Category:INSPECTION REPORT
MONTHYEARIR 05000083/20232012023-09-0505 September 2023 University of Florida – U.S. Nuclear Regulatory Commission Safety Inspection Report 05000083/2023201 IR 05000083/20232022023-08-28028 August 2023 University of Florida - U.S. Nuclear Regulatory Commission Security Inspection Report 05000083/2023202 (Public) IR 05000083/20222012023-02-0202 February 2023 University of Florida – U.S. Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000083/2022201 IR 05000083/20212012021-06-11011 June 2021 University of Florida U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000083/2021201 IR 05000083/20202022021-02-0909 February 2021 University of Florida - U.S. Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000083/2020202 IR 05000083/20192012019-09-18018 September 2019 University of Florida - U.S. Nuclear Regulatory Commission Routine Inspection Report 05000083/2019201 IR 05000083/20182012018-08-30030 August 2018 University of Florida & U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-083/2018-201 IR 05000083/20162022017-01-0404 January 2017 University of Florida - U.S. Nuclear Regulatory Commission Security Inspection Report No. 50-083/2016-202 ML16095A0952016-04-0606 April 2016 IR 05000083/2016201 - March 7-10, 2016, University of Florida IR 05000083/20122012012-02-24024 February 2012 IR 05000083-12-201 on January 30 Thru February 2, 2012 at the University of Florida - NRC Routine Inspection No. 50-083-12-201 IR 05000083/20122022012-02-24024 February 2012 IR 05000083-12-202 on January 30 Thru February 2, 2012 at the University of Florida - Transmittal Letter for NRC Security-Related IR 05000083/20112012011-06-0303 June 2011 IR 05000083-11-201, on April 4-7, 2011 at University of Florida - Severity Level IV and Notice of Violation IR 05000083/20102032010-09-15015 September 2010 IR 05000083-10-203, on August 17-19, 2010, University of Florida IR 05000083/20102012010-04-14014 April 2010 IR 05000083-10-201, on March 22-25 2010, University of Florida, Onsite Review of Selected Aspects of University of Florida'S (Licensee'S) Class II Research Reactor Safety Program Including: Organizational Structure & Staffing, Radiation Pro IR 05000083/20102022010-04-14014 April 2010 IR 05000083-10-202, on 03/22/2010 - 03/25/2010, Transmittal Letter of University of Florida, NRC Routine Security Inspection (Report Only OUO-SRI) IR 05000083/20072012007-02-0101 February 2007 IR 05000083-07-201, on 01/22-25/2007, University of Florida Test Reactor Facility IR 05000083/20062032006-11-22022 November 2006 NRC Inpsection Report No.0500083-06-203 and Notice of Violation, University of Florida IR 05000083/20062012006-02-17017 February 2006 IR 05000083-06-201, on 01/30-02/03/2006, University of Florida ML0510300342005-04-27027 April 2005 NRC Inspection Report No. 50-83/2005-201, Univ of Florida Test Reactor Facility, March 28-31, 2005 ML0200803612002-02-27027 February 2002 IR 05000083/2001-201, Univ. of Florida Test Reactor Facility, Inspection on 11/19-21/2002 Related to Organization & Staffing, Review & Audit Functions, Plant Operations, Procedures, Maintenance & Surveillance, Safeguards & Security Program IR 05000083/19982021998-11-0202 November 1998 Insp Rept 50-083/98-202 on 981006-09.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of Corrective Actions Previously Committed to by Licensee IR 05000083/19982011998-10-0101 October 1998 Insp Rept 50-083/98-201 on 980908-10.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Review of Respiratory Protection Program IR 05000083/19972011997-09-0909 September 1997 Insp Rept 50-083/97-201 on 970630-0703.