FENOC Peter P. Sena III 724-682-5234 Site Vice President FAX:. 724-643-8069 December 16, 2008 L-08-230 10 CFR 50.59(d)(2)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Beaver Valley Power Station, Unit No. 2 Docket No. 50-412, License No. NPF-73 Report of Facility Changqes, Tests and Experiments In accordance with 10 CFR 50.59(d)(2), the Report of Facility Changes, Tests, and Experiments for the Beaver Valley Power Station Unit No. 2 is provided. There were no evaluations completed pursuant to 10 CFR 50.59 during the period of November 13, 2006 to May 22, 2008.
There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager -
Fleet Licensing, at (330) 761-6071.
ely PeterP Senal 1 cc:
NRC Region I Administrator NRC Resident Inspector NRR Project Manager Director BRP/DEP Site BRP/DEP Representative