MONTHYEARJAFP-23-0065, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2023-12-14014 December 2023 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications JAFP-23-0069, Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements JAFP-23-0057, and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation JAFP-23-0064, Emergency Plan Document Revision2023-11-15015 November 2023 Emergency Plan Document Revision JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use JAFP-23-0059, Registration of Spent Fuel Cask Use2023-10-24024 October 2023 Registration of Spent Fuel Cask Use JAFP-23-0048, Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-31031 August 2023 Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0050, Physical Security Plan, Revision 242023-08-31031 August 2023 Physical Security Plan, Revision 24 JAFP-23-0047, Correction to the 2022 Annual Radioactive Effluent Release Report2023-08-30030 August 2023 Correction to the 2022 Annual Radioactive Effluent Release Report JAFP-23-0040, License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-0303 August 2023 License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0043, 10 CFR 50.46 Annual Report2023-07-31031 July 2023 10 CFR 50.46 Annual Report JAFP-23-0038, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2023-07-28028 July 2023 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance JAFP-23-0033, License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation2023-06-28028 June 2023 License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation JAFP-23-0025, 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Annual Radiological Environmental Operating Report JAFP-23-0023, 2022 Annual Radioactive Effluent Release Report2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report JAFP-23-0010, 2022 REIRS Transmittal of NRC Form 52023-03-20020 March 2023 2022 REIRS Transmittal of NRC Form 5 JAFP-23-0008, Supplement to Inservice Inspection Summary Report Cycle 252023-02-22022 February 2023 Supplement to Inservice Inspection Summary Report Cycle 25 JAFP-22-0053, Inservice Inspection Summary Report Cycle 252022-12-20020 December 2022 Inservice Inspection Summary Report Cycle 25 JAFP-22-0046, Core Operating Limits Report Cycle 262022-10-17017 October 2022 Core Operating Limits Report Cycle 26 JAFP-22-0040, 10 CFR 50.46 Annual Report2022-07-29029 July 2022 10 CFR 50.46 Annual Report JAFP-22-0033, Core Operating Limits Report Mid-Cycle 252022-06-23023 June 2022 Core Operating Limits Report Mid-Cycle 25 JAFP-22-0032, Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b..2022-06-16016 June 2022 Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.. JAFP-22-0030, Oswego County and New York State Participation in the Emergency Plan2022-05-13013 May 2022 Oswego County and New York State Participation in the Emergency Plan JAFP-22-0029, 2021 Annual Radiological Environmental Operating Report2022-05-11011 May 2022 2021 Annual Radiological Environmental Operating Report JAFP-22-0028, 2021 Annual Radioactive Effluent Release Report2022-04-27027 April 2022 2021 Annual Radioactive Effluent Release Report JAFP-22-0026, 2021 REIRS Transmittal of NRC Form 52022-04-0707 April 2022 2021 REIRS Transmittal of NRC Form 5 JAFP-22-2020, Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Info2022-03-0404 March 2022 Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Informed JAFP-22-0017, Amendments to Indemnity Agreements2022-02-15015 February 2022 Amendments to Indemnity Agreements JAFP-22-0007, Summary of Changes to Exelon Generation Company, LLC, Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102022-01-31031 January 2022 Summary of Changes to Exelon Generation Company, LLC, Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 JAFP-22-0010, Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments2022-01-24024 January 2022 Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments JAFP-22-0008, Response to Request for Supplemental Information by the Office of Nuclear Reactor Regulation to Support Review of a License Amendment Request to Eliminate Selected Response Time Testing for Reactor Protection System and Primary2022-01-14014 January 2022 Response to Request for Supplemental Information by the Office of Nuclear Reactor Regulation to Support Review of a License Amendment Request to Eliminate Selected Response Time Testing for Reactor Protection System and Primary