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of CA Previously Committed to by Licensee IR 05000083/19940021994-09-20020 September 1994 Insp Rept 50-083/94-02 on 940906-08.No Violations Noted. Major Areas Inspected:Organization & Staffing,Safety Committee Function,Procedures,Requalification Training,Logs & Records,Reactor Operator,Surveillance & Experiments IR 05000083/19930011993-10-0101 October 1993 Insp Rept 50-083/93-01 on 930914-15.No Violations Noted. Major Areas Inspected:Plans,Procedures & Reviews,Fixed Site Physical Protection of Special Nuclear Matl of Moderate Strategic Significance.Details Withheld (Ref 10CFR2.790) IR 05000083/19900011990-03-19019 March 1990 Insp Rept 50-083/90-01 on 900220-23.No Violations Noted. Major Areas Inspected:Onsite Review of Radiation Protection Program Activities,Including Radiation Controls,Environ Surveillance & Monitoring & Transportation IR 05000083/19890041990-01-30030 January 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-083/89-04.Response Meets Requirements of 10CFR2.201 ML20011D9841989-12-15015 December 1989 Insp Rept 50-083/89-04 on 891113-16.Violations Noted.Major Areas Inspected:Biennial Insp of Class II Research Reactor Operation & Followup of Previous Open Items,Including Health Physics Items IR 05000083/19890021989-11-0606 November 1989 Insp Rept 50-083/89-02 on 890926-27.No Noncompliance Noted. Major Areas Inspected:Plans & Procedures,Rept of Safeguards Events Fixed Site Physical Protection of SNM of Moderate Strategic Significance & Matls Accounting Records & Repts IR 05000083/19890011989-05-12012 May 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-083/89-01 ML20244C4991989-04-0404 April 1989 IR 50-083/89-01 on 890227-0302 & 27.Violations Noted. Major Areas Inspected:Radiation Protection Program Activities,Including Radiation Controls,Environ Surveillance & Monitoring & Licensee Actions Re NRC Info Notices IR 05000083/19880011988-05-19019 May 1988 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-083/88-01 ML20151E6911988-04-0404 April 1988 Insp Rept 50-083/88-01 on 880314-17.Violations Noted.Major Areas Inspected:Onsite Review of Radiation Protection, Environ Surveillance & Monitoring,Transportation Activities, Enforcement Issues & NRC Info Notices IR 05000083/19870041987-11-10010 November 1987 Insp Rept 50-083/87-04 on 871019-22.No Violations or Deviations Noted.Major Areas Inspected:Biennial Insp of Class II Research Reactors IR 05000083/19870031987-04-23023 April 1987 Partially Withheld Insp Rept 50-083/87-03 on 870406-08 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted. Major Areas Inspected:Nuclear Matl Control & Accounting Procedures,Records & Repts & SNM Physical Inventory IR 05000083/19870011987-03-26026 March 1987 Discusses Insp Rept 50-083/87-01 on 870209-11 & Forwards Notice of Violation.Civil Penalty Not Assessed Due to Prior Good Performance in Area of Violation & Prompt Action Taken Re Radwaste Transportation Program ML20207T3621987-02-13013 February 1987 Insp Rept 50-083/87-01 on 870209-11.Violations Noted:Failure to Comply W/Dot Requirements for Transportation of Matls,To Follow Radiation Protection Procedures & to Post Required Documents IR 05000083/19860021986-06-0404 June 1986 Partially Withheld Physical Security Insp Repts 50-083/86-02 & 70-1068/86-02 on 860528-29 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted.Major Areas Inspected:Plans & Procedures & Repts of Safeguards Events IR 05000083/19860011986-05-0606 May 1986 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-083/86-01 ML20138C5111986-03-10010 March 1986 Insp Rept 50-083/86-01 on 860218-21.Violation Noted:Failure to Document Safety Review of Mod to Control Blade Shrouds IR 05000083/19850031985-11-0404 November 1985 Insp Rept 50-083/85-03 on 851009-11.No Violation or Deviation Noted.Major Areas Inspected:Licensee Action on Previous Enforcement Matters & Sticking Safety Control Blade 3 IR 05000083/19850021985-07-0808 July 1985 Safeguards Insp Repts 50-083/85-02 & 70-1068/85-02 on 850624-25.No Violations or Deviations Noted.Major Areas Inspected:Security Plan & Implementing Procedures & Security Organization.Details Withheld (Ref 10CFR2.790) IR 05000083/19850011985-05-0606 May 1985 Ack Receipt of Informing NRC of Steps Taken to Correct Deviation Noted in Insp Rept 50-083/85-01 IR 05000083/19820011982-07-19019 