MONTHYEARIR 07200031/20234012023-10-0404 October 2023 Yankee Atomic Electric Company - Independent Spent Fuel Storage Security Inspection Report 07200031/2023401 IR 05000029/20210012021-10-29029 October 2021 Yankee Atomic Electric Company - NRC Independent Spent Fuel Storage Installation Inspection Report 07200031/2021001 and 0500029/2021001 IR 07200031/20204012020-10-21021 October 2020 Yankee Atomic Electric Company - Independent Spent Fuel Storage Security Inspection Report No. 07200031/2020401 IR 05000029/20180012018-05-30030 May 2018 Yankee Atomic Electric Company, Rowe, Massachusetts Site - NRC Independent Spent Fuel Storage Installation Report Nos. 07200031/2018001 and 05000029/2018001 IR 07200031/20184012018-05-17017 May 2018 Inspection Report 07200031/2018401, on May 17, 2018, Yankee Atomic Electric Company - ISFSI Security Inspection Report 07200031/2018401 - (Cover Letter Only) IR 05000029/20160012016-05-18018 May 2016 IR 07200031-16-001 and 05000029-16-001 on 4/20/16, Yankee Atomic Electric Company, Rowe, Ma Site IR 07200031/20140012014-05-0606 May 2014 IR 07200031-14-001, on 04/14-15/14, Independent Spent Fuel Storage Installation, Yankee Atomic Electric Company, Rowe, Ma Site ML1036300432010-12-28028 December 2010 IR 07200031-10-001, on 11/30/10, Yankee Atomic Electric Company, Rowe, Ma (Transmittal Letter) IR 07200031/20100012010-12-28028 December 2010 IR 07200031-10-001, on 11/30/10, Yankee Atomic Electric Company, Rowe, Ma IR 05000029/20060012007-07-0202 July 2007 Combined IR 05000029-06-001 and 05000029-07-001, in 2006-2007, Yankee Atomic Electric Company, Rowe, Massachusetts ML0717007532007-03-16016 March 2007 Yankee Nuclear Power Station, Site Closure Project, Phase IV Final Inspection Report IR 05000029/20050022006-06-13013 June 2006 IR 05000029-05-002; on 08/01/2005 to 05/15/2006; Yankee Nuclear Power Station ML0615304212006-03-13013 March 2006 In-Process Inspection Survey Results for the Remaining Spent Fuel Pool and Northeastern Upper RCA Yard Excavations and Concrete Structures within the Excavations at the Yankee Nuclear Power Station, Rowe, Massachusetts (Docket No 50-29; Rft IR 05000029/20050012005-10-18018 October 2005 IR 05000029-05-001, on 02/01/2005 - 08/31/2005, Yankee Atomic Electric Company, Rowe, Massachusetts ML0615303792005-10-12012 October 2005 In-Process Inspection Cursory Survey Results for the Primary Auxiliary Building Remaining Walls at the Yankee Nuclear Power Station, Rowe, Massachusetts (Docket No. 50-29; Rfta No. 05-008) IR 05000029/20040022005-02-23023 February 2005 Report for Analysis of a Concrete Sample from the Yankee Nuclear Power Station, Rowe, Massachusetts (Inspection No. 50-029/2004-002) (Rfta No. 05-001) ML0513600812005-02-16016 February 2005 Confirmatory Survey Results for Class 3 Open Land Areas Outside the RCA, Yankee Nuclear Power Station, Rowe, Massachusetts (Docket No. 50-29; Rfta No. 04-007) IR 05000029/20040012004-09-20020 September 2004 IR 05000029-04-001, on 01/22/2004 - 08/05/2004, Yankee Atomic Electric Company IR 05000029/20030022004-02-12012 February 2004 IR 05000029-03-002, on 06/28/03 to 01/21/04, Yankee Atomic Electric Company, Rowe, Massachuetts ML0320401272003-06-24024 June 2003 Powerpoint Presentation at Yankee Rowe Connecticut Yankee Management Meeting with the NRC, June 23, 2003 IR 05000029/20020022003-01-27027 January 2003 IR 05000029-02-002, on 07/08/2002 - 01/03/2003, Yankee Atomic Electric Co., Rowe, Massachusetts. Decommissioning Activities IR 05000029/20020012002-08-12012 August 2002 IR 05000029-02-001, on 07/07/02, Yankee Atomic Electric Company, to Determine Whether the Decommissioning Activities Carried Out at Yankee Rowe Facility Were Conducted Safely and in Accordance with NRC Requirements IR 05000029/20010032002-03-20020 March 2002 IR 05000029/2001-003, Yankee Atomic Electric Company IR 05000029/19990021999-08-0404 August 1999 Insp Rept 50-029/99-02 on 990411-0714.