HBL-13-003, Decommissioning Funding Report, Page 86 of 120 Through End
| ML13093A030 | |
| Person / Time | |
|---|---|
| Site: | Humboldt Bay |
| Issue date: | 04/01/2013 |
| From: | Pacific Gas & Electric Co |
| To: | NRC/FSME |
| Shared Package | |
| ML130930039 | List: |
| References | |
| HBL-13-003 | |
| Download: ML13093A030 (35) | |
Text
TABLE 5.3 WASTE DISPOSAL
SUMMARY
- PLANT SYSTEMS REFUELING BUILDING ft3 RB2-8 Suppression Chamber - East 3,267 RB2-9 Suppression Chamber - West 3,104 RB2-1 (75%)
Elev. -2ft, Suppression Pool Cooler 651 RB2-2 (75%)
Elev. -14ft, manlift 816 RB2-3 Elev. -24ft, CRD Hydraulic Filters 322 RB2-4 Elev. -34ft, SC Pool Access Hatch 123 RB2-5 Elev. -44ft, CRD Piping 1,551 RB2-6 Elev. -54ft, CRD Trip Accumulators 1,024 RB2-7 Elev. -66ft, Caisson Sump, REDT 904 TB4-2 (75%)
Pipe Gallery 1,952 TB5-2 Condensate Demineralizers 498 RB1-1 (90%)
Emergency Condenser 323 RBl-2 Spent Fuel Pool 116 RBl-3 Cask Shipping Area 106 RBl-4 SFP Pumps/Filters 611 RBl-5 Laydown/Cask Washdown Area 711 RBl-6 RV Cavity 907 RB3-2 New Fuel Storage/Fuel Pool Coolers 93 RB4-2 TBDT /Floor Drain Pumps 325 RADWASTE RW1-1 Concentrators, Pumps & Filters 1,124 RWl-2 Waste Receiver & Hold Tanks 2,604 RWl-3 Radwaste Demineralizer 34 RWl-6 Upper Elevation 741 21,907 Page 86 of 120
TABLE 5.4 WASTE DISPOSAL
SUMMARY
- INTERMODALS CPUC Weight Total Waste Disposal 2012 Volume 2012 CPUC Estimate Intermodals (150pcf Concrete 2012 CPUC Estimate Estimate 130pcf Soil)
(ft3)
(Ibs)
(30,970 Ibs/IM)
Total including Caisson 2,190,599 295,338,372 4,676 Total not including Caisson 1,073,005 145,493,412 3,217 Caisson Total 1,117,594 149,844,960 1,460 Total Concrete Removal 582,538 85,786,729 2,683 Concrete Recycled 137,963 20,694,450 668 Disposed Conc(ete 444,575 65,092,279 2,015 Total Soil Excavation 1,582,885 205,775,018 1,916 Reused Soil 1,126,323 146,421,990 Disposed Soil 456,562 59,353,028 1,916 Systems Removal 25,178 3,776,625 I 54 Decontamination & Demo Prep I
Building Demolition 630,632 84,677,217 ;
1,460 Goncrete I otal l~~,{U~
~7,461,57~ I HH~
Above Ground Structures 126,918 17,177,741 !
429 Cont Equip Storage Bldg Conc(ete' (LLR 684 102,533 3
Cont Equip Storage Bldg Steel 87 3,113 0
Gas Stack Abo\\e Grade 2,237 335,550 11 Hot Machine Shop Concrete 2,929 439,328 14 Hot Machine Shop Steel 330 11,792 0
New Off Gas Vault (SAS Bldg) 10,984 1,647,604 53 Radwaste Treatment Building Concrete 18,461 2,769,109 20 Radwaste Treatment Building Steel 2,197 78,466 3
Refueling Building Concrete 17,857 2,678,624 89 Refueling Building Steel 6,354 226,917 7
Solid Radwaste Building Steel 767 27,375 1
Turbine Building +12 Concrete 48,178 7,226,645 175 Turbine Building + 12 Steel 6,542 233,646 8
Yard Structures Abo\\e Grade 4,557 683,540 22
~",
': ~J~~~.t~A.~',':'"
t t
~2~I)T; 1'"
- \\
- ',.',,- 21 Radwaste Discharge Line I
Misc, RCA Areas incl Upper Yard 467,
70,000 2
Below Ground Structures 503,714 :
67,499,476 1,030 Cont Equip Storage Bldg (LLRW Hand E 603 90,450 3
Gas Stack Below Grade 5,090 763,500 25 Hot Machine Shop Slab 1,097 451,120 15 New Off Gas Vault (SAS Bldg) 13,136 1,970,472 64 Radwaste Treatment Building 3,197 479,607 15 Spent Fuel Pool Walls 12,716 1,907,400 62 Refueling Building 20,253 3,037,970 206 Solid Waste Vault 1,418 128,291 4
Solid Radwaste Building Below Grade 1,610 305,608 10 Offgas Tunnel South Offgas Tunnel North 8,129 1,219,420 39 Offgas Tunnel EW Units 1, 2, & 3 Circ Water Piping 14,453 2,167,900 161 Embedded Pipe (TB, RFB, LRW, & HM~
3,509 !
