L-04-137, October, 2004 Monthly Operating Report for Beaver Valley Power Station
| ML043240123 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 11/08/2004 |
| From: | Pearce L FirstEnergy Nuclear Operating Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, L-04-137 | |
| Download: ML043240123 (3) | |
Text
FENO C Pt~ y~drO eahgC~pny -
Beaver Valley Power Station P. 0. Box 4 Shippingport, PA 15077 L-04-137 November 8, 2004 Beaver Valley Power Station Unit I - Docket No. 50-334, License No. DPR-66
-Unit Dockct No. 50-412, License No. NPF-73 Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In accordance with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report", -and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit I and Unit 2 for the month of October, 2004. This information has also been inputted into the INPO Consolidated Data Entry (CDE) System. No regulatory commitments are contained in this submittal.
Respectfully, Vice-President BVPS DTJ/cmg Enclosures cc: NRC Regional Office . , , . -.- - I . - I . 1, . 1, King of Pruissia, PA ; I . . , .!, . , , 1, -- ; - % . -:, ", , ,! ': ., - " , . - - --, ., . . - . - 1,,.:,
. . . I . . - I . , I .
f..
O
- f OPERATING DATA REPORT DOCKET NO. 50-334 UNIT NAME Beaver Valley 1 DATE November 01, 2004 COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIO October 2004
- 1. Design Electrical Rating 835.00
- 2. Maximum Dependable Capacity (MWe-Net) 821.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 408.37 6,983.37 175,010.64
- 4. Number of Hours Generator On-line 408.02 6,983.02 172,480.84
55.--Reserve-Shutdown Hours------ - - - - 0.00- - - 0.00 - - 0.00
- 6. Net Electrical Energy Generated (MWHrs) 327,890.00 5,791,750.00 130,433,122.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments 1 10/18/2004 S 337.0 C 1 The Unit was shutdown for its planned 16th refueling outage on 10/18/04 at 0001 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
I Reason: 2 A Equipment Failure (Explain) Method:
B Maintenance or Test 1 Manual C Refueling 2 Manual Trip/Scram D Regulatory Restriction 3 Automatic Trip/Scram E Operator Training & License Examination 4 Continuation F Administration 5 Other (Explain)
G Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit began the report period operating at a nominal value of 100% output. On 10/16/04 at 1926 hours0.0223 days <br />0.535 hours <br />0.00318 weeks <br />7.32843e-4 months <br />, the Unit began a planned reduction to less than 50%'output in order to support Main Steam Safety Valve testing prior to beginning it's 16th refueling outage. An output of approximately 44% was achieved at 0412 hours0.00477 days <br />0.114 hours <br />6.812169e-4 weeks <br />1.56766e-4 months <br /> on 10/17/04. Following satisfactory completion of Main Steam Safety Valve testing, the Unit began to shutdown for it's planned 16th refueling outage at 1933 hours0.0224 days <br />0.537 hours <br />0.0032 weeks <br />7.355065e-4 months <br /> on 10/17/04. The Unit was taken off-line at 0001 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> on 10/18/04 to begin it's 16th refueling outage. Mode 2 was entered at 0020 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br />, Mode 3 was entered at 0022 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />, Mode 4 was entered at 0333 hours0.00385 days <br />0.0925 hours <br />5.505952e-4 weeks <br />1.267065e-4 months <br />, and Mode 5 (cold shutdown) was entered at 0718 hours0.00831 days <br />0.199 hours <br />0.00119 weeks <br />2.73199e-4 months <br /> on 10/18/04. The Unit remained shutdown in Mode 5 until 0445 hours0.00515 days <br />0.124 hours <br />7.357804e-4 weeks <br />1.693225e-4 months <br /> on 10/22/04, when Mode 6 was entered for refueling. The Unit remained shutdown in Mode 6 for the remainder of the report period.
Page 1 of 1
r OPERATING DATA REPORT DOCKET NO. 50-412 UNIT NAME Beaver Valley 2 DATE November 01 2004 COMPLETED BY David T. Jones . I TELEPHONE 724-682-4962 REPORTING PERIOD: October 2004
- 1. Design Electrical Rating 836.00
- 2. Maximum Dependable Capacity (MWe-Net) 831.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 745.00 7,320.00 124,928.48
- 4. Number of Hours Generator On-line 745.00 7,320.00 124,184.38
- -- 5.--Reserve Shutdown Hours ----- -0.00 - - - - - 0.00 97,8 12.00 _ _
- 6. Net Electrical Energy Generated (MWHrs) 624,297.00 6,077,014.00 97,896,412.00 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments NONE.