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Safe Operation of Sf Pool,Radiological Controls,Organization & Mgt Controls & Auditing & C/As for Decommissioning Activities IR 05000029/19990011999-05-0505 May 1999 Insp Rept 50-029/99-01 on 990101-0411.No Violations Noted. Major Areas Inspected:Cold Weather Preparations for Spent Fuel Pool,Radiological Controls & self-assessment & Auditing & Corrective Actions for Decommissioning Activities IR 05000029/19980031998-10-0101 October 1998 Insp Rept 50-029/98-03 on 980601-0731.No Violations Noted. Major Areas Inspected:Decommissioning Activities,Including Mods to Spent Fuel Pool Bldg & Radiological Controls IR 05000029/19980011998-06-24024 June 1998 Insp Repts 50-029/98-01 & 50-029/98-02 on 980101-0331.No Violations Noted.Major Areas Inspected:Mod to SFP Bldg, Radiological Controls & Decommissioning Activities IR 05000029/19970021997-09-23023 September 1997 Insp Rept 50-029/97-02 on 970401-0814.No Violations Noted. Major Areas Inspected:Licensee Activities Re Decommissioning IR 05000029/19970011997-05-16016 May 1997 Insp Rept 50-029/97-01 on 970301-31.No Violations Noted. Major Areas Inspected:Facility Operations IR 05000029/19960041997-01-24024 January 1997 Insp Rept 50-029/96-04 on 961119-21.No Violations Noted. Major Areas Inspected:Insp Verified by Observation, Documentation Review &/Or Discussions W/Responsible or Involved Plant Staff IR 05000029/19960031996-10-16016 October 1996 Insp Rept 50-029/96-03 on 960827-29.No Violations Noted. Major Areas Inspected:Operations,Rp Program,Including Operations,Staffing,Mgt & Licensee Experience in Identifying & Correcting Weaknesses Re Control of Radioactive Matls IR 05000029/19930071993-12-28028 December 1993 Insp Rept 50-029/93-07 on 930826-1118.Violation Noted. Major Areas Inspected:Posting of Radiological Areas & Other Controls,Organization & Staffing,Exposure ALARA Program & Radiological Info Available to Workers IR 05000029/19930081993-11-0909 November 1993 Insp Rept 50-029/93-08 on 931018-19.No Violations Noted. Major Areas Inspected:Mgt Support & Audits Protected Area Barriers,Detection & Assessment Aids Protected Area Access Control of Personnel,Alarm Stations & Communications IR 05000029/19930051993-08-18018 August 1993 Insp Rept 50-029/93-05 on 930510-0731.No Violations Noted. Major Areas Inspected:Operations,Maint Engineering & Plant Support,Including Radiological Controls,Security,Fire Protection & Housekeeping & Administration IR 05000029/19920111993-02-0505 February 1993 Insp Rept 50-029/92-11 on 921114-930201.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000029/19920101992-11-23023 November 1992 Insp Rept 50-029/92-10 on 921104-06.One Open Items Noted. Major Areas Inspected:Contamination Monitoring of Guardhouse,Postings & Other Controls,Radiological Control of Work in Progress & Organization & Staffing IR 05000029/19900231990-12-0505 December 1990 Insp Rept 50-029/90-23 on 901105-09.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Controls & Radiological Environ Monitoring Programs IR 05000029/19900161990-11-0606 November 1990 Insp Rept 50-029/90-16 on 900821-1001.Violation Noted.Major Areas Inspected:Daytime & Backshifts in Areas of Plant Operations,Radiological Controls,Maint & Surveillance, Emergency Preparedness,Security IR 05000029/19900811990-09-28028 September 1990 Insp Rept 50-029/90-81 on 900709-20 & 0806-10.Weaknesses & Unresolved Item Noted.Major Areas Inspected:Maint Program IR 05000029/19900121990-09-24024 September 1990 Insp Rept 50-029/90-12 on 900619-0820.