526,410 !
17 Radwaste Discharge Line 2,308 !
346,140 :
11 Page 87 of 120
TABLE 5.4 Cont'd WASTE DISPOSAL
SUMMARY
-INTERMODALS Page 88 of 120
Decommissioning Project Report for Humboldt Bay Power Plant Unit 3 Rev. 0 The analysis to estimate the costs to decommission HBPP Unit 3 relied upon the site-specific, technical information developed for previous analyses. The estimate also incorporates additional activities and considerations which have been identified as a result of the ongoing planning, implementation, and experience. While not an engineering study, the analysis provides PG&E with sufficient information to assess its financial obligations, as they pertain to completing the decommissioning of HBPP Unit 3.
The estimates described in this report are based on numerous fundamental assumptions, including regulatory requirements, stakeholder input, project contingencies, low-level radioactive waste disposal practices, high-level radioactive waste management options, and site restoration requirements. The decommissioning scenario reflects the fact that all spent fuel has been transferred to the ISFSI and it will remain in the ISFSI until such time that the DOE can complete the transfer of the assemblies to its repository.
The cost projected to complete decommissioning of HBPP Unit 3 is $727.6 million (including contingency) in 2011 dollars.
The primary cost contributors, identified in Table 6.1 are either labor-related or associated with the management and disposition of the radioactive waste. Staffing is the largest single contributor to the overall cost. The magnitude of the expense is a function of both the size of the organization required to manage the decommissioning, as well as the duration of the program.
The size and composition of the organization varies with the decommissioning phase and associated site activities.
As described in this report, spent fuel has been transferred to the ISFSI and will remain there until the DOE is able to receive it. Dry storage of the fuel under a separate license provides additional flexibility in the event the DOE is not able to meet the current timetable for completing the transfer of assemblies to an off-site facility and minimizes the associated caretaking expenses.
The cost for waste disposal includes only those costs associated with the controlled disposition of the low-level radioactive waste generated from decontamination and dismantling activities, including plant equipment and components, structural material, filters, resins and dry-active waste.
As described in Section 5, disposal of the radioactive material, including concrete and structural steel, as well as the highly radioactive material, is sent to either a currently licensed LLRW facility (Class A waste) or a licensed Class Band C waste burial site. Highly activated reactor vessel components (GTCC), requiring additional isolation from the environment, are packaged for geologic disposal and are stored at the ISFSI with the spent fuel, albeit in a separate container.
The cost of geologic disposal is based upon a cost equivalent for spent fuel.
Removal costs reflect the labor-intensive nature of the decommissioning process, as well as the management controls required to ensure a safe and successful program. Decontamination and packaging costs also have a large labor component that is based upon prevailing wages.
The reported cost for transport includes the tariffs and surcharges associated with moving large components and/or overweight shielded casks overland, as well as the general expense, e.g.,
Page 89 of 120
Decommissioning Project Report for Humboldt Bay Power Plant Unit 3 Rev. a labor and fuel, of transporting material to the destinations identified in this report. For purposes of this analysis, material is primarily moved overland by truck.
License termination survey costs are associated with the labor intensive and complex activity of verifying that contamination has been removed from the site to the levels specified by the regulating agency. This process involves a systematic survey of the surrounding environs, sampling, isotopic analysis, and documentation of the findings. The status of any plant components and materials not removed in the decommissioning process will also require confirmation and will add to the expense of surveying the facilities alone.
The remaining costs include allocations for heavy equipment and temporary services, as well as for other expenses such as regulatory fees and the premiums for nuclear insurance. While site operating costs are greatly reduced following the final cessation of plant operations, certain administrative functions do need to be maintained either at a basic functional or regulatory level.