July 1982 Forwards IE Safeguards Insp Repts 50-083/82-01 & 70-1068/82-01 on 820629-0701.No Noncompliance Noted IR 05000083/19810021981-08-10010 August 1981 Forwards IE Safeguards Insp Rept 50-083/81-02 on 810729-31. No Noncompliance Noted.Rept Withheld (Ref 10CFR2.790) IR 05000083/19810011981-08-0404 August 1981 IE Insp Rept 50-083/81-01 on 810714-17.No Noncompliance Noted.Major Areas Inspected:Organization,Logs,Records, Requalification Training,Surveillances,Experiments,Audit Functions & Procedures IR 05000083/19800011980-04-0909 April 1980 IE Insp Rept 50-083/80-01 on 800317-20.Noncompliance Noted: Failure to Perform Required Safety Sys Checkout Prior to Startup IR 05000083/19790021979-11-20020 November 1979 IE Insp Rept 50-083/79-02 on 791022-25.Noncompliance Noted: Failure to Make Written Records of Monthly Meetings & Failure to Make Intensive Review of Facility Operations During 1977 IR 05000083/19790011979-05-11011 May 1979 IE Insp Rept 50-083/79-01 on 790427.No Noncompliance Noted. Major Areas Inspected:Security Plans,Protection of SNM, Security Organization,Access Control,Locks,Procedures & Security Program IR 05000083/19780061978-12-26026 December 1978 IE Insp Rept 50-083/78-06 on 781205.No Noncompliance Noted. Major Area Inspected:Emergency Drill Observation 2023-09-05
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000083/19982021998-11-0202 November 1998 Insp Rept 50-083/98-202 on 981006-09.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of Corrective Actions Previously Committed to by Licensee IR 05000083/19982011998-10-0101 October 1998 Insp Rept 50-083/98-201 on 980908-10.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Review of Respiratory Protection Program IR 05000083/19972011997-09-0909 September 1997 Insp Rept 50-083/97-201 on 970630-0703.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of CA Previously Committed to by Licensee IR 05000083/19940021994-09-20020 September 1994 Insp Rept 50-083/94-02 on 940906-08.No Violations Noted. Major Areas Inspected:Organization & Staffing,Safety Committee Function,Procedures,Requalification Training,Logs & Records,Reactor Operator,Surveillance & Experiments IR 05000083/19930011993-10-0101 October 1993 Insp Rept 50-083/93-01 on 930914-15.No Violations Noted. Major Areas Inspected:Plans,Procedures & Reviews,Fixed Site Physical Protection of Special Nuclear Matl of Moderate Strategic Significance.Details Withheld (Ref 10CFR2.790) IR 05000083/19900011990-03-19019 March 1990 Insp Rept 50-083/90-01 on 900220-23.No Violations Noted. Major Areas Inspected:Onsite Review of Radiation Protection Program Activities,Including Radiation Controls,Environ Surveillance & Monitoring & Transportation ML20011D9841989-12-15015 December 1989 Insp Rept 50-083/89-04 on 891113-16.Violations Noted.Major Areas Inspected:Biennial Insp of Class II Research Reactor Operation & Followup of Previous Open Items,Including Health Physics Items IR 05000083/19890021989-11-0606 November 1989 Insp Rept 50-083/89-02 on 890926-27.No Noncompliance Noted. Major Areas Inspected:Plans & Procedures,Rept of Safeguards Events Fixed Site Physical Protection of SNM of Moderate Strategic Significance & Matls Accounting Records & Repts ML20244C4991989-04-0404 April 1989 IR 50-083/89-01 on 890227-0302 & 27.Violations Noted. Major Areas Inspected:Radiation Protection Program Activities,Including Radiation Controls,Environ Surveillance & Monitoring & Licensee Actions Re NRC Info Notices ML20151E6911988-04-0404 April 1988 Insp Rept 50-083/88-01 on 880314-17.Violations Noted.Major Areas Inspected:Onsite Review of Radiation Protection, Environ Surveillance & Monitoring,Transportation Activities, Enforcement Issues & NRC Info Notices IR 05000083/19870041987-11-10010 November 1987 Insp Rept 50-083/87-04 on 871019-22.No Violations or Deviations Noted.Major Areas Inspected:Biennial Insp of Class II Research Reactors IR 05000083/19870031987-04-23023 April 1987 Partially Withheld Insp Rept 50-083/87-03 