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Security,Engineering/Technical Support,Safety Assessment/Quality Verification & Repts IR 05000029/19900141990-09-0707 September 1990 Rev 1 to Notification of Significant Licensee Meeting 90-110 on 900921 in Region I Ofc Re Insp Rept 50-029/90-14 IR 05000029/19900131990-08-0303 August 1990 Insp Rept 50-029/90-13 on 900709-13.One Noncited Violation Noted.Major Areas Inspected:Implementation of Radiation Protection Program During Current Refueling Outage & Review of Training & Qualification of Contractor Technicians IR 05000029/19900111990-08-0101 August 1990 Insp Rept 50-029/90-11 on 900619-22.No Violations or Deviations Noted.Major Areas Inspected:Safety Injection Tank Design & Replacement Procedures Together W/Walkdown of Safety Injection Sys Pumps,Valves & Piping IR 05000029/19890801990-07-25025 July 1990 Ack Receipt of Re Violations Noted in Insp Rept 50-029/89-80 IR 05000029/19900061990-07-24024 July 1990 Exam Rept 50-029/90-06OL on 900619-21.Exam Results:All Three Candidates Passed Exams & Issued Licenses IR 05000029/19900091990-07-16016 July 1990 Insp Rept 50-029/90-09 on 900515-0618.No Violations Noted. Major Areas Inspected:Operational Safety,Plant Operations, Radiological Controls,Maint & Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000029/19900051990-02-16016 February 1990 Physical Security Insp Rept 50-029/90-05 on 900207-09.No Violations Noted.Major Areas Inspected:Implementation of Safeguards Info & Personnel Access Control Programs at Corporate Ofc IR 05000029/19890141989-08-31031 August 1989 Forwards Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations Noted IR 05000029/19890111989-08-28028 August 1989 Insp Rept 50-029/89-11 on 890626-0731.Unresolved Items Noted Re Plant Operations Review Committee Actions to Address Task Force Investigation Results of 890725 Loss of Emergency Bus.Areas Investigated:Security & LERs IR 05000029/19890131989-08-23023 August 1989 Physical Security Insp Rept 50-029/89-13 on 890724-28.No Violations Noted.Major Areas Inspected:Action on Findings of NRC Regulatory Effectiveness Review,Mgt Support,Security Program Plan,Audits & Protected & Vital Area Physical 2023-10-04
[Table view] |
Text
October 21, 2020
SUBJECT:
YANKEE ATOMIC ELECTRIC COMPANY - INDEPENDENT SPENT FUEL STORAGE SECURITY INSPECTION REPORT NO. 07200031/2020401
Dear Mr. Yorke:
On September 23, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an Independent Spent Fuel Storage Installation (ISFSI) security inspection at the Yankee Atomic Electric Company in Rowe, Massachusetts. The inspection covered the licensees physical security plan and the October 16, 2002, Interim Compensatory Measures for Dry Independent Spent Fuel Storage Installations Order and was conducted using NRC Inspection Procedure 81311, Physical Security Requirements for Independent Spent Fuel Storage Installations.
The enclosed inspection report documents the inspection results, which were discussed with you and other members of your staff, on September 23, 2020.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter and enclosure will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, X /RA/
Signed by: Fred L. Bower Fred L. Bower, III, Chief Plant Support Branch Division of Reactor Safety
Enclosure:
Inspection Report No. 07200031/2020401
REGION I==
INSPECTION REPORT Docket No. 07200031 License No. SFGL-13 Report No. 07200031/2020401 Licensee: Yankee Atomic Electric Company Address: 49 Yankee Road, Rowe, MA 01367 Location Inspected: Yankee Atomic Electric Company Independent Spent Fuel Storage Installation (ISFSI)
Inspection Dates: September 16 - 23, 2020 Inspectors: Jeremiah Rey, Physical Security Inspector Kenneth Hussar, Physical Security Inspector Approved by: Fred L. Bower, III, Chief Plant Support Branch Division of Reactor Safety Enclosure
REPORT DETAILS a. Inspection Scope Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2690, Inspection Program for Dry Storage of Spent Reactor Fuel at Independent Spent Fuel Storage Installations. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
The inspectors evaluated this area by reviewing the Independent Spent Fuel Storage Installation (ISFSI) security plan, implementing procedures, and records; conducting interviews with responsible security personnel and plant employees; and performing walk-downs of the ISFSI.
