UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 21, 2017 Mr. Charles Workman Site Security Manager St. Lucie Nuclear Plant Florida Power & Light Company 6501 South Ocean Drive Jensen Beach, FL 34957 SUBJECT: SAINT LUCIE NUCLEAR PLANT - U.S. NUCLEAR REGULATORY COMMISSION PHYSICAL SECURITY INSPECTION REPORT 05000335/2017403 AND 05000389/2017403

Dear Mr. Workman:

On February 16, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your St Lucie Nuclear Plant, Units 1 and 2. The NRC inspectors discussed the results of this inspection with Mr. and other members of your staff.

The inspectors documented the results of this inspection in the enclosed inspection report (IR).

No NRC-identified or self-revealing findings were identified during this inspection.

However, inspectors documented a licensee-identified violation, which was determined to be of very low safety significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest this violation or significance of this NCV, you should provide a response within 30 days of the date of this IR with the basis of your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II, and the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the St. Lucie Nuclear Plant.

This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemption, Request for Withholding. However, the material enclosed herein contains Security-Related Information in accordance with 10 CFR 2.390(d)(1), and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the Enclosure will not be made available electronically for public inspection in the NRC Public Document Room, or from the PARS component of NRCs ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1), and follow the instructions for withholding in 10 CFR 2.390(b)(1).

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,

/RA/

James C. Shehee, Acting Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos. 50-335 and 50-389 License Nos. DPR-67 and NPF-16 Enclosure:

NRC IR 05000335 and 389/2017403 w/Attachment: Supplemental Info (OUO)

cc: (See page 3) cc:

Robert Bitner Nuclear Fleet Security Florida Power & Light Co.

St. Lucie Nuclear Plant 700 Universe Blvd Juno Beach, FL 33408 Mano Nazar President and Chief Nuclear Officer Nuclear Division NextEra Energy P.O. Box 14000 Juno Beach, FL 33408 Michael J. Snyder Licensing Manager St. Lucie Nuclear Plant Florida Power & Light Co.

6501 S. Ocean Drive Jensen Beach, FL 34957 Dan DeBoer Site Director Florida Power & Light Company 6501 S. Ocean Drive Jensen Beach, FL 34957 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS/PSB2 RII:DRP/BR3 RII:DRS/PSB2 SIGNATURE JHW2 LJB4 JCS3 NAME J. Wallo L. Suggs J. Shehee DATE 3/ 20/2017 3/21/2017 3/21/2017 E-MAIL COPY YES NO YES NO YES NO