JAFP-21-0093, Propose Change to Eliminate Selected Response Time Testing for Reactor Protection System and Primary Containment Isolation Instrumentation2021-10-18018 October 2021 Propose Change to Eliminate Selected Response Time Testing for Reactor Protection System and Primary Containment Isolation Instrumentation JAFP-21-0089, Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2021-09-27027 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position JAFP-21-0087, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-09-16016 September 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments JAFP-21-0083, Notification of Readiness for NRC 95001 Inspection2021-09-0909 September 2021 Notification of Readiness for NRC 95001 Inspection JAFP-21-0081, Supplement to Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2021-09-0303 September 2021 Supplement to Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements JAFP-21-0075, Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs2021-08-12012 August 2021 Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs JAFP-21-0073, Response to Request for Additional Information Regarding Application to Revise the James A. FitzPatrick Nuclear Power Plant Limiting Condition for Operation (LCO) 3.5.1, ECCS - Operating Surveillance.2021-08-0909 August 2021 Response to Request for Additional Information Regarding Application to Revise the James A. FitzPatrick Nuclear Power Plant Limiting Condition for Operation (LCO) 3.5.1, ECCS - Operating Surveillance. JAFP-21-0069, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2021-07-30030 July 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors JAFP-21-0070, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b2021-07-30030 July 2021 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b JAFP-21-0071, 10 CFR 50.46 Annual Report2021-07-29029 July 2021 10 CFR 50.46 Annual Report JAFP-21-0064, Supplemental Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting2021-07-0707 July 2021 Supplemental Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting JAFP-21-0053, Emergency License Amendment Request - One Time Extension to TS 3.5.1 Condition a, TS 3.6.1.9 Condition a, and TS 3.6.4.1 Condition a Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement2021-06-14014 June 2021 Emergency License Amendment Request - One Time Extension to TS 3.5.1 Condition a, TS 3.6.1.9 Condition a, and TS 3.6.4.1 Condition a Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement JAFP-21-0052, Emergency License Amendment Request, One Time Extension of Condition a to TS 3.5.1, TS 3.6.1.9, and TS 3.6.4.1 Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement2021-06-13013 June 2021 Emergency License Amendment Request, One Time Extension of Condition a to TS 3.5.1, TS 3.6.1.9, and TS 3.6.4.1 Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement JAFP-21-0051, Emergency License Amendment Request - One Time Extension to TS 3.5.1 Condition a, TS 3.6.1.9 Condition a, and TS 3.6.4.1 Condition a Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement2021-06-13013 June 2021 Emergency License Amendment Request - One Time Extension to TS 3.5.1 Condition a, TS 3.6.1.9 Condition a, and TS 3.6.4.1 Condition a Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement JAFP-21-0050, Emergency License Amendment Request, One Time Extension of Condition a to TS 3.5.1, TS 3.6.1.9, and TS 3.6.4.1 Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement2021-06-12012 June 2021 Emergency License Amendment Request, One Time Extension of Condition a to TS 3.5.1, TS 3.6.1.9, and TS 3.6.4.1 Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement JAFP-21-0044, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-06-11011 June 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments JAFP-21-0042, Reply to a Notice of Violation; EA-20-1382021-06-0303 June 2021 Reply to a Notice of Violation; EA-20-138 JAFP-21-0041, Supplement to Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing2021-05-17017 May 2021 Supplement to Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing JAFP-21-0040, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2021-05-14014 May 2021 Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs 2023-08-31
[Table view] Category:Schedule and Calendars
