L-2002-133, June 2002 Monthly Operating Report for St. Lucie, Units 1 & 2
| ML021960059 | |
| Person / Time | |
|---|---|
| Site: | Saint Lucie |
| Issue date: | 07/11/2002 |
| From: | Jernigan D Florida Power & Light Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, L-2002-133, TS 6.9.1.6 | |
| Download: ML021960059 (7) | |
Text
0FPL Florida Power & Light Company, 6501 South Ocean Drive, Jensen Beach, FL 34957 July 11, 2002 L-2002-133 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: St. Lucie Units I and 2 Docket Nos. 50-335 and 50-389 Monthly Operatinq Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the June 2002 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.
Please co act us should there be any questions regarding this information.
Ve~ry t yours, Donald E. Jer an Vice President St. Lucie Plant DEJ/spt Attachments an FPL Group company
DOCKET NO.: 50-335 UNIT NAME: St. Lucie Unit 1 DATE: July 1, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: June 2002
- 1. Design Electrical Rating (Mwe-Net) 830
- 2. Maximum Dependable Capacity (Mwe-Net). 839 MONTH -YTD CUMULATIVE
- 3. Number of Hours Reactor Critical 720 4343 180943.5
- 4. Number of Hours Generator On Line 720 4343 179130
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy (MWH). 611470 3717209 146393948
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: July 1, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Unit 1 operated at essentially full power through the entire month of June.
In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: July 1, 2002 COMPLETED BY: J.A.Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Down Action to Reactor 3 Prevent Recurrence Unit I operated at essentially full power for the entire month of June.
1 3 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)
G - Operational Error (Explain)
H - Other (Explain) 091587 PPL
DOCKET NO.: 50-389 UNIT NAME: St. Lucie Unit 2 DATE: July 1, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: June 2002
- 1. Design Electrical Rating (Mwe-Net). 830
- 2. Maximum Dependable Capacity (Mwe-Net)_ 839 MONTH -YTD CUMULATIVE
- 3. Number of Hours Reactor Critical 720 4328.4 144341.6
- 4. Number of Hours Generator On Line 720 4325.6 142583.3
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy (MWH) 609805 3685563 117416209
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: July 1, 2002 COMPLETED BY: J. A.Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Unit 2 operated at essentially full power through the entire month of June.
In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: July 1, 2002 COMPLETED BY: J.A.Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Down Action to Reactor 3 Prevent Recurrence Unit 2 operated at essentially full power for the entire month of June.
1 2 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)
G - Operational Error (Explain)
H - Other (Explain) 091587 PPL
Text
0FPL Florida Power & Light Company, 6501 South Ocean Drive, Jensen Beach, FL 34957 July 11, 2002 L-2002-133 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: St. Lucie Units I and 2 Docket Nos. 50-335 and 50-389 Monthly Operatinq Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the June 2002 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.
Please co act us should there be any questions regarding this information.
Ve~ry t yours, Donald E. Jer an Vice President St. Lucie Plant DEJ/spt Attachments an FPL Group company
DOCKET NO.: 50-335 UNIT NAME: St. Lucie Unit 1 DATE: July 1, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: June 2002
- 1. Design Electrical Rating (Mwe-Net) 830
- 2. Maximum Dependable Capacity (Mwe-Net). 839 MONTH -YTD CUMULATIVE
- 3. Number of Hours Reactor Critical 720 4343 180943.5
- 4. Number of Hours Generator On Line 720 4343 179130
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy (MWH). 611470 3717209 146393948
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: July 1, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Unit 1 operated at essentially full power through the entire month of June.
In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: July 1, 2002 COMPLETED BY: J.A.Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Down Action to Reactor 3 Prevent Recurrence Unit I operated at essentially full power for the entire month of June.
1 3 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)
G - Operational Error (Explain)
H - Other (Explain) 091587 PPL
DOCKET NO.: 50-389 UNIT NAME: St. Lucie Unit 2 DATE: July 1, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: June 2002
- 1. Design Electrical Rating (Mwe-Net). 830
- 2. Maximum Dependable Capacity (Mwe-Net)_ 839 MONTH -YTD CUMULATIVE
- 3. Number of Hours Reactor Critical 720 4328.4 144341.6
- 4. Number of Hours Generator On Line 720 4325.6 142583.3
- 5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 6. Net Electrical Energy (MWH) 609805 3685563 117416209
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: July 1, 2002 COMPLETED BY: J. A.Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Unit 2 operated at essentially full power through the entire month of June.
In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: July 1, 2002 COMPLETED BY: J.A.Rogers TELEPHONE: (772) 467-7296 REPORT MONTH June 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Down Action to Reactor 3 Prevent Recurrence Unit 2 operated at essentially full power for the entire month of June.
1 2 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)
G - Operational Error (Explain)
H - Other (Explain) 091587 PPL