IE Insp Rept 50-322/84-16 on 840416-20,30 & 0501-04.No Violations Noted.Major Areas Inspected:Preoperational Test Program,Test Witnessing of Integrated Electrical Test & Tours
ML20197H030
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 05/18/1984
From: Bettenhausen L, Nicholas H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20197H019 List:
References
50-322-84-16, NUDOCS 8406180253
Download: ML20197H030 (10)


Text

,

. .

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report.No. 50-322/84-16

>

Docket No. 50-322 License No. CPPR-95 Priority --

Category B :

Licensee: Long Island Lighting Company '

175 East Old Country Road Hicksville, New York 11801

<

Facility Name: Shoreham Nuclear Power Station Inspection At: Shoreham, New York Inspection Conducted: April 16-20, 30, May 1-4, 1984 h

Inspectors: *

1 4 EN H.R. Nicholas, Lead Reactor Engineer / dat4 Ai; proved by:

L.H. Bettenhausen, Chief, Test

'

kN date Programs Section Inspection Summary: Inspection on April 16-20, 30, May 1-4, 1984 (Report No. 50-322/84-16)

Areas Inspected: Routine unannounced inspection of licensee's action on ,

previous inspection findings; preoperational test program including test pro- ,

gram implementation and verification, test procedure review of completed tests for test results evaluation, test witnessing of integrated electrical test; ;

'

and, tours of the facility. The inspection involved 61 hours7.060185e-4 days <br />0.0169 hours <br />1.008598e-4 weeks <br />2.32105e-5 months <br /> on-site by one region-based inspecto Results: No violations were identifie PDR ADOCK 05000322 0 PDR

- - - -

. .

.

DETAILS Persons Contacted Long Island Lighting Company

+ J. Alexander, Reactor Engineer B. Beytin, Assistant Startup Manager (Acting)

+ L. Calone, Chief Technical Engineer

+* G. Gisonda, Compliance Engineer -

+* G. Gogates, Compliance Engineer M. Herlihy, Lead Startup Engineer J. Kelly, Field Quality Assurance

+ J. Morin, Regulatory Compliance

+ A. Muller, OQA Engineer R. Purcell, Assistant Startup Manager

+* T. Rose, 00A Engineer

+ A. Robeson, PATP Test Coordinator

+* W. Steiger, Plant Manager

+ J. Scalice, Operations Manager D. Terry, Chief Maintenance Engineer

  • J. Wynne, Compliance Engineer E. Youngling, Startup Manager Stone and Webster Engineering Corporation
  • A. Dobrzeniecki, Startup Engineer W. Matejek, Lead Advisory Engineer General Electric Corporation A. Ketcham, Lead Startup Engineer J. Livingston, Startup Engineer

+ J. Riley, Operations Manager U.S. Nuclear Regulatory Commission

+ J. Chung, Lead Reactor Engineer

  • A. Finkel, Lead Reactor Engineer
  • E. McCabe, Section Chief, RI
  • C. Petrone, Resident Inspector
  • denotes those present at exit interview on April 19, 1984

+ denotes those present at exit interview on May 4, 1984 Licensee Action On Previous Inspection Findings (Closed) Unresolved Item (322/83-27-01)

Unresolved test exceptions to be closed for completed preoperational and acceptance test . .

These test exceptions for completed preoperational and acceptance tests have been resolved by the licensee. The resolutions were reviewed and verified by the inspecto This item is close (Closed) Unresolved Item (322/83-27-02)

Unresolved test exceptions to be closed for completed preoperational and acceptance test These test exceptions for completei preoperational and acceptance tests have been resolved by the licensee. The resolutions were reviewed and verified by the inspecto This item is close (Closed)_ Unresolved Item (322/82-27-02)

Battery rooms, cleaning, repair of door locks, battery charger ammeter and battery cell jumper stra The inspector verified the cleanliness of the battery rooms and the repair of the door locks, the battery cell jumper strap and the replacement of the battery charger ammete This item is close (Closed) Unresolved Item (322/82-27-03)

Dirt, debris, construction equipment and materials in containment, reactor building and screenwell room The inspector toured the containment, the reactor building, and the screenwell rooms and verified the removal of all construction equipment and acceptable cleanliness and painting of these area This item is close (Closed) Unresolved Item (322/82-12-01)

Unresolved test exceptions to be closed for completed preoperational and acceptance test These test exceptions for completed preoperational and acceptance tests have been resolved by the licensee. These resolutions were reviewed and verified by the inspecto This item is close (Closed) Unresolved Item (322/84-07-01)

Unresolved test exceptions to be closed for completed preoperational and acceptance test .

-, .

