JAFP-14-0105, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049)

From kanterella
(Redirected from JAFP-14-0105)
Jump to navigation Jump to search

Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049)
ML14241A261
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/28/2014
From: Coyle L
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, JAFP-14-0105
Download: ML14241A261 (15)


Text

Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

James A. FitzPatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315-342-3840 Lawrence M. Coyle Site Vice President - JAF JAFP-14-0105 August 28, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049)

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-059

Reference:

1. NRC Order Number, EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012
2. NRC Interim Staff Guidance, JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 0, dated August 29, 2012
3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide, Revision 0, dated August 2012

4. Entergy to NRC, JAFP-12-0124, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated October 29, 2012
5. Entergy to NRC, JAFP-13-0025, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013

Dear Sir or Madam:

On March 12, 2012, the Nuclear Regulatory Commission (NRC or Commission) issued an order [Reference 1] to James A. FitzPatrick Nuclear Power Plant (JAF). Reference 1 was immediately effective and directed JAF to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.

JAFP-14-0105 Page 2 of 2 Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance [Reference 2] and an overall integrated plan pursuant to Section IV, Condition C.2. Reference 2 endorsed industry guidance document NEI 12-06, Revision O

[Reference 3] with clarifications and exceptions identified in Reference 2. Reference 4 provided the JAF initial status report regarding mitigation strategies. Reference 5 provided the JAF overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the third six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact Chris M. Adner, Regulatory Assurance Manager, at 315-349-6766.

I declare under penalty of perjury that the foregoing is true and correct. Executed on 281h day of August, 2014.

Sincerely, LMC/CMA/mh

Attachment:

James A. FitzPatrick Nuclear Power Plant's (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator NRC Resident Inspector Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRG Mr. Doug Pickett, Senior Project Manager Ms. Bridget Frymire, NYSPSC Mr. John B. Rhodes, President NYSERDA

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (12 Pages)

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events

1. Introduction JAF developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2. Milestone Accomplishments The following milestone(s) have been completed since July 31, 2013, and are current as of July 31, 2014.

First Six-Month Status Report August 2013 (JAFP-13-0112)

Second Six-Month Status Report February 2013 (JAFP-14-0023)

3. Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Target Completion Revised Target Milestone Activity Status Date* Completion Date 60-day Status Update October 29, 2012 Complete Submit Overall Integrated February 28, 2013 Complete Plan Six-Month Status Report August 2013 Complete Refine Strategies December 2014 Started Perform Staffing Analysis June 2015 In progress Develop Strategies / May 2015 Started Contract with RRC Six-Month Status Report February 2014 Complete Develop Mods June 2015 Not Started Draft Implementing June 2016 Not Started Procedures Regional Response Center July 2015 Started Operational Develop Storage Plan June 2015 Started Purchase FLEX Equipment Fall 2016 Not Started Issue Maintenance Fall 2016 Not Started Procedures (for FLEX equipment)

Six-Month Status Report August 2014 Complete Page 1 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Target Completion Revised Target Milestone Activity Status Date* Completion Date Develop Training Plan October 2014 Not Started November 2015 Refueling Outage 1 Fall 2014 Not Started Six-Month Status Report February 2015 Not Started Implement Training May 2015 Not Started March 2016 Implement Mods (non- June 2015 Not Started outage)

Six-Month Status Report August 2015 Not Started Six-Month Status Report February 2016 Not Started Issue Implementing May 2016 Not Started Procedures Six-Month Status Report August 2016 Not Started Implement Mods (outage) Fall 2016 Not Started Implement Training Fall 2016 Not Started Updates Refueling Outage 2 (full Fall 2016 Not Started implementation)

Validation / Demonstration Fall 2016 Not Started

  • Target Completion Date is the last submitted date from either the overall integrated plan or previous six-month status report.
4. Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan (Reference 1 and 3).
5. Need for Relief/Relaxation and Basis for the Relief/Relaxation JAF expects to comply with the order implementation date and no relief/relaxation is required at this time.
6. Open Items from Overall Integrated Plan and Interim Staff Evaluation The following tables provide a summary and status of any open items documented in the Overall Integrated Plan and any open items or confirmatory items documented in the Interim Staff Evaluation (ISE) (Reference 4). A fourth table includes the status of each FitzPatrick Audit Question for the Mitigation Strategies (FLEX) Order.

