L-78-122, Refueling Outage Schedule
| ML18114A214 | |
| Person / Time | |
|---|---|
| Site: | Saint Lucie |
| Issue date: | 04/05/1978 |
| From: | Robert E. Uhrig Florida Power & Light Co |
| To: | Reid R Office of Nuclear Reactor Regulation |
| References | |
| L-78-122 | |
| Download: ML18114A214 (3) | |
Text
REGULATORY INFORMATION DISTRIBUTIO DISTRIBUTION FOR INCOMING MATERIAL SYSTEM
< RIDS) 50-335 REC:
REID R
W NRC ORG:
UHRIG R E FL PWR h LIGHT l30CDATE: 04/05/78 DATE RCVD: 04/06/78 DOCTYPE:
LETTER NOTARIZED:
NO
SUBJECT:
FURNISHING INFO RE APPLICANT"8 PRESENT SCHEDULE REFUELING OUTAGE FOR UNIT i.
PLANT NAME: ST LUCIE Qi COPIES'ECEIVED LTR 3 ENCL 0 FOR COMPLETION OF THE C
REVIEWER INITIAL:
XJM DISTRIBUTOR INITIAL:
++++4~+4H~+++++++++ DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS GENERAL DISTRIBUTION FOR AFTER ISSUANCE OF OPERATING LICENSE.
<DISTRIBUTION CODE AOOi)
FOR ACTION:
INTERNAL:
BR CHIEF R
Y<7)
REG FILE++LTR ONLY(1)
HANAUER44LTR ONLY(i)
EISENHUT++LTR ONLY(i >
BAER+~LTR ONLY<i)
GRIMES++LTR ONLY(i >
J.
MCGOUGH4~LTR ONLY(i)
NRC PDR++LTR ONLY<i)
OELD~+LTR ONLY(i>
CHECK++LTR ONLY<i)
SHAO>+LTR ONLY(i>
BUTLER44LTR ONLY<i)
J COLLINS+>LTR ONLY(i >
EXTERNAL:
LPDR S FT PIERCEi FL++LTR ONLY(i>
TIC4+LTR ONLY<i)
NSIC++LTR ONLY(i>
ACRS CAT 8+4LTR ONLY<i6)
DISTRIBUTION:
LTR 40 ENCL 0 SIZE:
iP THE END CONTROL NBR:
780970028 pp
il I
FLORIDAPOWER & LIGHTCOMPANY Office of Nuclear Reactor Regulation Attention:
Mr. Robert W. Reid, Chief Operating Reactors Branch No.
4 Division of Operating Reactors U.
S. Nuclear Regulatory Commission Washington, D.
C.
20555
Dear Mr. Reid:
April 5 L-78-12
<<n a
~e Kl R
CO 1978 2
, Ql g
gl CQI j CO~
e M
~3 Re:
St. Lucie Unit No. 1, Docket No.
50-335 Refuelin Outa e Schedule l
As you know, St. Lucie Unit No.
1 is, presently undergoing its first refueling outage.
The purpose of this letter is to advise you of our present schedule for completion of the outage.
The expected completion times for the activities on the present schedule have been developed on ithe basis of what is known to FPL.
This schedule shows that the unit would be ready to begin initial criticality on May 15, 1978.
Because of some "critical path" work to be performed on the secondary side of the unit, the outage would not be completed, and power operation is therefore not scheduled to begin, until May 25, 1978.
There are a number of activities which have the potential for delay and which could thereby extend those dates stated above.
- However, the extent of any such delay is unknown to us at this time.
We therefore plan to keep you apprised of any changes to the schedule on a weekly basis and any sig-nificant developments which. could impact the schedule as they occurs Very truly yours, Robert E. Uhrig Vice President REU:LLL:sl cc:
Mr. Peter B. Erickson Mr. J.
P. O'Reilly, Region II Harold F. Reis, Esquire Oops q/O P EOPLE... SERVING P EOP LE