on 870406-08 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted. Major Areas Inspected:Nuclear Matl Control & Accounting Procedures,Records & Repts & SNM Physical Inventory ML20207T3621987-02-13013 February 1987 Insp Rept 50-083/87-01 on 870209-11.Violations Noted:Failure to Comply W/Dot Requirements for Transportation of Matls,To Follow Radiation Protection Procedures & to Post Required Documents IR 05000083/19860021986-06-0404 June 1986 Partially Withheld Physical Security Insp Repts 50-083/86-02 & 70-1068/86-02 on 860528-29 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted.Major Areas Inspected:Plans & Procedures & Repts of Safeguards Events ML20138C5111986-03-10010 March 1986 Insp Rept 50-083/86-01 on 860218-21.Violation Noted:Failure to Document Safety Review of Mod to Control Blade Shrouds IR 05000083/19850031985-11-0404 November 1985 Insp Rept 50-083/85-03 on 851009-11.No Violation or Deviation Noted.Major Areas Inspected:Licensee Action on Previous Enforcement Matters & Sticking Safety Control Blade 3 IR 05000083/19850021985-07-0808 July 1985 Safeguards Insp Repts 50-083/85-02 & 70-1068/85-02 on 850624-25.No Violations or Deviations Noted.Major Areas Inspected:Security Plan & Implementing Procedures & Security Organization.Details Withheld (Ref 10CFR2.790) IR 05000083/19810011981-08-0404 August 1981 IE Insp Rept 50-083/81-01 on 810714-17.No Noncompliance Noted.Major Areas Inspected:Organization,Logs,Records, Requalification Training,Surveillances,Experiments,Audit Functions & Procedures IR 05000083/19800011980-04-0909 April 1980 IE Insp Rept 50-083/80-01 on 800317-20.Noncompliance Noted: Failure to Perform Required Safety Sys Checkout Prior to Startup IR 05000083/19790021979-11-20020 November 1979 IE Insp Rept 50-083/79-02 on 791022-25.Noncompliance Noted: Failure to Make Written Records of Monthly Meetings & Failure to Make Intensive Review of Facility Operations During 1977 IR 05000083/19790011979-05-11011 May 1979 IE Insp Rept 50-083/79-01 on 790427.No Noncompliance Noted. Major Areas Inspected:Security Plans,Protection of SNM, Security Organization,Access Control,Locks,Procedures & Security Program IR 05000083/19780061978-12-26026 December 1978 IE Insp Rept 50-083/78-06 on 781205.No Noncompliance Noted. Major Area Inspected:Emergency Drill Observation IR 05000083/19770041977-03-0101 March 1977 IE Insp Rept 50-083/77-04 on 770721-22.No Noncompliance Noted.Major Areas Inspected:Security Plan,Sys & Areas,Access Control,Surveillance & Security Program Review ML20054C7471975-04-22022 April 1975 IE Insp Rept 50-083/75-02 on 750324-26.No Noncompliance Noted.Major Areas Inspected:Recordkeeping Sys IR 05000083/19750021975-04-22022 April 1975 IE Insp Repts 50-083/75-02,70-0462/75-01,70-0049/75-01 & 70-1068/75-02 on 750324-26.No Noncompliance Noted.Major Areas Inspected:Procedures,Reactor Thermal Output & Nuclear Matl Depletion & Production 1998-11-02
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000083/19982021998-11-0202 November 1998 Insp Rept 50-083/98-202 on 981006-09.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of Corrective Actions Previously Committed to by Licensee IR 05000083/19982011998-10-0101 October 1998 Insp Rept 50-083/98-201 on 980908-10.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Review of Respiratory Protection Program IR 05000083/19972011997-09-0909 September 1997 Insp Rept 50-083/97-201 on 970630-0703.