Page 2 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Overall Integrated Plan Open Items Status OI-1: Beyond-design-basis external event impact on requirements in Entergy has existing licensing documents will be determined based on input determined that from the industry groups and direction from the NRC. update to existing licensing basis documents are not required to reflect BDBEEs.

OI-2: The structure, content and details of the Regional Response Started Center playbook will be determined.

Interim Staff Evaluation Open Items Status 3.1.1.3.A Procedural Interface (Seismic Hazard) - Evaluate the In Progress.

impacts from large internal flooding sources. (Audit This item will be Question 5) addressed by update to Audit Question (AQ) JAF-005 response when Information is available.

3.1.3.1.A Protection of FLEX Equipment (High Wind Hazard) - In Progress.

Evaluate the separation distance and the axis of separation This item will be considering the predominant path of tornados in the addressed by update geographic area to demonstrate that at least N sets of FLEX to AQ JAF-001 equipment would remain deployable in the context of a response when tornado missile hazard. (Audit Question 1) Information is available.

3.1.4.2.B Deployment of FLEX Equipment (Snow, Ice and Extreme In Progress.

Cold) - Evaluate the potential impact on the UHS due to ice This item will be blockage or formation of frazil ice as a result of extreme addressed on the cold. updated AQ response spreadsheet on the ePortal when Information is available.

3.2.3.A Containment- Verify that the implementation of Boiling In Progress.

Water Reactor Owners Group (BWROG) Emergency This item will be Procedure Guideline (EPG)/Severe Accident Guideline addressed by update (SAG), Revision 3, including any associated plant-specific to AQ JAF-017 evaluations, has been completed in accordance with the response when provisions of NRC letter dated January 9, 2014 (Reference Information is 23 of ISE - Letter from Jack R. Davis (NRC) to Joseph E. available.

Pollock (NEI) dated January 9, 2014, regarding Boiling Page 3 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Interim Staff Evaluation Open Items Status Water Reactor Containment Venting (ADAMS Accession No. ML13358A206))

Interim Staff Evaluation Confirmatory Items Status 3.1.1.2.A Deployment of FLEX Equipment- Confirm that soil In Progress.

liquefaction will not impede vehicle movement following a This item will be seismic event. addressed by update to AQ JAF-002 response when Information is available.

3.1.1.2.B Deployment of FLEX Equipment- Confirm final design In Progress.

features of the new storage building including the This item will be susceptibility to the loss of ac power to deploy equipment. addressed by update to AQ JAF-001 response when Information is available.

3.1.1.2.C Deployment of FLEX Equipment - Confirm the storage In Progress.

locations and means of protection against the seismic This item will be hazard of the super duty pickup trucks and the two flatbed addressed by update trailers used for deployment of FLEX equipment. to AQ JAF-001 response when Information is available.

3.1.1.4.A Offsite Resources- Confirm location of offsite staging In Progress.

area(s), access routes and methods of delivery of This item will be equipment to the site considering the seismic, flood, high addressed by update wind, snow, ice and extreme cold hazards. to AQ JAF-043 response when Information is available.

3.1.3.2.A Deployment of FLEX Equipment (High Wind Hazard) - In Progress.

Confirm availability of debris removal equipment to This item will be facilitate deployment of FLEX equipment. addressed on the updated AQ response spreadsheet on the ePortal when Information is available.

3.1.3.2.B Deployment of FLEX Equipment (High Wind Hazard) - In Progress.

Page 4 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Interim Staff Evaluation Confirmatory Items Status Confirm protection of the means to move FLEX equipment. This item will be addressed by update to AQ JAF-001 response when Information is available.