These test exceptions for completed preoperational and acceptance tests have been resolved by the licensee. These resolutions were reviewed and verified by the inspecto ,

This item is close (Closed) Unresolved Item (322/84-07-02)

Unresolved test exceptions to be closed for completed preoperational and acceptance test These test exceptions for completed preoperational and acceptance tests have been resolved by the licensee. These resolutions were reviewed and verified by the inspecto This item is close . Preoperational Test program References The references for the preoperational test program are listed as indicated in inspection report 50-322/83-23 and are used throughout the entire test progra .1 Test Program Implementation and Verification Scope The inspector held discussions with the plant manager, the startup manager and members of his staff, concerning the completed preopera-tional and acceptance tests (with the exception of the diesel genera-tor sets), test results to be reviewed and approved, and test excep-tions to be prioritized and resolve The discussions and reviews centered on the status of the preoperational test program, with agreement reached between the NRC inspector and the licensee's staff as to those:

(1) Completed Tests with no exceptions (2) Completed Tests with exceptions (required for fuel load)

(3) Completed Tests with exceptions (not required for fuel load)

(4) Diesel Generator tests to be handled separately Findings Through discussions with licensee personnel, review of documents, review of test results evaluation and approval of completed tests, and review of resolve test exceptions, the inspector verified that with the exception of the diesel generators, the licensee's preopera-

.. .

tional test program-is essentially, complete and adequate. The inspector verified the following:

(1) Completed tests that had no exceptions (2) Completed tests that had exceptions and were required for fuel load, and, (3) Completed tests with exceptions but not required for fuel loa In the prioritization of the licensee's preoperational test program test exceptions, the following priority code definitions have been given to the remaining test exceptions that will be followed up in subsequent inspection OC1 Generation Synchronization (1st time) and run thereafter 0C2A Low Power Physics Testing Initial Criticality 0C28 Normal Startup Initial Plant Heat-Up OC3 Hot Shutdown OC4 Cold Shutdown 0C5 Refuel: Required for Fuel Load (Synonymous with OPA or prior to Fuel Load)

TC1 Test Conditions No. 1 > 5% to 20% Thermal Power TC2 Test Conditions No. 2 between 25% to 50% Thermal Power

.TC3 Test Conditions No. 3 between 50% to 75% Thermal Power TC4 Test Conditions No. 4100% Rod Line with Natural Circulation only TC5 Test Conditions No. 5100% Rod Line 75% Thermal Power TC6 Test Conditions No. 6 100% Thermal Power MIS Miscellaneous, Reviewed but not required to support Fuel load or Power Ascension Program 1 REF Item deferred to 1st Refueling Outage 2 REF Item deferred to 2nd Refueling Outage The 13 completed test procedures that have test exceptions remaining, but are not required for fuel load, will be examined on subsequent inspections in accordance with the prioritized test exception status

. .

schedule, for resolution and approval by the licensee. This is Unresolved Item (388/84-16-01).

3.2 Procedure Review For Test Results Evaluation Scope The 4 completed test procedures listed below were reviewed to verify that adequate testing was conducted in order to satisfy regulatory guidance and licensee commitments and to ascertain whether uniform criteria were being applied in the evaluation of completed preopera-tional tests in order to assure their technical and administrative adequac (1) PT 307.003A-2 Revision 2, Approved January 5,1984 EDG 101 Electrical Preoperational Test Test results approved April 23, 1984 (2) PT 307.003B-2 Revision 2, Approved January 5, 1984 EDG 102 Electrical Preoperational Test Test results approved March 24, 1984 (3) PT 307.004A-2 Revision 2, Approved November 8, 1983 EDG 101 Qualification Preoperational Test Test results approved April 23, 1984 (4) PT 307.0048-3 Revision 3, Approved January 26, 1984 EDG 102 Qualification Preoperational Test Test results approved April 3, 1984 The inspector reviewed the test results and verified the licensee's evaluation of test results by review of test changes, test excep-tions, test deficiencies, "As-Run", copy of test procedures, accep-tance criteria, performance verification, recording conduct of tests, QC inspection records, restoration of systems to normal after tests, independent verification of critical steps or parameters, identifi-cation' of personnel conducting and evaluating test data, and verifica-tion that the test results have been approve Findings No discrepancies or unacceptable conditions were noted in the review of these procedures. These unresolved test exceptions were noted:

Procedure Title Exception PT 307.003A-2 EDG 101 Elec Test 041 ^

PT 307.003B-2 EDG 102 Elec Test 018

. .

These test procedures will be examined on a subsequent inspection for resolution and approval by the licensee. This is Unresolved Item (322/84-16-02).

3.3 Test Witnessing References

-- Integrated Electrical Test With Diesels 101 and 102 Available, Diesel 103 Not Available, PT 307.007

-- Final Safety Analysis Report, SNPS

-- Stone and Webster General Description, Diesel Generators

-- Stone and Webster Elementary Diagrams

-- Stone and Webster Electrical Drawings

-- General Electric Elementary Diagrams

-- Station Maintenance Procedures, SNPS

-- Station Operating Procedures, SNPS

-- Station Emergency Procedures, SNPS

-- Technical Specifications, SNPS

-- Nuclear Regulatory Commission Regulatory Guides Scope The objective of the Integrated Electrical Test was to verify the existence of independence among redundant onsite power sources and their load groups to the maximum extent possible with EDG 103 not available. Various equipment configurations were utilized to demon-strate independence during plant response to the Loss of Coolant Accident (LOCA) with and without a Loss of Offsite Power (LOOP).