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of CA Previously Committed to by Licensee ML20135C1961997-02-24024 February 1997 NRC Operator Licensing Exam Rept 50-083/OL-97-01 Including Completed & Graded Tests for Tests Administered on 970210-11.Candidate Passed Exam IR 05000083/19940021994-09-20020 September 1994 Insp Rept 50-083/94-02 on 940906-08.No Violations Noted. Major Areas Inspected:Organization & Staffing,Safety Committee Function,Procedures,Requalification Training,Logs & Records,Reactor Operator,Surveillance & Experiments IR 05000083/19930011993-10-0101 October 1993 Insp Rept 50-083/93-01 on 930914-15.No Violations Noted. Major Areas Inspected:Plans,Procedures & Reviews,Fixed Site Physical Protection of Special Nuclear Matl of Moderate Strategic Significance.Details Withheld (Ref 10CFR2.790) IR 05000083/19900011990-03-19019 March 1990 Insp Rept 50-083/90-01 on 900220-23.No Violations Noted. Major Areas Inspected:Onsite Review of Radiation Protection Program Activities,Including Radiation Controls,Environ Surveillance & Monitoring & Transportation ML20011D9861990-01-0404 January 1990 Notice of Violation from Insp on 891113-16.Violation Noted: Blade Drop Time Check Not Performed within Eight Months After Being Performed on 881205 & Quarterly Scram Checks Not Performed within Four Months After 890221 ML20011D9841989-12-15015 December 1989 Insp Rept 50-083/89-04 on 891113-16.Violations Noted.Major Areas Inspected:Biennial Insp of Class II Research Reactor Operation & Followup of Previous Open Items,Including Health Physics Items IR 05000083/19890021989-11-0606 November 1989 Insp Rept 50-083/89-02 on 890926-27.No Noncompliance Noted. Major Areas Inspected:Plans & Procedures,Rept of Safeguards Events Fixed Site Physical Protection of SNM of Moderate Strategic Significance & Matls Accounting Records & Repts ML20244C4951989-04-0707 April 1989 Notice of Violation from Insp on 880227-0302.Violation Noted:From Jan 1988 - Feb 1989,licensee Surveys Inadequate to Evaluate Extent of Radiation Hazards Present ML20244C4991989-04-0404 April 1989 IR 50-083/89-01 on 890227-0302 & 27.Violations Noted. Major Areas Inspected:Radiation Protection Program Activities,Including Radiation Controls,Environ Surveillance & Monitoring & Licensee Actions Re NRC Info Notices ML20196D5141988-11-10010 November 1988 Exam Rept 50-083/OL-88-02 on 881014.Exam Results:One Reactor Operator Passed Written Test ML20151E6671988-07-0505 July 1988 Exam Rept 50-083/OL-88-01 on 880608-09.Exam Results:Two Candidates Passed Operating Tests & One Candidate Passed Written Exams ML20151E6911988-04-0404 April 1988 Insp Rept 50-083/88-01 on 880314-17.Violations Noted.Major Areas Inspected:Onsite Review of Radiation Protection, Environ Surveillance & Monitoring,Transportation Activities, Enforcement Issues & NRC Info Notices ML20151E6741988-03-0707 March 1988 Notice of Violation from Insp on 880314-17.Violation Noted: Licensee Failed to Conduct Adequate Surveys to Evaluate Extent of Radiation Hazards Present in Liquid & Gaseous Effluents Released from Facility IR 05000083/19870041987-11-10010 November 1987 Insp Rept 50-083/87-04 on 871019-22.No Violations or Deviations Noted.Major Areas Inspected:Biennial Insp of Class II Research Reactors IR 05000083/19870031987-04-23023 April 1987 Partially Withheld Insp Rept 50-083/87-03 on 870406-08 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted. Major Areas Inspected:Nuclear Matl Control & Accounting Procedures,Records & Repts & SNM Physical Inventory ML20205N9891987-03-26026 March 1987 Notice of Violation from Insp on 870209-11.Violations Noted: Licensee Transported Two 55-gallon Drums Containing Licensed Matl Outside Confines of Plant Over Road Accessible to Public & Did Not Comply W/Dot Requirements ML20207T3551987-02-20020 February 1987 Notice of Violation from Insp on 870209-11 ML20207T3621987-02-13013 February 1987 Insp Rept 50-083/87-01 on 870209-11.Violations Noted:Failure to Comply W/Dot Requirements for Transportation of Matls,To Follow Radiation Protection Procedures & to Post Required Documents IR 05000083/19860021986-06-0404 June 1986 Partially Withheld Physical Security Insp Repts 50-083/86-02 & 70-1068/86-02 on 860528-29 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted.Major Areas Inspected:Plans & Procedures & Repts of Safeguards Events ML20138C5071986-03-27027 March 1986 Notice of Violation from Insp on 860218-21 ML20138C5111986-03-10010 March 1986 Insp Rept 50-083/86-01 on 860218-21.Violation Noted:Failure to Document Safety Review of Mod to Control