O r.- @ rotsoo enEDISDN L80-1032 July 8, 1980 PILE: RR 2 (P-6-80-0C; Docket No. 50-346 License No. NPF-3 Mr. Victor Stello, Jr., Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Dear Mr. Stello:
Monthly Operating Report, June, 1980 Davis-Besse Nuclear Power Station Unit 1 Enclosed find ten (10) copies of the Monthly Operating Report for Davis-Besse Nuclear Power Station Unit 1, for the month of June, 1980.
Also enclosed is a 1.st of the monthly values of the unit capacity factors which could not be determined in the past, for November, 1977 through January, 1980.
Yours truly,
%oW Terry D. Murray Station Superintendent Davis-Besse Nuclear Power Station TDM/1jk Enclosures cc:
Mr. James G. Keppler Regional Director, Region III Enc 1:
1 Mr. Norman Haller, Director Office of Management Program Analysis Encl:
2 THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO. OHfu 43652 80071403/p p