Other: JAFP-15-0027, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-15-0105, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-16-0027, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049), JAFP-16-0028, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-16-0030, Request to Defer Indefinitely Onsite Audit Visit for Compliance with Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order Modifying Licenses with Regard, JAFP-16-0060, Extension to Commitments Made in Response to March 12, 2012, Information Request Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3, Emergency Communication and Staffing Assessments, JAFP-16-0139, Seventh Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, JAFP-16-0140, Seventh Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, JAFP-17-0017, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events, JAFP-17-0018, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-17-0084, Report of Full Compliance with March 12, 2012, Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), ML16060A260, ML16173A342, ML16252A387, ML16343A011
|
MONTHYEARJAFP-15-0027, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other JAFP-15-0105, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other JAFP-16-0025, Transmittal of Emergency Plan Updates2016-02-23023 February 2016 Transmittal of Emergency Plan Updates Project stage: Request JAFP-16-0030, Request to Defer Indefinitely Onsite Audit Visit for Compliance with Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order Modifying Licenses with Regard2016-02-23023 February 2016 Request to Defer Indefinitely Onsite Audit Visit for Compliance with Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order Modifying Licenses with Regard Project stage: Other JAFP-16-0027, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049) Project stage: Other JAFP-16-0028, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML16060A2602016-03-0202 March 2016 Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other JAFP-16-0045, Certification of Permanent Cessation of Power Operations2016-03-16016 March 2016 Certification of Permanent Cessation of Power Operations Project stage: Request JAFP-16-0061, Request for Relaxation of March 12, 2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool Instrumentation2016-04-14014 April 2016 Request for Relaxation of March 12, 2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool Instrumentation Project stage: Request JAFP-16-0060, Extension to Commitments Made in Response to March 12, 2012, Information Request Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3, Emergency Communication and Staffing Assessments2016-04-14014 April 2016 Extension to Commitments Made in Response to March 12, 2012, Information Request Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3, Emergency Communication and Staffing Assessments Project stage: Other JAFP-16-0096, Supporting Information for Request for Relaxation of March 12, 2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool2016-06-16016 June 2016 Supporting Information for Request for Relaxation of March 12, 2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool Project stage: Request JAFP-16-0139, Seventh Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-25025 August 2016 Seventh Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other JAFP-16-0140, Seventh Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2016-08-25025 August 2016 Seventh Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other JAFP-16-0147, Request for Extension to Comply with 03/12/2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Reliable Spent Fuel Pool Instrumentation2016-09-0808 September 2016 Request for Extension to Comply with 03/12/2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Reliable Spent Fuel Pool Instrumentation Project stage: Request ML16252A3872016-09-27027 September 2016 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML16173A3422016-12-0202 December 2016 Relaxation of the Schedule Requirements for Order EA-12-049 and Order EA-12-051 Project stage: Other ML16343A0112016-12-14014 December 2016 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other JAFP-17-0017, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events2017-02-28028 February 2017 Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events Project stage: Other JAFP-17-0018, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2017-02-28028 February 2017 Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other 05000333/LER-2017-002, Regarding Residual Heat Removal to Reactor Water Recirculation Loop a Weld Flaw Indication2017-03-22022 March 2017 Regarding Residual Heat Removal to Reactor Water Recirculation Loop a Weld Flaw Indication Project stage: Request ML17104A0122017-04-10010 April 2017 Submittal of 2017 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Project stage: Request JAFP-17-0084, Report of Full Compliance with March 12, 2012, Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2017-08-29029 August 2017 Report of Full Compliance with March 12, 2012, Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML17342A0062017-12-18018 December 2017 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Approval 2016-04-14
[Table View] |
Text
~ Entergy JAFP-16-0045 March 16, 2016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A. FitzPatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315-342-3840 Brian R. Sullivan Site Vice President - JAF 10 CFR 50.82
Subject:
Certification of Permanent Cessation of Power Operations James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-059
Reference:
Entergy letter, Notification of Permanent Cessation of Power Operations, JAFP-15-0133, dated November 18, 2015
Dear Sir or Madam:
On November 18, 2015, Entergy Nuclear Operations, Inc (Entergy) notified the NRC that it intended to permanently cease power operations of James A. FitzPatrick Nuclear Power Plant (JAF) in late 2016 or early 2017 [Reference]. On February 18, 2016, Entergy announced the planned shutdown date for JAF. In view of the Reference letter and pursuant to 10 CFR 50.82(a)(1)(i) and 10 CFR 50.4(b)(8), Entergy certifies that it plans to permanently cease power operations at JAF on January 27, 2017.