MONTHYEARRS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations JAFP-15-0068, J. A. FitzPatrick - License Amendment Request - Cyber Security Plan Implementation Schedule2015-06-22022 June 2015 J. A. FitzPatrick - License Amendment Request - Cyber Security Plan Implementation Schedule JAFP-11-0103, NRC Form 536, Operator Licensing Examination Data, Update2011-08-19019 August 2011 NRC Form 536, Operator Licensing Examination Data, Update JAFP-11-0098, Submittal of NRC Form 536, Operator Licensing Examination Data2011-07-28028 July 2011 Submittal of NRC Form 536, Operator Licensing Examination Data JAFP-08-0069, Submittal of NRC Form 536, Operator Licensing Examination Data in Response to Regulatory Issue Summary 2008-16, Preparation and Scheduling of Operator Licensing Examinations.2008-07-25025 July 2008 Submittal of NRC Form 536, Operator Licensing Examination Data in Response to Regulatory Issue Summary 2008-16, Preparation and Scheduling of Operator Licensing Examinations. JAFP-06-0143, NRC Form 536, Operator Licensing Examination Data2006-09-19019 September 2006 NRC Form 536, Operator Licensing Examination Data 2023-06-16
[Table view] |
Text
Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
- -~- James A. FitzPatrick NPP
- - tergy P.O. Box 110 Lycoming, NY 13093 Tel 315-342-3840 Eugene Dorman Acting Licensing Manager - JAF NPP JAFP-11-0103 August 19, 2011 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington DC 20555-0001
Subject:
NRC Form 536, Operator Licensing Examination Data, Update James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-59
Reference:
- 1. Regulatory Issue Summary 2011-004, Preparation and Scheduling of Operator Licensing Examinations, dated May 25, 2011.
- 2. Letter from Entergy to the NRC, dated July 28, 2011, JAFP-11-0098, "NRC Form 536, Operator Licensing Examination Data."
Dear Sir or Madam:
Enclosed are two NRC 536 Forms for the calendar years (CY) 2011 thru 2016. They are provided as an update to reference 2 in accordance with reference 1.
There are no commitments contained in this letter.
Should you have any questions, please contact Mr. Brian Finn, Acting Training Manager, at 315-349-6004.
Very truly yours,
- t.tU.~... ~
Eugene Dorman Acting Licensing Manager EDljo
Enclosures:
NRC Form 536, Operator Licensing Examination Data (CY 2011 - 2012)
NRC Form 536, Operator Licensing Examination Data (CY 2013 - 2016) cc: see next page
JAFP-11-0103 Page 2 of 2 cc: Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Resident Inspector James A. FitzPatrick Nuclear Power Plant U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. Bhalchandra Vaidya, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8-G14 Washington, DC 20555-0001 B. Finn C. Adner J. McCann JAF/RMS JAFP File WPO Licensing
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2011 (10-2008)
Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet EXAMINATION DATA e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NRC REGION James A. FitzPatrick Nuclear Power Plant 1
A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 12 CY 12 CY CY ESTIMATED NUMBER OF LICENSEE-PREPARED 1 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 12 CY 12 CY CY NUMBER OF REACTOR 1 6 OPERATORS NUMBER OF SENIOR REACTOR 6 0 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE 1 0 NUMBER OF SENIOR REACTOR 0 OPERATORS - LIMITED 0
PROPOSED DATES PRIMARY DATE 02/27/2012 09/03/2012 ALTERNATE DATE 03/27/2012 09/10/2012 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 11 CY 12 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 6 14 CANDIDATES NRC FORM 536 (10-2008) PRINTED ON RECYCLED PAPER
NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2011 (10-2008)
Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet EXAMINATION DATA e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NRC REGION James A. FitzPatrick Nuclear Power Plant 1
A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 13 CY 14 CY 15 CY 16 ESTIMATED NUMBER OF LICENSEE-PREPARED 1 0 1 0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 13 CY 14 CY 15 CY 16 NUMBER OF REACTOR 8 0 1 0 OPERATORS NUMBER OF SENIOR REACTOR 6 0 8 0 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE 2 0 1 0 NUMBER OF SENIOR REACTOR 0 0 0 OPERATORS - LIMITED 0
PROPOSED DATES PRIMARY DATE 09/14/2013 01/07/2015 ALTERNATE DATE 10/14/2013 02/07/2015 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 13 CY 14 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 9 CANDIDATES NRC FORM 536 (10-2008) PRINTED ON RECYCLED PAPER