Page 90 of 120
Year PG&E Labor 2011
$2.7 2012 16.5 2013 15.1 2014 12.0 2015 11.0 2016 9.2 2017 10.0 2018 8.6 2019 5.2 2020 3.4 2021 3.2 2022 3.2 2023 3.2 2024 3.2 2025 3.2 Total
$109.9 Expended and Collected From Trust Decommissioning Project Report for Humboldt Bay Power Plant Unit 3 TABLE 6.1 PACIFIC GAS AND ELECTRIC COMPANY CASH FLOW FOR DECOMMISSIONING HBPP UNIT 3 (IN MILLIONS OF 2011 DOLLARS)
Equipment &
Process &
Materials Contractor Labor Burial
$0.6
$4.6
$1.6 1.9 50.2 13.0 4.1 84.9 27.8 2.6 103.2 28.5 2.1 45.0 24.9 1.3 45.3 18.9 0.9 26.6 9.8 0.3 12.6 8.3 3.3 1.3 0.9 0.9 0.9 1.4 4.8
$13.9
$385.9
$132.8 Total Decommissioning Cost Estimate Rev. 0 Other Total
$(0.3)
$9.2 1.6 81.7 22.9 154.9 26.7 173.0 13.0 96.0 12.2 86.9 8.1 55.3 4.9 34.6 1.4 9.9 0.7 5.4 0.6 4.8 0.6 4.8 0.6 4.8 0.8 5.5 2.2 10.2
$95.8
$736.82
$245.6
$982.4 2
This number is the sum of the total remaining cost to decommission Humboldt Unit 3 from January 1, 2012 to 2025
($727.6 million) plus costs incurred in 2011 but not recovered from the trust fund until 2012 ($9.2 million).
Page 91 of 120
5 REFERENCES Decommissioning Project Report for Humboldt Bay Power Plant Unit 3 Rev. 0
- 1.
U.S. Code of Federal. Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72, "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988
- 2.
U.S. Nuclear Regulatory Commission, Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors," October 2003
- 3.
U.S. Code of Federal Regulations, Title 1 0, Part 20, Subpart E, "Radiological Criteria for License Termination"
- 4.
U.S. Code of Federal Regulations, Title 10, Parts 20 and 50, "Entombment Options for Power Reactors," Advanced Notice of Proposed Rulemaking, Federal Register Volume 66, Number 200, October 16, 2001
- 5.
U.S.
Code of Federal Regulations, Title 10, Parts 2,
50 and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61 (p 39278 et seq.), July 29, 1996
- 6.
"Nuclear Waste Policy Act of 1982 and Amendments," U.S. Department of Energy's Office of Civilian Radioactive Management, 1982
- 7.
DOE/RW-0604, "Project Decision Schedule," U.S. Department of Energy's Office of Civilian Radioactive Waste Management, January 2009
- 8.
U.S. Code of Federal Regulations, Title 10, Part 50, "Domestic Licensing of Production and Utilization Facilities," Subpart 54 (bb), "Conditions of Licenses"
- 9.
U.S. Code of Federal Regulations, Title 10, Part 61.55, "Waste classification"
- 10.
"Low-Level Radioactive Waste Policy," Public Law 96-573,1980
- 11.
"Low-Level Radioactive Waste Policy Amendments Act of 1985," Public Law 99-240,.
January 15, 1986
- 12.
"Establishing an Appropriate Disposal Rate for Low Level Radioactive Waste During Decommissioning", Robert A Snyder NEWEX, Revision 0, July 2008
- 13.
U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, "Radiological Criteria for License Termination," Federal Register, Volume 62, Number 139 (p39058 et seq.),
July 21, 1997
- 14.
"Establishment of Cleanup Levels for CERCLA Sites with Radioactive Contamination," EPA Memorandum OSWER No. 9200.4-18, August 22, 1997 Page 92 of 120
Decommissioning Project Report for Humboldt Bay Power Plant Unit 3 Rev. 0
- 15.
U.S. Code of Federal Regulations, Title 40, Part 141.16, "Maximum contaminant levels for beta particle and photon radioactivity from man-made radionuclides in community water systems"
- 16.
"Memorandum of Understanding Between the Environmental Protection Agency and the Nuclear Regulatory Commission: Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites," OSWER 9295.8-06a, October 9, 2002
- 17.
SAFSTOR Decommissioning Plan for the Humboldt Bay Power Plant, Unit No.3, July 1984
- 18.
Preliminary Shutdown Decommissioning Activities Report, PG&E letter HBL-09-009 dated June 30, 2009
- 19.
"Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM),"
NUREG/CR-1575, Rev. 1, EPA 402-R-97 -016, Rev. 1, August 2000
- 20.
T.S. LaGuardia et aI., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986
- 21.
