IR 05000320-07-007; May 31, June 26, and August 23; Three Mile Island Station, Unit 2, Safestor Inspection
ML072920094
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 10/19/2007
From: Ray Lorson
Decommissioning Branch I
To: Leidich G
GPU Nuclear
References
IR-07-007
Download: ML072920094 (8)


Text

UNITED STATES ber 19, 2007

SUBJECT:

INSPECTION 05000320/2007007, GPU NUCLEAR, THREE MILE ISLAND UNIT 2, MIDDLETOWN, PENNSYLVANIA

Dear Mr. Leidich:

The NRC has completed an announced inspection at your Middletown, PA facility, which covered an inspection period that began on May 31, 2007, and concluded on August 30, 2007.

The preliminary findings of the inspection were discussed with Mr. David Petro and other members of your staff upon the conclusion of the site inspection on May 31, 2007. Additional information provided on June 26 and August 23, 2007 was reviewed, and a summary of the inspection findings for the entire inspection period was discussed with Mr. Petro and other members of your staff during a telephone exit meeting on August 30, 2007. The enclosed report presents the results of that inspection.

Your programs for Post-Defueling Monitored Storage, corrective actions, occupational exposure controls, radiological environmental monitoring, and radioactive effluent controls were reviewed during this period. The inspector reviewed selected procedures and records, interviewed personnel, and observed activities. Within the scope of this inspection, no violations were identified.

In accordance with Section 2.390 of the NRCs Rules and Practices, Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC Public Document Room (PDR) and will be accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html. No response to this letter is required.

Sincerely,

/RA/

Raymond Lorson, Chief ber 19, 2007

SUBJECT:

INSPECTION 05000320/2007007, GPU NUCLEAR, THREE MILE ISLAND UNIT 2, MIDDLETOWN, PENNSYLVANIA

Dear Mr. Leidich:

The NRC has completed an announced inspection at your Middletown, PA facility, which covered an inspection period that began on May 31, 2007, and concluded on August 30, 2007.

The preliminary findings of the inspection were discussed with Mr. David Petro and other members of your staff upon the conclusion of the site inspection on May 31, 2007. Additional information provided on June 26 and August 23, 2007 was reviewed, and a summary of the inspection findings for the entire inspection period was discussed with Mr. Petro and other members of your staff during a telephone exit meeting on August 30, 2007. The enclosed report presents the results of that inspection.

Your programs for Post-Defueling Monitored Storage, corrective actions, occupational exposure controls, radiological environmental monitoring, and radioactive effluent controls were reviewed during this period. The inspector reviewed selected procedures and records, interviewed personnel, and observed activities. Within the scope of this inspection, no violations were identified.

In accordance with Section 2.390 of the NRCs Rules and Practices, Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC Public Document Room (PDR) and will be accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html. No response to this letter is required.

Sincerely,

/RA/

Raymond Lorson, Chief Decommissioning Branch Division of Nuclear Materials Safety Docket No. 05000320 License No. DPR-73 Distribution w/encl: R. Bellamy, DRP R. Laufer, RI OEDO B. Watson, FSME S. Collins, RA S. Barber, DRP P. Bamford, PM, NRR K. Banovac, FSME M. Dapas, DRA D. Kern, DRP, Senior E. Miller, NRR, Backup ROPreports@nrc.gov B. Holian, DNMS Resident Inspector J. Lubinski, NRR Region I Docket D. Lew, DRP J. Brand, DRP, RInspector H. Chernoff, NRR J. Clifford, DRP C. LaRegina, DRP, Res.OA D. Persinko, FSME DOCUMENT NAME: C:\FileNet\ML072920094.wpd SUNSI Review Complete: LKauffman After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: C = Copy w/o attach/encl E = Copy w/ attach/encl N = No copy OFFICE DNMS/RI E DRP /RI DNMS/RI NAME LKauffman RBellamy RLorson DATE 10/18/07 10/18/07 10/18/07 OFFICIAL RECORD COPY ML072920094

Enclosure:

NRC Region I Inspection Report No. 05000320/2007007 w/Attachment Supplemental Information

REGION I==

Inspection No. 05000320/2007007 Docket No. 05000320 License No. DPR-73 Licensee: Three Mile Island Station, Unit 2 (TMI-2)

Location: P.O. Box 480 Middletown, Pennsylvania 17057-0191 Inspection Dates: May 31, 2007 Date Followup Information Received: June 26 and August 23, 2007 Inspector: Laurie A. Kauffman, Health Physicist Approved By: Raymond Lorson, Chief Decommissioning Branch Division of Nuclear Materials Safety i Enclosure

SUMMARY OF FINDINGS

IR 05000320/2007007; May 31, June 26, and August 23; Three Mile Island Station, Unit 2,

SAFESTOR Inspection.

