JPN-83-102, Informs of Delayed Installation of Mod to post-accident Sampling Sys,Per NUREG-0737,Item II.B.3.2,due to Postponed Equipment Delivery.Delay Not in Violation of 830314 Confirmatory Order
| ML20079M835 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 12/29/1983 |
| From: | Bayne J POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK |
| To: | Vassallo D Office of Nuclear Reactor Regulation |
| References | |
| RTR-NUREG-0737, TASK-2.B.3, TASK-TM JPN-83-102, NUDOCS 8401270440 | |
| Download: ML20079M835 (2) | |
Text
123 Main street g,
e, White Plains, New York 10601 914 681.02CD MbkbWer se"c"e't!T."riemoee, tv Authority December 29, 1983 JPN-83-102 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Attention:
Mr. Domenic B. Vassallo, Chief Operating Reactor Branch No. 2 Division of Licensing
Subject:
James A.
FitzPatrick Nuclear Power Plant Docket No. 50-333 NUREG-0737 II.B.3.2 Post-Accident Sampling System
References:
1.
PASNY letter, J.P. Bayne to D.B.
- Vassallo, dated December 23, 1982 (JPN-82-91).
2.
NRC letter, D.B.
Vassallo to L.W.
- Sinclair, dated March 14, 1983.
3.
NYPA letter, J.P.
Bayne to D.B.
- Vassallo, dated August 5, 1983 (JPN-83-72).
Dear Sir:
Reference 1 discussed NUREG-0737 Item II.B.3.2 - Post-Accident Sampling System (PASS), and scheduled completion of the mod-l ification by the end of the Reload 5/ Cycle 6 refueling outage.
Reference 2 transmitted the Commission's Order confirming that schedule.
Reference 3 reaffirmed that a system had been purchased and was being installed.
Reference 3 also discussed the problems en-countered in the dissolved gas portion or the system.
These problems were addressed by the BWR Owners' Group PASS Sub-committee, and a modification to improve the dissolved gas sampling was developed.
Based on the Owners' Group delivery schedule, the Authority anticipated that the corrective modifi-cation would be installed by December 31, 1983.
8401270440 831229 DR ADOCK 05000333 PDR A04 uj,c,
e h
.w The Authority has recently been informed that delivery has been postponed until 1984.
This delay makes it necessary for us to reschedule installation until after delivery.
It is our. understanding that the Authority.will not be considered in violation of the Confirmatory Order due to this delay.
If you have any questions regarding this matter, please contact Mr. J. A.
Gray, Jr. of my staff.
Very truly yours,
' (/
'~)
f r' ~. '-)P.n Bdyne"f'.
(
J
' ' Executive Vice President Nuclear Generation cc:
Resident Inspector U.S. Nuclear Regulatory Commission P.O.
Box 136 Lycoming, NY 13093