Certification of permanent cessation of operation is a commitment to cease operations on January 27, 2017. The new regulatory commitment for JAF is listed in the Attachment. Should you have any questions, please contact Mr. Chris Adner, Regulatory Assurance Manager, at 315-349-6766.
I declare under penalty of perjury that the foregoing is true and correct; executed on March 16, 2016.
Sincerely, Brian R. Sullivan Site Vice President BRS/CMA/mh
\\
Attachment:
Regulatory Commitments cc next page
JAFP-16-0045 Page 2 of 2 cc:
Daniel Dorman, Regional Administrator Bill Dean, Director, Office of Nuclear Reactor Regulation Edward Knutson, NRC Senior Resident Inspector - JAF William C. Huffman, Project Manager Bridget Frymire, NYSPSC John B. Rhodes, NYSERDA
JAFP-16-0045 Attachment Regulatory Commitments (1 Page)
JAFP-16-0045 Attachment Regulatory Commitments Page 1 of 1 This table identifies actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRCs information and are not commitments.
COMMITMENT TYPE (Check one)
SCHEDULED COMPLETION DATE (If Required)
ONE-TIME ACTION CONTINUING COMPLIANCE James A. FitzPatrick Nuclear Power Plant will cease operations per 10 CFR 50.82(a)(1)(i) on January 27, 2017.
X January 27, 2017
~ Entergy JAFP-16-0045 March 16, 2016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A. FitzPatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315-342-3840 Brian R. Sullivan Site Vice President - JAF 10 CFR 50.82
Subject:
Certification of Permanent Cessation of Power Operations James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-059
Reference:
Entergy letter, Notification of Permanent Cessation of Power Operations, JAFP-15-0133, dated November 18, 2015
Dear Sir or Madam:
On November 18, 2015, Entergy Nuclear Operations, Inc (Entergy) notified the NRC that it intended to permanently cease power operations of James A. FitzPatrick Nuclear Power Plant (JAF) in late 2016 or early 2017 [Reference]. On February 18, 2016, Entergy announced the planned shutdown date for JAF. In view of the Reference letter and pursuant to 10 CFR 50.82(a)(1)(i) and 10 CFR 50.4(b)(8), Entergy certifies that it plans to permanently cease power operations at JAF on January 27, 2017.
Certification of permanent cessation of operation is a commitment to cease operations on January 27, 2017. The new regulatory commitment for JAF is listed in the Attachment. Should you have any questions, please contact Mr. Chris Adner, Regulatory Assurance Manager, at 315-349-6766.
I declare under penalty of perjury that the foregoing is true and correct; executed on March 16, 2016.
Sincerely, Brian R. Sullivan Site Vice President BRS/CMA/mh
\\
Attachment:
Regulatory Commitments cc next page
JAFP-16-0045 Page 2 of 2 cc:
Daniel Dorman, Regional Administrator Bill Dean, Director, Office of Nuclear Reactor Regulation Edward Knutson, NRC Senior Resident Inspector - JAF William C. Huffman, Project Manager Bridget Frymire, NYSPSC John B. Rhodes, NYSERDA
JAFP-16-0045 Attachment Regulatory Commitments (1 Page)
JAFP-16-0045 Attachment Regulatory Commitments Page 1 of 1 This table identifies actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRCs information and are not commitments.
COMMITMENT TYPE (Check one)
SCHEDULED COMPLETION DATE (If Required)
ONE-TIME ACTION CONTINUING COMPLIANCE James A. FitzPatrick Nuclear Power Plant will cease operations per 10 CFR 50.82(a)(1)(i) on January 27, 2017.
X January 27, 2017