1 2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G - Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire report period.
Page 1 of 1
Text
FENO C Pt~ y~drO eahgC~pny -
Beaver Valley Power Station P. 0. Box 4 Shippingport, PA 15077 L-04-137 November 8, 2004 Beaver Valley Power Station Unit I - Docket No. 50-334, License No. DPR-66
-Unit Dockct No. 50-412, License No. NPF-73 Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In accordance with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report", -and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit I and Unit 2 for the month of October, 2004. This information has also been inputted into the INPO Consolidated Data Entry (CDE) System. No regulatory commitments are contained in this submittal.
Respectfully, Vice-President BVPS DTJ/cmg Enclosures cc: NRC Regional Office . , , . -.- - I . - I . 1, . 1, King of Pruissia, PA ; I . . , .!, . , , 1, -- ; - % . -:, ", , ,! ': ., - " , . - - --, ., . . - . - 1,,.:,
. . . I . . - I . , I .
f..
O
- f OPERATING DATA REPORT DOCKET NO. 50-334 UNIT NAME Beaver Valley 1 DATE November 01, 2004 COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIO October 2004
- 1. Design Electrical Rating 835.00
- 2. Maximum Dependable Capacity (MWe-Net) 821.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 408.37 6,983.37 175,010.64
- 4. Number of Hours Generator On-line 408.02 6,983.02 172,480.84
55.--Reserve-Shutdown Hours------ - - - - 0.00- - - 0.00 - - 0.00
- 6. Net Electrical Energy Generated (MWHrs) 327,890.00 5,791,750.00 130,433,122.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments 1 10/18/2004 S 337.0 C 1 The Unit was shutdown for its planned 16th refueling outage on 10/18/04 at 0001 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
I Reason: 2 A Equipment Failure (Explain) Method:
B Maintenance or Test 1 Manual C Refueling 2 Manual Trip/Scram D Regulatory Restriction 3 Automatic Trip/Scram E Operator Training & License Examination 4 Continuation F Administration 5 Other (Explain)
G Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit began the report period operating at a nominal value of 100% output. On 10/16/04 at 1926 hours0.0223 days <br />0.535 hours <br />0.00318 weeks <br />7.32843e-4 months <br />, the Unit began a planned reduction to less than 50%'output in order to support Main Steam Safety Valve testing prior to beginning it's 16th refueling outage. An output of approximately 44% was achieved at 0412 hours0.00477 days <br />0.114 hours <br />6.812169e-4 weeks <br />1.56766e-4 months <br /> on 10/17/04. Following satisfactory completion of Main Steam Safety Valve testing, the Unit began to shutdown for it's planned 16th refueling outage at 1933 hours0.0224 days <br />0.537 hours <br />0.0032 weeks <br />7.355065e-4 months <br /> on 10/17/04. The Unit was taken off-line at 0001 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> on 10/18/04 to begin it's 16th refueling outage. Mode 2 was entered at 0020 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br />, Mode 3 was entered at 0022 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />, Mode 4 was entered at 0333 hours0.00385 days <br />0.0925 hours <br />5.505952e-4 weeks <br />1.267065e-4 months <br />, and Mode 5 (cold shutdown) was entered at 0718 hours0.00831 days <br />0.199 hours <br />0.00119 weeks <br />2.73199e-4 months <br /> on 10/18/04. The Unit remained shutdown in Mode 5 until 0445 hours0.00515 days <br />0.124 hours <br />7.357804e-4 weeks <br />1.693225e-4 months <br /> on 10/22/04, when Mode 6 was entered for refueling. The Unit remained shutdown in Mode 6 for the remainder of the report period.
Page 1 of 1
r OPERATING DATA REPORT DOCKET NO. 50-412 UNIT NAME Beaver Valley 2 DATE November 01 2004 COMPLETED BY David T. Jones . I TELEPHONE 724-682-4962 REPORTING PERIOD: October 2004
- 1. Design Electrical Rating 836.00
- 2. Maximum Dependable Capacity (MWe-Net) 831.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 745.00 7,320.00 124,928.48
- 4. Number of Hours Generator On-line 745.00 7,320.00 124,184.38
- -- 5.--Reserve Shutdown Hours ----- -0.00 - - - - - 0.00 97,8 12.00 _ _
- 6. Net Electrical Energy Generated (MWHrs) 624,297.00 6,077,014.00 97,896,412.00 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments NONE.
1 2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G - Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire report period.