Plant equipment was aligned for each test to demonstrate maximum response to each event while attempting to adhere to normal system lineups. Equipment response was verified using Control Room indica-tion The test completely demonstrated the engineered safety feature reset concern outlined in NRC Bulletin 80-06. This demonstration was incor-porated in tests 1 and 2 so that all equipment was include . .

f

Test 1 This test was a simulated LOCA with offsite power available. This demonstrated that diesels 101 and 102 started without load shedding and with the automatic initiation of emergency core cooling systems (ECCS) by high drywell pressure accident signa Test 2 This test was an initiation of simultaneous simulated LOCA and LOOP conditions, with the orange emergency DC battery system and associa-ted emergency AC diesel generator out of service. This demonstrated separation of the orange DC and 103 emergency bus from the red an blue DC buses and the 101 and 102 emergency AC buse Test 3

,

This test was an initiation of simultaneous simulated LOCA and LOOP conditions, with the blue and orange emergency DC battery systems and associated emergency AC diesel generators out of service. This demonstrated separation of the red DC 101 emergency bus from the blue and orange DC buses and the 102 and 103 emergency AC buse Test 4 This test was an initiation of simultaneous simulated LOCA and LOOP  ;

conditions with the red and orange emergency DC battery systems and associated emergency AC diesel generators out of service. This demonstrated separation of the blue DC and 102 emergency bus from the red and orange DC buses and the 101 and 103 emergency AC buse The testing of emergency diese; generator 103 response to a LOCA and/or LOOP was not demonstrated in this test due to engine unavaila-bilit Final testing to verify ECCS response of EDG 103 and inte- i grated plant response with various EDG combinations will be performed '

under test procedure PT 307.002, Integrated Electrical Tes Discussion  !

During this inspection, the inspector witnessed six of the eight test runs of the integrated electrical test (PT 307.007) for EDG 101 and l 102 only. This included dry runs as well as official record run The following plant emergency procedures were used successfully-during the integrated electrical tes (1) SP 29.023.01 Revision 3, Approved October 5, 1983 EP RPV Water Level Control (2) SP 29.015.01 Revision 4, Approved October 5, 1983 EP Loss of Offsite Power i.

- . _ . - , - . _ . -.. . . - ---,- .. - - - - - . . - . . _ _ _

. ..

(3) SP 29.010.01 Revision 4, Approved August 16, 1983 EP Emergency Shutdown (4) SP 29.023.03 Revision 8, Approved March 30, 1984 EP Containment Control-Witnessing by the inspector during these tests included review of overall crew performance as reflected in the following observations:

-- Approved procedures withelatest revision available and in use by test personnel,

-- Designated person in charge and conducting the test,

-- Minimum test personnel requirements met,

-- Test prerequisites met,  !

-- Proper plant supporting systems in service,

-- Special test equipment required by test procedure calibrated and I in service,

-- Testing performed as required by test procedure,

-- Test personnel actions appeared to be correct and timely during performance of test,

-- QA observations and documentation of witness points,

-- Data was collected for final analysis by proper personnel, and,

-- Periodic observation and notation of generator loads and parame-ters of diesel engines and supporting systems were mad Findings Through observations, records review, independent calculations and performance evaluation of licensee personnel involved in test runs of the integrated electrical tests, the inspector verified that testing was conducted in accordance with approved procedures that included the licensee's test commitments and regulatory requirements. The inspector verified the preliminary acceptability of test results for these test runs witnessed. The inspector had no further questions on these test runs at this tim . Plant Tours The inspector made several tours of the plant during the course of the inspection. The tours included the containment drywell, reactor building, turbine building, suam tunnel, control room, emergency switchgear rooms,

.. .

cable spreading / relay rooms, battery rooms, diesel generator rooms, fuel oil transfer pump rooms, MG set room, auxiliary boiler room, yard switch gear, screenwell rooms and circulating water pump are The inspection tour included observation of disassembly of EDG 103 for analysis of cracks in the engine block; preparations being made for the Integrated Electrical Test (IET); and the addition of the 20 MW gas tur-bine and the four 2.5 MW blue diesel generato-s; housekeeping and clean-liness, storage and protection of components and equipment. No items of noncompliance were observed during these tour . Unresolved Items Unresolved items are matters about which more information is required to ascertain whether they are acceptable items, items of noncompliance, or deviations. Unresolved items, resulting from this inspection are discus-sed in Section 3.1 and . Exit Interview At the conclusion of the site inspection on May 4, 1984, an exit meeting was conducted with the licensee's senior site representatives (denoted in Paragraph 1). The inspector summarized the scope and findings of the inspection. Previous inspections in this area were also discussed. At no time curing this inspection was written material provided to the licensee by the inspecto .