The inspectors: (1) reviewed the access authorization program for the ISFSI; (2) verified and assessed the licensees testing and maintenance program to assure the functionality and reliability of security equipment; and (3) verified that a rapid, capable response to safeguards contingency events had been appropriately developed and effectively implemented.
The inspectors conducted the following specific inspection activities and evaluated the program to determine if: (a) the access authorization program provided reasonable assurance that individuals granted unescorted access to the ISFSI Protected Area (PA)
were trustworthy and reliable and did not constitute an unreasonable risk to public health and safety; (b) procedures were in place to ensure that vehicles accessing the ISFSI had proper authorization and were properly searched; (c) keys, locks, combinations, and associated hardware used in the ISFSI PA were properly controlled; (d) the intrusion detection system (IDS) had the ability to detect and assess unauthorized penetration of the ISFSI PA and adequate response capability existed; (e) alarms for the ISFSI IDS annunciated at an alarm station which was continually staffed; (f) the ISFSI PA was illuminated to facilitate adequate assessment of PA penetration or unauthorized activity; (g) a program was in place for testing and maintenance of the physical protection systems associated with the ISFSI; (h) the spent fuel storage was within a PA and was protected by two barriers; (i) the vehicle barrier system satisfied the design vehicle bomb attack requirements; (j) communications had been established between onsite security forces and a designated response force or local law enforcement agency (LLEA); (k) a
security organization with written procedures had been established; (l) members of the security organization were trained, equipped, qualified, and requalified to perform assigned duties; (m) the committed responders provided for an adequate armed response; (n) written response procedures were established and maintained; (o) training included ISFSI activities; (p) safeguards events were being properly reported; (q) audits of the physical protection system were conducted; (r) signs were posted in accordance with requirements; (s) the licensee established an emergency plan; (t) the response force or LLEA had unimpeded access to the ISFSI PA during contingency events; and (u) staffing, procedures, and resources were adequate to protect against radiological sabotage.
b. Findings and Observations No findings were identified.
The inspectors reviewed approximately 19 condition reports, multiple self and independent assessments and an Apparent Cause Evaluation regarding deficiencies associated with the Yankee Atomic training program. The licensee implemented significant corrective actions to address these deficiencies. No violations of regulatory requirements were identified during this review.
Exit Meeting Summary On September 23, 2020, the inspectors presented the inspection results to Mr. David Yorke ISFSI Manager, and other members of the licensees staff. The inspectors verified that no proprietary information was retained by the inspectors or documented in this report.
A-2 ATTACHMENT SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT Licensee Personnel D. Yorke, ISFSI Manager J. Lenois, Security Program Manager S. Hemingway, Asst. Director of Operations LIST OF ITEMS OPEN, CLOSED, AND DISCUSSED Opened None Opened and Closed None Closed None INSPECTION PROCEDURES USED IP 81311, Physical Security Requirements for Independent Spent Fuel Storage Installations LIST OF DOCUMENTS REVIEWED Procedures SP-2, PA Access Authorization Program, Revision 10 SP-4, Control of Safeguards and Security Related Information, Revision 20 SP-11, Testing and Maintenance of Security Equipment, Revision 29 SP-13, Lock and Key Control, Revision 16 Condition Reports YA-CR-18-118 YA-CR-19-059 YA-CR-19-076 YA-CR-19-205 YA-CR-18-119 YA-CR-19-063 YA-CR-19-080 YA-CR-20-049 YA-CR-19-035 YA-CR-19-064 YA-CR-19-083 YA-CR-20-051 YA-CR-19-055 YA-CR-19-065 YA-CR-19-125 YA-CR-20-078 YA-CR-19-058 YA-CR-19-075 YA-CR-19-127 YA-CR-20-082 Condition Reports Generated YA-CR-20-146 YA-CR-20-147 YA-CR-20-148