The report covered an announced inspection related to the Post-Defueling Monitored Storage (PDMS) program, corrective actions, occupational exposure controls, radiological environmental monitoring, and radioactive effluent controls. The inspection was conducted by a regional inspector and was based upon Manual Chapter (MC) 2561, Decommissioning Power Reactor Inspection Program. This routine inspection included a review of PDMS activities related to the safe storage of radioactive material and the implementation of the Unit 2 Technical Specifications (TS). The inspection focused on implementation of the TS requirement to perform an annual surveillance of the exclusion area barriers and accessible areas within the exclusion areas. The inspector determined that the licensee had an adequate program for the safe storage of radioactive material and the implementation of the TS requirement to perform an annual surveillance of the exclusion area barriers and accessible areas within the exclusion areas.

NRC Identified and Self-Revealing Findings

Cornerstone: Radiation Safety

No findings of significance were identified.

Licensee-Identified Violations

None ii

REPORT DETAILS

4OA5 Other Activities

.1 Inspection Procedure (IP) 40801 - Corrective Action Program - 1 sample

a. Inspection Scope

The inspector evaluated the TMI-2 corrective action program to assess the licensees ability to identify, resolve, and prevent recurrence of conditions and issues that could degrade the safety or quality of PDMS activities. The inspector examined selected issue reports (IRs) and action reports (ARs) and conducted interviews with personnel familiar with the selected issues.

b. Observations and Findings

No findings of significance were identified. The licensee maintained an adequate corrective action program to identify and resolve issues.

.2 IP 83750 and 84750 - Plant Support - 2 samples

a. Inspection Scope

The inspector reviewed PDMS activities related to the safe storage of radioactive material and the implementation of primary containment isolation requirements, TS 3/4.1, Containment Systems. The inspection included site tours and observations of the licensees annual reactor building entry surveillance test (ST). The reactor building ST included activities such as: conducting radiological surveys; water and air sampling; exchanging and analyzing the reactor building breather (passive air flow diaphragm); monitoring and sampling any potential radioactive gaseous effluent through the reactor building purge exhaust; and, collecting liquid samples from the reactor building sump.

The inspector also evaluated aspects of the occupational radiation protection program, radioactive effluent monitoring program, and the radiological environmental monitoring program. The inspector reviewed the related implementing procedures and associated surveillance test results, and the radioactive liquid and radioactive gaseous effluent release permits and data, from January 2006 through May 2007.

b. Observations and Findings

No findings of significance were identified. The inspector determined that the licensee had an adequate program for the safe storage of radioactive material and the implementation of the TS requirement to perform an annual surveillance of the exclusion area barriers and accessible areas within the exclusion areas.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On August 30, 2007, the NRC inspector presented the inspection results to Mr. Petro.

The inspector confirmed that proprietary and safeguards information were not included in this inspection report.

Supplemental Information

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

GPU Nuclear Three Mile Island, Unit 2 and Exleon/AmerGen Three Mile Island, Unit 1

J. Bowers, Radiation Protection Engineer, ALARA Analyst
R. Crawford, Radiation Waste Operator
E. A. Curry, Supervisor, TMI-2, GPUN
E. Parido, Radiation Protection Technician, TMI-1, AmerGen
D. Petro, Responsible Engineer, TMI-2; Senior Consultant, First Energy Nuclear

Operating Company (FENOC)

D. Smith, PDMS Manager, Work Management, TMI-1, AmerGen
C. Wend, Radiation Protection Manager
G. Welsh, Senior Mechanical Maintenance Technician

LIST OF ITEMS

OPENED, CLOSED AND DISCUSSED

OPEN NONE CLOSED NONE DISCUSSED NONE

LIST OF DOCUMENTS REVIEWED