0 FPLEnergy AN FPL GnouP COMPANY SEP 2 8.2007 L-2007-156 Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: Point Beach Nuclear Plant, Units 1 and 2 Docket Nos. 50-266, 50-301 Transfer of Ownership of Point Beach Nuclear Plant on September 28, 2007 The purpose of this letter is to inform you that a change in ownership of Point Beach Nuclear Plant, Units 1 and 2 has occurred. The Point Beach Nuclear Plant was formally owned by Wisconsin Electric Power Company (WEPCO) and operated by Nuclear Management Company (NMC) under Facility Operating License Nos. DRP-24 and DPR-

27. The transfer of ownership of Point Beach Nuclear Plant to the new owner and operator, FPL Energy Point Beach, LLC, was effective on September 28, 2007, at 12:01 AM CDT.

Should you have any questions regarding this matter, please contact Mitchell S. Ross, Vice President and Associate General Counsel, at 561-691-7126.

Sincerely yours, J.A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer FPL Energy Point Beach, LLC Cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Director, Spent Fuel Project Office PO Box 14000 o Juno Beach, Florida 33408.0420 e (561) 691-7171 Fax: (561). 691-7177