Blade Shrouds IR 05000083/19850031985-11-0404 November 1985 Insp Rept 50-083/85-03 on 851009-11.No Violation or Deviation Noted.Major Areas Inspected:Licensee Action on Previous Enforcement Matters & Sticking Safety Control Blade 3 IR 05000083/19850021985-07-0808 July 1985 Safeguards Insp Repts 50-083/85-02 & 70-1068/85-02 on 850624-25.No Violations or Deviations Noted.Major Areas Inspected:Security Plan & Implementing Procedures & Security Organization.Details Withheld (Ref 10CFR2.790) IR 05000083/19810011981-08-0404 August 1981 IE Insp Rept 50-083/81-01 on 810714-17.No Noncompliance Noted.Major Areas Inspected:Organization,Logs,Records, Requalification Training,Surveillances,Experiments,Audit Functions & Procedures PNO-II-80-127, on 800724,reactor Was Being Brought to Power When Area Monitor Alarmed.Caused by Failure to Remove Startup Source.Reactor Manually Tripped & Startup Source Removed1980-07-24024 July 1980 PNO-II-80-127:on 800724,reactor Was Being Brought to Power When Area Monitor Alarmed.Caused by Failure to Remove Startup Source.Reactor Manually Tripped & Startup Source Removed IR 05000083/19800011980-04-0909 April 1980 IE Insp Rept 50-083/80-01 on 800317-20.Noncompliance Noted: Failure to Perform Required Safety Sys Checkout Prior to Startup IR 05000083/19790021979-11-20020 November 1979 IE Insp Rept 50-083/79-02 on 791022-25.Noncompliance Noted: Failure to Make Written Records of Monthly Meetings & Failure to Make Intensive Review of Facility Operations During 1977 IR 05000083/19790011979-05-11011 May 1979 IE Insp Rept 50-083/79-01 on 790427.No Noncompliance Noted. Major Areas Inspected:Security Plans,Protection of SNM, Security Organization,Access Control,Locks,Procedures & Security Program IR 05000083/19780061978-12-26026 December 1978 IE Insp Rept 50-083/78-06 on 781205.No Noncompliance Noted. Major Area Inspected:Emergency Drill Observation ML20147B8171978-08-17017 August 1978 Notice of Violation from Inspec on 780817 ML20151X4781977-08-19019 August 1977 PNO-77-146:flushing of Reactor Bldg Toilet Caused Reactor Scrams Over Past Several Yrs.No Safety Implications Involved & Contrary to Published News Repts,Sys Not Required for Emergency Cooling of Reactor IR 05000083/19770041977-03-0101 March 1977 IE Insp Rept 50-083/77-04 on 770721-22.No Noncompliance Noted.Major Areas Inspected:Security Plan,Sys & Areas,Access Control,Surveillance & Security Program Review ML20054C7471975-04-22022 April 1975 IE Insp Rept 50-083/75-02 on 750324-26.No Noncompliance Noted.Major Areas Inspected:Recordkeeping Sys IR 05000083/19750021975-04-22022 April 1975 IE Insp Repts 50-083/75-02,70-0462/75-01,70-0049/75-01 & 70-1068/75-02 on 750324-26.No Noncompliance Noted.Major Areas Inspected:Procedures,Reactor Thermal Output & Nuclear Matl Depletion & Production 1998-11-02
[Table view] |
Inspection Report - - 1981001 |
---|
|
|
Text
{{#Wiki_filter:-_
_.
/
fg
UNITED STATES P
NUCLEAR REGULATORY COMMISSION o
f E
REGION ll O[
101 MARIETTA ST., N.W., SUITE 3100
o ATLANTA, GEORGIA 30303 Report No.
50-83/81-01 Licensee: University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611 Facility Name: University of Florida Training Reactor Docket No. 50-83 License No. R-56 Inspector:
-
.
&
h
R. C. Butsher, Project Snspector Date Signed Approved by:
i
-
IN, f[M[[
C. A. Juliarf/ Acting Section Chief, Division of Date Signed Resident and Reactor Project Inspection SUMMARY Inspection on July 14-17, 1981 Areas Inspected This routine, unannounced inspection involved 28 resident inspector-hours on site in the areas of organization, logs, records, requalification training, sur-veillances, experiments, audit functions, procedures, licensee event followup and review of previous outstanding items.
Resul ts Of the ten areas inspected, no violations or deviations were identified.
i
G109010363 810804" DR ADOCK 05000083 PDR
'
'
.
.
-
.
DETAILS 1.
Persons Contacted Licensee Employees
- A. N. Jacobs, Chairman, Department of Nuclear Engineering Science
.
