Additional Information Regarding License Amendment Request for Transition to 10 CFR 50.48(c) - NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)
ML15140A220
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 05/12/2015
From: Costanzo C
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML15140A209 List:
References
L-2015-145, NFPA-805
Download: ML15140A220 (2)


Text

Enclosures 1 and 2 contain Security Related Information - Withhold Under 10 CFR 2.390. Upon removal of Enclosures 1 and 2, this document is decontrolled.

W May 12, 2015 FPL.

L-2015-145 10 CFR 50.90 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001 Re:

St. Lucie Units I and 2 Docket Nos. 50-335 and 50-389 Additional Information Regarding License Amendment Request for Transition to 10 CFR 50.48(c) - NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)

References:

1. FPL letter L-2013-099 dated March 22, 2013: Transition to 10 CFR 50.48(c) -NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)
2. FPL letter L-2014-056 dated February 24, 2014: 60-Day Response to Request for Additional Information Regarding License Amendment Request for Transition to 10 CFR 50.48(c) - NFPA 805
3. FPL letter L-2014-083 dated March 25, 2014: 90-Day Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
4. FPL letter L-2014-109 dated April 25, 2014: 120-Day Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
5. FPL letter L-2014-203 dated July 14, 2014: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
6. FPL letter L-2014-270 dated August 27, 2014: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
7. FPL letter L-2014-289 dated September 10, 2014: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
8. FPL letter L-2014-314 dated October 10, 2014: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
9. FPL letter L-2015-068 dated March 10, 2015: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
10. FPL letter L-2015-104 dated April 1, 2015: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805
11. FPL letter L-2015-134 dated April 20, 2015: Response to Request for Additional Information Regarding LAR for Transition to 10 CFR 50.48(c) - NFPA 805 Florida Power & Light Company 6501 S. Ocean Drive, Jensen Beach, FL 34957

L-2015-145 Page 2 of 2 Per Reference I above, Florida Power and Light Company (FPL) requested an amendment to the Renewed Facility Operating License (RFOL) for St. Lucie Units I and 2. The License Amendment Request (LAR) will enable FPL to adopt a new fire protection licensing basis which complies with the requirements in 10 CFR 50.48(a) and (c) and the guidance in Revision 1 of Regulatory Guide (RG) 1.205.

Per References 2 through 11, FPL responded to specific NRC requests for additional information to clarify aspects of the LAR submittal. Enclosure 1 to this letter provides supplemental clarification to information previously provided per References 1 through 11. Enclosure 2 to this letter provides the LAR Attachment S mark-up associated with the changes described in.

The information provided in this submittal does not impact the 10 CFR 50.92 evaluation of"No Significant Hazards Consideration" previously provided in FPL letter L-2013-099 (Reference 1).

This letter makes new commitments and changes existing commitments.

FPL requests that the enclosures to this letter, which contains security-related information, be withheld from public disclosure in accordance with 10 CFR 2.390. Upon removal of Enclosures 1 and 2, this document is decontrolled.

Should you have any questions regarding this application, please contact Mr. Eric Katzman, Licensing Manager, at 772-467-7734.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on May/IZ, 2015.

Reectfully submitted, Christopher R. Costanzo Site Vice President St. Lucie Plant CRC/rcs

Enclosures:

1. St. Lucie Units I and 2 NFPA 805 LAR Additional Information -

Withheld from Public Disclosure

2. St. Lucie Units 1 and 2 NFPA 805 LAR Attachment S Mark-Up -

Withheld from Public Disclosure cc:

Ms. Cindy Becker, Florida Department of Health USNRC Regional Administrator, Region II USNRC Senior Resident Inspector, St. Lucie Units I and 2