3.1.4.2.A Deployment of FLEX Equipment (Snow, Ice and Extreme In Progress.

Cold) - Confirm availability of snow removal equipment to This item will be facilitate deployment of FLEX equipment. addressed by update to AQ JAF-001 response when Information is available.

3.2.1.1.A Computer Code Used for ELAP Analysis - Benchmarks In Progress.

need to be identified and discussed which demonstrate This item will be that Modular Accident Analysis Program (MAAP) is an addressed by update appropriate code for the simulation of an ELAP event at to AQ JAF-009 JAF. response when Information is available.

3.2.1.1.B Computer Code Used for ELAP Analysis -Confirm that the In Progress.

collapsed level remains above Top of Active Fuel (TAF) This item will be and the cool down rate is within technical specifications addressed by update limits. to AQ JAF-012 response when Information is available.

3.2.1.1.C Computer Code Used for ELAP Analysis - Confirm that In Progress.

MAAP was used in accordance with Sections 4.1, 4.2, 4.3, This item will be 4.4, and 4.5 of the June 2013 position paper (ADAMS addressed by update Accession No. ML13190A201). to AQ JAF-010 response when Information is available.

3.2.1.1.D Computer Code Used for ELAP Analysis - Confirm that the In Progress.

licensee, in using MAAP, identified and justified the subset This item will be of key modeling parameters cited from Tables 4-1 through addressed by update 4-6 of the "MAAP Application Guidance, Desktop to AQ JAF-011 Reference for Using MAAP Software, Revision 2" (Electric response when Power Research Institute Report 1 020236). Information is available.

3.2.1.1.E Computer Code Used for ELAP Analysis - Confirm that the In Progress.

Page 5 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Interim Staff Evaluation Confirmatory Items Status specific MAAP analysis case that was used to validate the This item will be timing of mitigating strategies in the Integrated Plan has addressed by update been identified and is available for NRC staff to review. to AQ JAF-009 Alternately, a comparable level of information has been response when included in the supplemental response. In either case, the Information is analysis should include a plot of the collapsed vessel level available.

to confirm that TAF is not reached {the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits.

3.2.1.2.A Recirculation Pump Seal Leakage Models - Confirm the In Progress.

seal leakage model used in the updated MAAP analysis This item will be (which will address the MAAP code limitations when used addressed by update for ELAP analysis). Evaluate the seal leakage rate model to AQ JAF-014 used, the details of the seal qualification tests and response when supporting test data, and leakage rate pressure- Information is dependence. available.

3.2.1.3.A Sequence of Events (SOE) - Confirm the SOE timeline In Progress.

after reanalysis using the MAAP code which will address This item will be the limitations when used for the ELAP analysis. addressed by updated AQ JAF-012 response when Information is available.

3.2.1.4.A Systems and Components for Consequence Mitigation - In Progress.

Confirm sizing of the FLEX pumps and 600 Vac FLEX This item will be diesel generator (DG) and the 4160 Vac generator to be addressed by update obtained from the RRC. to AQ JAF-022 response when Information is available.

3.2.1.5.A Monitoring Instrumentation and Controls- Confirm ac In Progress.

powered torus temperature, pressure and level and drywell This item will be temperature and pressure instrumentation is modified to addressed by update remain powered during an ELAP. to AQ JAF-006 response when Information is available.

3.2.1.8.A Use of Portable Pumps - Confirm that the use of raw water In Progress.

from Lake Ontario for long term core and spent fuel pool This item will be cooling strategies is acceptable. addressed by update to AQ JAF-023 Page 6 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Interim Staff Evaluation Confirmatory Items Status response when Information is available.

3.2.2.A Spent Fuel Pool Cooling - Confirm the method of In Progress.

ventilation and power requirements, if any, of the spent This item will be fuel pool area. addressed by update to AQ JAF-028 response when Information is available.