- N. J. Diaz, Reactor Supervisor and Director of Nuclear Facilities
- G. R. Dalton, University of Florida Subcommittee Chairman
'
G. Norton, Radiation Control Officer
- A. W. !1arvin, Reactor Manager H. Gogun, Senior Reactor Operator
!
G. Fogle, Reactor Operator
'
M. Constable, Reactor Operator
- Attended exit interview 2.
Exit Interview The inspection scope and findings were summarized on July 17, 1981, with those persons indicated in Paragraph 1 above.
The licensee understood and
concurred in the findings presented.
3.
Licensee Action on Previous Inspection Findings See Paragraph 9 for details.
'
!
4.
Unresolved Items were not identified during this inspection.
l
Operating Logs, Records and Experiments The inspector reviewed representative samples of the control console operating logs from March 1980 to present. All entries appeared adequate.
The daily and weekly check sheets were complete and correct except for a few minor omissions such as:
a.
May 1,1981 daily - Item 4.2.3 not acknowledged as being accomplished.
b.
May 5, 1981 daily - Items 5.6.6 thru 5.6.10 not acknowledged as being accomplished, c.
May 17, 1981 daily - Operators name not entered on sheet In each case, it appears that the work was actually accomplished but that the appropriate blank was not checked off.
The inspector reviewed the records of experiments since March 1980 and found the " Requests for UFTR Operation" records, as required by Standard Operating Procedure (50P) 5.A, were not complete in that experiment numbers 81-1 and 81-2 did not have. paragraph 5 " Expected Reactivity Effects in the Reactor" completed. These experiments were both class 1 and duplicated previous I
{
__
_
.
.
_
_
_ _ _ _
. _ -
__
,
___
_
..
.
.
.
.'
,'
experiments in which reactivity effects were observed to be negligible.
Although in these two examples the blanks were not filled in, it appears that the experiments were properly reviewed and the technical specifications met.
i Since the above findings were a small portion of the total log and record entries, they are noted here for licensee corrective action and for inspector followup on future inspections to ensure improvement in this area.
This is an inspector followup item (50-83/81-01-01).
,
The facility organization and staffing was consistent with Technical
Specification requirements. The inspector had no further comments.
6.
Requalification Training
,
The inspector reviewed the requalification records for the operators
.
presently licensed at the UFTR and checked operating log entries for correlation.
It was found that one senior reactor operator had allowed his
'
license to expire on February 10, 1981.
Subsequently, on February 26, 1981, the operator's log show that individual's initials as the reactor operator.
A licensed reactor operator's initials had been entered also but were marked l
thru. Discussions with several members of staff and management indicate that the individual in question never operated the UFTR without one of the
full time licensed operators present. The operations were done under the direction of a licensed operator for training in support of a license
'
renewal request.
Operator lecture attendance records, examinations and test results and operational manipulations were documented. The inspector had no further coments.
7.
Surveillances The inspector reviewed surveillance records for five parameters which are required by Technical Specifications:
a.
Control blade drop time b.
Control blade reactivity worth c.
Operability test of interlocks listed in Table 1 of the Technical Specifications d.
!!inimum shutdown margin e.
Reactivity insertion rate for a single control blade The inspector observed the performance of a daily preoperational check, a reactor startup and the shutdown of the reactor. A failure to check the wide range channel count rate interlock is discussed in paragraph 9.e.
The inspector also noted that Technical Specifica'. ion paragraph IV.C.4 requires an operability test of interlocks prior to each startup.
UFTR 50P A.1 requires a daily preoperational check within 6 hours of startup unless the
- - -,
- - - -.
- - -. - - -
.
. - - -. -
-
.
,.
.,
.
.
reactor has been shutdown less than 6 hours from a run begun that same day and no known condition exists that would prevent a successful check from being performed.
Proposed UFTR Technidal Specifications have been revised to permit operation as defined in S0P A.1 and have been submitted to the NRC for approval.
This is an unresolved item (50-83/81-01-02) pending further review during a future inspection.
8.
Procedures The inspector reviewed the status of the facility standard operating procedures (50P's).
The following minor discrepancies were noted.
The console copy of the UFTR S0P's list of effective pages is out of a.
date.
b.
S0P A.1 cover sheet shows revision 10 entered but the last revision number in the book is revision 8.
Several sheets have no revision number but they have later dates than revision 8.
c.
