MONTHYEARIR 05000320/20240012024-08-28028 August 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2024001 and 05000320/2024002 IR 07200077/20240012024-06-18018 June 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 07200077/2024001 IR 05000320/20230042024-02-0707 February 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023004 IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 IR 05000320/20220042023-02-16016 February 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2022004 and 05000320/2022401 IR 05000289/20220022023-02-13013 February 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 – NRC Inspection Report Nos. 05000289/2022002 and 005000289/2022402 IR 05000289/20220012022-08-26026 August 2022 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report Nos. 05000289/2022001 and 07200077/2022001 ML22228A0142022-08-17017 August 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report IR 05000289/20224012022-04-12012 April 2022 NRC Security Decommissioning Inspection Report No. 05000289/2022401 IR 05000289/20210022022-01-31031 January 2022 NRC Inspection Report 05000289/2021002 and 07200077/2021001 IR 05000320/20210042022-01-27027 January 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021004 IR 05000289/20210012021-06-28028 June 2021 NRC Inspection Report No. 05000289/2021001, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20214012021-06-28028 June 2021 Security Decommissioning Inspection Report 05000289/2021401 IR 05000320/20210032021-06-22022 June 2021 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021003 IR 05000289/20200052021-02-0101 February 2021 NRC Inspection Report No. 05000289/2020005, Exelon Generation Co., LLC, Three Mile Island Nuclear Station Unit 1 IR 05000320/20200022020-10-19019 October 2020 Gpu Nuclear, Inc., Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report 05000320/2020002 IR 05000289/20204012020-09-0101 September 2020 Unit 1 - Security Baseline Inspection Report 05000289/2020401 IR 05000289/20200032020-07-20020 July 2020 NRC Inspection Report No. 05000289/2020003, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20200012020-04-30030 April 2020 NRC Inspection Report 05000289/2020001 IR 05000289/20190102020-02-0404 February 2020 NRC Inspection Report No. 05000289/2019010, Exelon Generation Co., LLC, Three Mile Island Unit 1, Middletown, PA IR 05000289/20190032019-11-0606 November 2019 Integrated Inspection Report 05000289/2019003 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20193012019-08-15015 August 2019 Initial Operator Licensing Examination Report 05000289/2019301 IR 05000289/20190022019-08-0909 August 2019 Integrated Inspection Report 05000289/2019002 IR 05000320/20190012019-06-10010 June 2019 Gpu Nuclear, Inc., Three Mile Island Station, Unit 2 - NRC Inspection Report 05000320/2019001 IR 05000289/20195012019-06-0303 June 2019 Emergency Preparedness Biennial Exercise Inspection Report 05000289/2019501 IR 05000289/20194102019-03-18018 March 2019 Baseline Security Inspection Report 05000289/2019410 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180042019-01-31031 January 2019 Integrated Inspection Report 5000289/2018004 IR 05000289/20182012018-12-13013 December 2018 NRC Inspection Report 05000289/2018201 IR 05000289/20180032018-11-0808 November 2018 Integrated Inspection Report 5000289/2018003 IR 05000289/20184102018-09-18018 September 2018 Baseline Security Inspection Report 05000289/2018410 (Letter Only) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20180022018-08-0202 August 2018 Integrated Inspection Report 5000289/2018002 IR 05000320/20180112018-05-23023 May 2018 NRC Inspection Report 05000320/2018011 IR 05000289/20180102018-05-0202 May 2018 Design Bases Assurance Inspection (Teams) Report 05000289/2018010 IR 05000289/20180012018-05-0202 May 2018 Integrated Inspection Report 5000289/2018001 and Exercise of Enforcement Discretion IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170042018-01-25025 January 2018 Integrated Inspection Report 05000289-2017004 IR 05000289/20174052017-11-29029 November 2017 Problem Identification and Resolution Cyber Security Inspection Report 05000289/2017405 (Cover Letter) IR 05000289/20170032017-10-25025 October 2017 Integrated Inspection Report 5000289/2017003 IR 05000289/20174032017-09-25025 September 2017 Baseline Security Inspection Report 05000289/2017403 (Cover Letter) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20170102017-08-25025 August 2017 Susquehanna Steam Electric Station, Units 1 and 2 - Problem Identification and Resolution Cyber Security Inspection Report 05000387/2017405 and 05000388/2017405 (Cover Letter) IR 05000289/20173012017-08-23023 August 2017 Initial Operator Licensing Examination Report 05000289/2017301 IR 05000289/20170022017-08-0808 August 2017 Integrated Inspection Report 05000289/2017002 2024-08-28
[Table view] |
Text
eptember 22, 2006
SUBJECT:
INSPECTION 05000320/2006011, GPU NUCLEAR, THREE MILE ISLAND UNIT 2, MIDDLETOWN, PENNSYLVANIA
Dear Mr. Leidich:
The NRC has completed an announced inspection at your Middletown, PA facility, which covered an inspection period that began on May 31, 2006, and concluded on August 07, 2006.
The findings of the inspection were discussed with Mr. James Byrne and other members of your staff upon the conclusion of the site inspection on June 1, 2006. Additional information provided on July 5, 2006 was reviewed, and a summary of the inspection findings for the entire inspection period was discussed with Mr. Byrne and other members of your staff during a telephone conversation on August 31, 2006. The enclosed report presents the results of that inspection.
Your programs for Post-Defueling Monitored Storage, corrective actions, occupational exposure controls, radiological environmental monitoring, and radioactive effluent controls were inspected during this inspection period. The inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations made by the inspector.
The programs related to the Unit 2 Technical Specifications were appropriately implemented.
Within the scope of this inspection, no violations were identified.
In accordance with Section 2.390 of the NRCs Rules and Practices, Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC Public Document Room (PDR) and will be accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html. No response to this letter is required.
Sincerely,
/RA/
Marie Miller, Chief Decommissioning Branch Division of Nuclear Materials Safety GPU Nuclear Enclosure:
NRC Region I Inspection Report No. 05000320/2006011 cc:
J. Rinckel, Vice President, GPU Nuclear Oversight R. West, Vice President, Three Mile Island Unit 1 (TMI-1)
T. Nahay, Director Work Management, TMI-1 D. Smith, PDMS Manager, Work Management, TMI-1 L. Weir, TMI Nuclear Oversight Manager (TMI-2 matters)
C. Smith, Manager, Regulatory Assurance, TMI-1 A. Miller, Senior Regulatory Specialist, Regulatory Assurance, TMI-1 D. Petro, Responsible Engineer, TMI-2 E. Anderson, Responsible Engineer, TMI-2 Commonwealth of Pennsylvania