3.2.4.2.A Ventilation (Equipment Cooling) - Confirm that additional In Progress.

evaluations of the RCIC room temperature demonstrate This item will be that an acceptable environment is maintained during the addressed by update transition phase both for equipment in the room and to AQ JAF-031 habitability for operators who may need to enter the room. response when Information is available.

3.2.4.2.B Ventilation (Equipment Cooling) - Confirm that evaluations In Progress.

of the battery room temperature demonstrate that an This item will be acceptable environment, during both high ambient addressed by update temperature and during extreme cold ambient to AQ JAF-069 temperature, is maintained during Phases 2 and 3. response when Information is available.

3.2.4.2.C Ventilation (Equipment Cooling) - Confirm the required In Progress.

ventilation flow or the size of the portable fans to maintain This item will be acceptable environmental conditions in the DC equipment addressed by update room. to AQ JAF-061 response when Information is available.

3.2.4.3.A Heat Tracing - Confirm completion of walkdowns and In Progress.

evaluation of where heat tracing may be needed for freeze This item will be protection of equipment or instruments used in the ELAP addressed by update mitigation strategies. to AQ JAF-035 response when Information is available.

3.2.4.4.A Lighting - Confirm need for additional portable lighting, In Progress.

such as dc powered lights. This item will be addressed by update to AQ JAF-036 Page 7 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Interim Staff Evaluation Confirmatory Items Status response when Information is available.

3.2.4.4.B Communications - Confirm that upgrades to the site's NRC Confirmatory communication system have been completed. Action 3.2.4.8.A Electrical Power Sources - Confirm the technical basis for In Progress.

the selection and size of the FLEX generators to be used This item will be in support of the coping strategies. addressed by update to AQ JAF-050 response when Information is available.

3.2.4.10.A Load Reduction to Conserve DC Power - Confirm final In Progress.

load shed list and the evaluation of any potential adverse This item will be effects of shedding those loads. addressed by update to AQ JAF-052 response when Information is available.

3.2.4.10.B Load Reduction to Conserve DC Power - Confirm the final In Progress.

dc load profile with the required loads and the finalized This item will be minimum battery voltage. addressed by update to AQ JAF-066 response when Information is available.

3.2.4.10.C Load Reduction to Conserve DC Power- Confirm time after In Progress.

the ELAP for connecting the FLEX DG to the battery This item will be chargers. addressed by update to AQ JAF-052 response.

3.4.A Off-site Resources- Confirm that NEI 12-06, Section 12.2 In Progress.

guidelines 2 through 10 are addressed, or that an This item will be appropriate alternative is justified. addressed by update to AQ JAF-043 response when Information is available.

Page 8 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Audit Completion or Status Questions Target Date In progress - This AQ response will be updated when information is available (ISE Open Item 3.1.3.1.A and JAF-001 August 2015 ISE Confirmatory Items 3.1.1.2.B, 3.1.1.2.C, 3.1.3.2.B, 3.1.4.2.A)

In progress - This AQ response will be updated when August 2015 JAF-002 information is available (ISE Confirmatory Item 3.1.1.2.A)

In progress - This AQ response will be updated when August 2015 JAF-003 information is available In progress - This AQ response will be updated when August 2015 JAF-004 information is available In progress - This AQ response will be updated when August 2015 JAF-005 information is available (ISE Open Item 3.1.1.3.A)

In progress - This AQ response will be updated when August 2015 JAF-006 information is available (ISE Confirmatory Item 3.2.1.5.A)

In progress - This AQ response will be updated when August 2015 JAF-008 information is available In progress - This AQ response will be updated when August 2015 JAF-009 information is available (ISE Confirmatory Items 3.2.1.1.A, 3.2.1.1.E)

In progress - This AQ response will be updated when August 2015 JAF-010 information is available (ISE Confirmatory Item 3.2.1.1.C)

In progress - This AQ response will be updated when August 2015 JAF-011 information is available (ISE Confirmatory Item 3.2.1.1.D)

In progress - This AQ response will be updated when August 2015 JAF-012 information is available (ISE Confirmatory Items 3.2.1.1.B, 3.2.1.3.A)