S0P E.3.A. was reviewed and the system walk down showed the procedure was out of date. The procedure referred to the addit 1on of a jumper to connect city water (a backup source) to the secondary side of the reactor heat exchanger.
This was made obsolete when two check valves and a motor operated valve were added.
See paragraph 9.c for further information. The console copy of S0P's was verified to contain the latest version of SOP's.
The licensee has committed to reviewing procedures for accurary and completeness. The inspector had no further comments.
9.
Review of Previous Outstanding Items Inspector Followup Item (79-02-06) " Licensee will complete Generation a.
of Procedure E-4 for Safety-Related Auxiliary Systems by July 1,1980" The inspector reviewed the facility standard operating procedures (S0P's).
SOP's E.4.A " Reactor Shielding and Graphite" and E.4.B
" Auxiliary Systems liaintenance - Shield Tank and Shield Tank Recirculating System" have been reviewed and approved by the IJFTR subcommittee. This was outstanding item 50-83/79-02-06.
This item is closed.
b.
IE Circular 80-02 " Nuclear Power Plant Staff Work Hours" The inspector discussed the staff work with the Reactor Supervisor.
'
There are administrative guidelines that require an individual who works greater than 40 hours in any one week to take off equivalent hours the following week unless permissions to do otherwise is obtained from the administrative office. In general, excessive work hours fc-
,
.
operators has never been a problem at the UFTR.
This item is closed.
I i
s
-
,.
.,
.
.
c.
IE Circular 80-14 " Radioactive Contamination of Plant Demineralized Water System and Resultant Internal Contamination" The inspector reviewed the actions taken by the UFTR personnel. The city water connection to the well water for the secondary side of the reactor heat exchanger has two chack valves in series plus it is normally isolated by a motor operned valve.
This item is closed.
d.
IE Circular 79-15 " Bursting of High Pressure Hose and Malfunction of Relief Valve and '0'-Ring in Certain Self-Contained Breathing Apparatus" The inspector examined the self contained breathing apparatus (SCBA)
used by the UFTR.
They use MTA model 401 and Scott air Pac model 6000 A2M SCBA's and this circular is not applicable. This item is closed.
e.
Infraction (80-01-02) " Technical Specification IV.C. Requires Check of Wide Range Count Rate Inhibit Check Prior to Each Startup" The technical specifications require a check of the wide range source count rate inhibit circuit prior to each startup. The check at 2 cps cannot be accomplished as explained in UFTR letter dated May 7,1980 and a change to the technical specifications regarding this check has been submitted to the NRC.
This item remains open at this time.
f.
Inspector Followup Item (79-02-01) " Develop and Implement a Written Procedure for Test Reactivity Measurements" The UFTR procedure for reactivity measurements which measures control blade reactivity worths, shut down margin and reactivity insertion rates was reviewed by the inspector. The tests appeared to be con-ducted correctly and the written procedure completes the licensee commitment to develop such procedures.
This item is closed.
,
i
!
10.
Licensee Event Followup An unusual occurrence was reported by the licensee by telephone on July 24, 1980 and by written report on August 5, 1980. The occurrence involved the failure of the reactor operator to remove the PuBe source from the reactor prior to attempting to bring the reactor to full power.
The licensee i
committed to corrective actions in the August 5,1980 report.
The inspector I
reviewed the reactor faci'!ty and UFTR records for compliance to the commitments. The following status was found.
,
!
a.
UFTR S0P's A.2 and A.4 were revised to include provisions for insertion and removal of the PuBe source. The revisions had been reviewed and approved by the UFTR subcommittee.
b.
An audible alarm that actuates when the reactor reaches 10 watts with the PuBe source still inserted has been installed.
L
>
.
..
The Radiation Control Committee (RCC) also recommended that the reactor building ventilation system have the capability to be closed from the ou tside. The licensee stated that the design was complete and this modification is to be accomplished during a shutdown scheduled for August 1981.
The inspector had no further questions.
11.
UFTR Subcommittee Review and Audit
.
The inspector reviewed the minutes from the meetings of the Univarsity of Florida Training Reactor (UFTR) subcommittee held from March 1980 thru 1981.
The meetings frequency met or exceeded the time limit in the technical specifications. The meeting minutes were formally documented and retained in file.
The subcommittee organization and quorum met technical specifi-cation requirements.
The inspector had no further questions.