Text

une 1, 2009

SUBJECT:

D. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000315/2009403(DRS);

05000316/2009403(DRS)

Dear Mr. Jensen:

On May 1, 2009, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your D. C. Cook Nuclear Power Plant, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on May 1, 2009, with L. Weber and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no findings of significance were identified. However, one licensee-identified violation, which was determined to be of very low security significance, is listed in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section VI.A.1. of the NRC Enforcement Policy because of the very low security significance of the violation and because it was entered into your corrective action program.

If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the D. C. Cook Nuclear Power Plant.

Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74 Nonpublic Enclosure: Inspection Report 05000315/2009403(DRS);

05000316/2009403(DRS)

w/Attachment: Supplemental Information cc w/encl: D. Riffle, NSIR/DSO/DDSO T. Strong, State Liaison Officer cc w/o encl: L. Weber, Site Vice President J. Gebbie, Plant Manager O. Isiogu, Michigan Public Service Commission Michigan Department of Environmental Quality Planning Manager, Emergency Management and Homeland Security Division, Michigan State Police Department