L-98-132, Forwards Response to NRC Administrative Ltr 98-03 Re Estimated Number of Licensing Actions Expected to Be Submitted in FY98 & Estimated Number of Licensing Actions Expected to Be Submitted in FY99
| ML20236L303 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 07/02/1998 |
| From: | Jain S DUQUESNE LIGHT CO. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| AL-98-03, AL-98-3, L-98-132, NUDOCS 9807100305 | |
| Download: ML20236L303 (2) | |
Text
_ - _ - - _ _ _
l
]
g Beaver Valley Power Station Shippingport, PA 15077-0004
,s'-
SUSHIL C. JAIN (412) 393 5512 j
Senior Vice President Fax (724) 643 8069 IIeN*$*o*ivision July 2, 1998 L-98-132 U. S. Nuclear Regulatory Commission Attention: Document Control Desk
. Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit No. I and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 NRC Administrative Letter 98-03 Response This letter forwards the Beaver Valley Power Station response to Administrative Letter 98-03 request for information regarding (1) a simple numerical estitnate of the number of new licensing. ections expected to be submitted in the remainder of Fiscal Year (FY) 1998 and (2) o estimate of the number of lic< nsing actions expected to be submitted in FY 1999. As requested those licensing actions expected to generate complex reviews, such as power uprate requests, license renewal requests, and dry cask storage applications are identified by a brief title.
The attached enclosure provides a restatement of the NRC information request followed by the Beaver Valley Power Station response.
[~
If you have any questions regarding this information, please contact Mr. S. Hobbs at (412) 393-5203.
Sincerely, g
&Nfty Sushil C. Jain I
c:
Mr. D. S. Brinkman, Sr. Project Manager Mr. D. M. Kern, Sr. Resident Inspector Mr. H. J. Miller, NRC Region I Administrator Mr. M. L. Boyle, U.S. Nuclear Regulatory Commission DEL 1VERING QU ALITY l
9007100305 900702 ENEIGV PDR ADOCK 05000334 P
PM i
- .?
ENCLOSURE p
l Beaver Vallev Power Station Response to NRC Administrative Letter 98-03 i
- Licensees were requested to provide:
l (1) a simple numerical estimate of the licensing actions expected to be l
submitted in the remainder of Fiscal Year 1998.
Response
Beaver Valley Power Station expects to submit approximately 12 licensing actions (i.e., License Amendment Requests, etc.) in the remainder of Fiscal Year 1998.
(2) an estimate of the number oflicensing actions expected to be submitted in Fiscal Year 1999.
L
Response
Beaver Valley Power Station expects to submit approximately 14 licensing actions (i.e., License Amendment Requests, etc.) in 1999.
(3) identify by brief title those licensing actions that are expected to generate complex reviews.
Response
Beaver Valley Power Station does not expect to submit any License Amendment Requests that will generate complex reviews during the remainder of Fiscal Year 1998 or in Fiscal Year 1999.