W.J.
Manion and T.S. LaGuardia, "Decommissioning Handbook," U.S. Department of Energy, DOE/EV/10128-1, November 1980
- 22.
"Building Construction Cost Data 2004," Robert Snow Means Company, Inc., Kingston, Massachusetts
- 23.
Project and Cost Engineers' Handbook, Second Edition, p. 239, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, 1984
- 24.
"Technical Position Paper for Establishing an Appropriate Contingency Factor for Inclusion in the Decommissioning Revenue Requirements", Study Number: DECON-POS-H002, Revision A, Status: Preliminary (provided by PG&E)
- 25.
"Strategy for Management and Disposal of Greater-Than-Class C Low-Level Radioactive Waste," Federal Register Volume 60, Number 48 (p 13424 et seq.), March 1995
- 26.
U.S. Department of Transportation, Title 49 of the Code of Federal Regulations, "Transportation," Parts 173 through 178, 1996.U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72, "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018+), June 27, 1988
- 27.
Tri-State Motor Transit Company, published tariffs, Interstate Commerce Commission (ICC), Docket No. MC-427719 Rules Tariff, March 2004, Radioactive Materials Tariff, January 2008
- 28.
"Microsoft Project 2003," Microsoft Corporation, Redmond, WA, 2002 Page 93 of 120
Decommissioning Project Report for Humboldt Bay Power Plant Unit 3
- 29.
"Atomic Energy Act of 1954." (68 Stat. 919)
- 30.
T.S. LaGuardia et aI., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986.
- 31.
DECON-POS-H010 (Soil Remediation) Enercon, 2009 (Compares three end-state conditions for HBPP; and is based on historical spill data and other industry soil remediation projects)
- 32.
DECON-POS-H009 (Removal of Sub-Grade Structures) Enercon, 2009
- 33.
Humboldt Bay Power Plant Decommissioning Capstone Document, June, 2012
- 34.
Kiewit Feasibility Study for Removal of the Caisson.
- 35.
Specification Section 01-11-01, Health and Safety Requirements, June, 2012 Rev. 0
- 36.
Calculated volumes of soils within the slurry ring wall and other miscellaneous RCA areas, by: P.M. Gent, Nov. 2012 Page 94 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 A photographic record of the Humboldt Bay Power Plant site and surrounding area has been compiled by PG&E to show the evolution of construction and demolition at the facility. The first available photograph is from about 1940 and shows the bay and the point upon which the site would ultimately be developed Page 95 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 In the late 1940s, the area that would become known as King Salmon was starting to take shape Future King Salmon Development Rev. 0 Page 96 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 A construction site for HBPP Unit 1 was established in the late 1940s Rev. 0 Page 97 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 HBPP Unit 1 was completed in the early 1950s and construction of Unit 2 was underway. The photograph also shows the progress of the King Salmon development.
Page 98 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 By the mid-1950s, both of the fossil units were operational and the King Salmon development was well established.
Page 99 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 HBPP Unit 3 was constructed in the earl 19608 and became 0 rational in 1963.
Rev. 0
~~=~~
Also installed were two Mobile Emergency Power Production Systems that were used to supplement the grid during peak loads and in the event of an unexpected plant outage.
Page 100 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 In the same time frame) the King Salmon area was nearly fully developed.
Rev. 0 Kina Salmon Develooment Page 101 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 Unit 3 was shut down for the last time in 1976. Several years after the shutdown, an earthquake damaged the Vent Stack. Since it was no longer required for plant operations, PG&E opted to remove it.
Page 102 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 In the early 2000s, the site for the future Independent Spent Fuel Storage Installation (ISFSI) was selected.
Location of the future ISFSI Page 103 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 Infrastructure (road) was constructed to facilitate ISFSI construction and other site needs.
Page 104 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 The ISFSI was completed in 2008. In preparation for the shutdown and decommissioning of the fossil units (including the two MEPPS Units), construction of a new Humboldt Bay Generating Station (HBGS) was undertaken in about 2009. Additional infrastructure, in the form of trailers, was needed to support construction as the planning effort for both fossil and nuclear decommissioning. To accommodate the increased number of personnel at the site, one fuel oil tank was removed and a parking lot constructed.
Note: The site is extremely congested with facilities and office trailers. This condition caused significant interferences between adjacent activities, and limited the scope of work performed at any given time.
~--------------------~
Page 105 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 BGS construct took about two years. Concurrent development significantly reduced usable and complicated coordination of activities.