In progress - This AQ response will be updated when August 2015 JAF-013 information is available In progress - This AQ response will be updated when August 2015 JAF-014 information is available (ISE Confirmatory Item 3.2.1.2.A)

JAF-015 Closed*

JAF-016 Closed*

In progress - This AQ response will be updated when JAF-017 August 2015 information is available (ISE Open Item 3.2.3.A)

JAF-018 Closed*

JAF-019 In progress - This AQ response will be updated when August 2015 Page 9 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Audit Completion or Status Questions Target Date information is available JAF-021 Closed*

In progress - This AQ response will be updated when August 2015 JAF-022 information is available (ISE Confirmatory Items 3.2.1.4.A)

In progress - This AQ response will be updated when August 2015 JAF-023 information is available (ISE Confirmatory Item 3.2.1.8.A)

JAF-026 Closed*

In progress - This AQ response will be updated when August 2015 JAF-027 information is available In progress - This AQ response will be updated when August 2015 JAF-028 information is available (ISE Confirmatory Item 3.2.2.A)

JAF-029 Closed*

In progress - This AQ response will be updated when August 2015 JAF-031 information is available (ISE Confirmatory Item 3.2.4.2.A)

JAF-032 Closed*

In progress - This AQ response will be updated when August 2015 JAF-033 information is available JAF-034 Closed*

In progress - This AQ response will be updated when August 2015 JAF-035 information is available (ISE Confirmatory Item 3.2.4.3.A)

In progress - This AQ response will be updated when August 2015 JAF-036 information is available (ISE Confirmatory Item 3.2.4.4.A)

JAF-037 Closed*

JAF-038 Closed*

In progress - This AQ response will be updated when August 2015 JAF-040 information is available In progress - This AQ response will be updated when August 2015 JAF-043 information is available (ISE Confirmatory Items 3.1.1.4.A, 3.4.A)

JAF-046 Closed*

JAF-049 Closed*

In progress - This AQ response will be updated when JAF-050 August 2015 information is available (ISE Confirmatory Item 3.2.4.8.A)

Page 10 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Audit Completion or Status Questions Target Date In progress - This AQ response will be updated when JAF-052 information is available (ISE Confirmatory Items August 2015 3.2.4.10.A, 3.2.4.10.C)

JAF-053 Closed*

JAF-055 Closed*

In progress - This AQ response will be updated when August 2015 JAF-056 information is available JAF-057 Closed*

JAF-058 Closed*

JAF-059 Closed*

In progress - This AQ response will be updated when August 2015 JAF-060 information is available In progress - This AQ response will be updated when August 2015 JAF-061 information is available (ISE Confirmatory Item 3.2.4.2.C)

In progress - This AQ response will be updated when August 2015 JAF-062 information is available JAF-063 Closed*

In progress - This AQ response will be updated when August 2015 JAF-064 information is available In progress - This AQ response will be updated when August 2015 JAF-065 information is available In progress - This AQ response will be updated when August 2015 JAF-066 information is available (ISE Confirmatory Item 3.2.4.10.B)

JAF-068 Closed*

In progress - This AQ response will be updated when August 2015 JAF-069 information is available (ISE Confirmatory Item 3.2.4.2.B)

JAF-071 Closed*

JAF-072 Closed*

JAF-073 Closed*

  • Closed indicates that Entergys response is complete.
7. Potential Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time.

Page 11 of 12

JAFP-14-0105 Attachment James A. FitzPatrick Nuclear Power Plants (JAF) Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events

8. References The following references support the updates to the Overall Integrated Plan described in this attachment.
1. Entergy to NRC, JAFP-13-0025, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013.
2. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012.
3. Entergy to NRC, JAFP-13-0112, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049), dated August 28, 2013.
4. NRC letter, James A. FitzPatrick Nuclear Power Plant - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC No. MF1077), dated February 21, 2014
5. Entergy to NRC, JAFP-14-0023, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA 049), dated February 28, 2014 Page 12 of 12