUNE 2003 2 pages follow

Commiffed to Nuear Exce DOCKET NO. 50-263 UNIT NAME Monticello DATE July 2, 2003 COMPLETED BY J. I. Helland TELEPHONE 763-295-1333 OPERATING DATA REPORT REPORTING PERIOD: June 2003 MONTH YEAR TO DATE CUMULATIVE

1. Design Electrical Rating (MWe-Net) 600.0 600.0 600.0
2. Maximum Dependable Capacity (MWe-Net) 578.1 578.1 578.1
3. Number of Hours the Reactor Was Critical 674.1 3,613.8 232,455.5
4. Number of Hours the Generator Was On Line 656.4 3,552.7 228,971.5
5. Unit Reserve Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWHe) 369,107.1 2,032,763.6 118,198,306.1

UNIT SHUTDOWNS DOCKET NO. 50-263 It UNIT NAME Monticello DATE 07 03 COMPLETED BY J. I. Helland REPORTING PERIOD: June 2003 TELEPHONE 763-295-1333 No. Type Method of Cause/Corrective Actions (Year F:Forced Duration Reason Shutting Down

- to - Date S:Scheduled (hours) (1) (2) Comments d ate ) _ _ _ _ _ _ _ _ _ _ __ _ _ _ _

2 6/14 S 63.6 B 2 Shutdown to fix leaking safety relief valves and condenser air in-leakage.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Scram C Refueling 3 Automatic Trip/Scram D Regulator Restriction 4 Continuation E Operator Training & Licensing Examination 5 Other (Explain)

F Administrative G Operational Error (Explain)

H Other (Explain)

SUMMARY

The plant operated at essentially 100% power for the month of June except for one planned shutdown to fix leaking safety relief valves and to stop condenser air in-leakage. There were also some rod pattem adiustments. There were no Unplanned power reductions during the month of June.

There was one planned shutdown during June. The plant began shutting down on June 13 and was shutdown via a manual reactor scram on June 14.

The plant began starting up on June 16 and reached 100% power on June 17. There was one minor power loss during the month.

The power was reduced to the 96 - 98% range for a series of rod pattern adjustments over a roughly 15-hour time span on June 17/18. These were performed to bring the plant to an equilibrium post-startup rod pattem.