JPN-94-038, Forwards Application for Amends to License DPR-59,proposing Ts,To Revising Primary Containment Atomsphere Monitoring Requirements
| ML20071P596 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 08/04/1994 |
| From: | Josiger W POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| Shared Package | |
| ML20071P601 | List: |
| References | |
| JPN-94-038, JPN-94-38, NUDOCS 9408090434 | |
| Download: ML20071P596 (2) | |
Text
'
123 Main Street White Plains, New York 10601 l
Q14 6816200 l
l l
- > NewYorkPower 4# Authority August 4,1994 JPN-94-038 U.S. Nuclear Regulatory Commission j
ATTN: Document Control Desk Mail Station P1-137 Washington, DC 20555 l
l
Subject:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Proposed Changes to the Technical Specifications Primary Containment Atmosohere Monitorina (JPTS-93-010)
Reference:
1.
NRC NUREG-1433, " Standard Technical Specifications General Electric Plants BWR/4,"
Revision 0, dated September 1992.
Dear Sir:
This application for an amendment to the James A. FitzPatrick Technical Specifications proposes to revise the primary containment atmosphere monitoring requirements. The proposed changes add an action statement to Note F of Table 3.2-8,
" Accident Monitoring Instrumentation,"in place of the existing reference to 3.7.A.9.
Specification 3.7.A.9 is deleted since the monitoring requirements will be included in Table 3.2-8. In addition, the proposed changes revise Specification 3.7.A.6 to adopt the inerting/de-inerting requirements of the Standard Technical Specifications (STS)
(Reference 1) which require inerting to less than four percent oxygen concentration within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of exceeding 15% rated thermal power and allow de-inerting 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to reducing thermal power to less than 15% of rated before a plant shutdown. Similar changes are also proposed to the drywell to torus differential pressure requirements.
Other administrative changes are proposed to Tables 3.2-8, " Accident Monitoring Instrumentation," and 4.2-8, " Minimum Test and Calibration Frequency for Accident Monitoring Instrumentation," which will improve the overall quality of the Technical Specifications.
The signed original of the Application for Amendment to the Technical Specifications is enclosed for filing. Attachments I,11, and lit to this application contain the proposed changes to the Technical Specifications, the associated Safety Evaluation, and a mark-up of the current Technical Specifications pages.
In accordance with 10 CFR 50.91, a copy of this application and the associated attachments are being provided to the designated New York State official.
re e a h
V U U w., Li 9408090434 940B04 (0 (
PDR ADOCK 0500 3
g P
)
l l-l If you have any questions, please contact Mr. J. A. Gray, Jr.
I 1
Very truly yours, A
iam A. Jo iger j
Acting Exec ive Vice President Nuclear G eration i
i l
cc:
Regional Administrator U.S. Nuclear Regulatory Commission 475 Allendale Road l
King of Prussia, PA 19406 Office of the Resident inspector U.S. Nuclear Regulatory Commission l
P. O. Box 136 i
Lycoming, NY 13093 Mr. John E. Menning Project Directorate 1-1 Division of Reactor Projects - t/II U.S. Nuclear Regulatory Commission Mail Stop 14 B2 Washington, DC 20555 i
Ms. Donna Ross New York State Energy Office 2 Empire State Plaza 16* Floor Albany, NY 12223