Page 106 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 While construction of the HBGS was ongoing, the planning and initial decommissioning phases were started on Unit 3. The initial phases included construction of the additional infrastructure needed to support decommissioning (i.e., Count Room) and relocating the spent nuclear fuel to the ISFSI Major capital improvements were required to support Decommissioning work such as a new Count Room, Access Control, Laydown Areas, Office Trailers, parking, roads, and utilities to service these facilities.
Page 107 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Rev. 0 Upon completion of the new HBGS, the old fossil units were shut down and their decommissioning was immediately started as Nuclear Decommissioning continued. Once again, site congestion caused intetierences that restricted work. Additional improvements were also needed, such as a Waste Handling Tent, a truck scale and two radiation portal monitors.
Once the HBGS was operational, Units 1 and 2 were shut down, decommissioning of those units started, and the last large oil tank removed.
Demolition Started Page 108 of 120
Attachment A Site History of Humboldt Bay Power Plant Unit 3 Demolition of Units 1 and 2 above ground structures was completed in 2011.
Fossil Demolition complete Rev. 0 The completion of fossil demolition made room for staging demolition of the Turbine Building.
However, space was soon lost to a 60 Kv substation upgrade project that began in 2012, continuing the challenge of coordinating interferences.
Page 109 of 120
Attachment B Rev. 0 List of Subject Matter Experts Personnel Decommissioning Sites/Projects Scope of Work Decommissioning Manager TOCDF, PCAPP, JACADS, Oyster Planning, Engineering, Scheduling, Creek, Saxton Work Packages, Characterization, Accident Analyses, ISFSI, Implementation, Design for Closure Decommissioning Project Trojan, FWENC, ME Yankee, CT Procedures, Planning, ISFSI, Assistant Yankee, Fort Calhoun Assessment, CAP, Cask Loading Supervisor, Technical Director, Readiness Review Conceptual Planning Lead JACADS, Savannah River Conceptual Planning, Rigging Engineering Field Engineers JACADS Conceptual Planning, Rigging Engineering Decommissioning Estimators CT Yankee, ME Yankee, Berkeley Planning, Construction (UK), Hanford, INEL Management, Project Management Work Package Writers NASA Plumbrook, Big Rock Point, Field Supervisor, Planning, Yankee Rowe, ME Yankee, CT Procedures, Commodity Removal, Yankee, Advanced Medical Work Planning, Decon Tech, Services, Braidwood, Indian Point, Decon-Demo Supervisor, Decom Seco, Los Alamos National Lab Site Supervisor Job Supervisors CT Yankee, Hanford, Yankee Operations, Maintenance, Ground Rowe, ME Yankee Water Controls, Supervision, QA, QC, CAP, Procedures, Instructional Technologist, ISFSI Cask Loading Supervisor I nstrumentation Respiratory Rancho Seco, Trojan Rad Engineering Protection Supervisor Special Projects - ISFSI and Trojan, FWENC, ME Yankee, CT Fuel Transfer, Program Reduction, Reactor Vessel Removal Yankee, Yankee Rowe Final Status Survey, Management, Oversight Rad Waste Rancho Seco, Camp Parks, Rad Waste Management, Project Packaging/Transportation Hanford, San Onofre, GE Management Supervisor Vallecitos Page 110 of 120
Attachment B Rev. 0 List of Subject Matter Experts Personnel Decommissioning Sites/Projects Scope of Work Decommissioning Trainer Rancho Seco, NASA Plumbrook, Training, MARRSIM, Oak Ridge Dismantlement, Remediation, SR HP Tech, FSS Technical Writer Fort St. Vrain, Rancho Seco, Big Accident Analyses, Procedures, Rock Point, Army Materials Decommissioning Planning, Technology Laboratory Facilities, Program Assessments, Army Materials Technology Environmental Assessment, Laboratory Research Reactor License Termination Planning, Dose Modeling, Technical Bases Document Development, ODCM,
- FSS, Technical Oversight Zion, CT Yankee, Yankee Rowe, Decom Project Management, Zion, Rancho Seco, Ft Greely, La Decom Planning Management, Crosse Characterization, Seg mentation Planning Project Manager, Technical Saxton, Westinghouse Test Waste Management, Soil Oversight Reactor, UW Test Reactor, Remediation, MARRSIM, FSS, Heritage Minerals, Westinghouse Planning, Estimating, Licensing facilities, fuels facilities, metal Modifications and Interfaces, facilities, chemical facilities Characterization, Building Remediation, License Termination Technical Oversight ME Yankee, Saxton, Waste Management, Soil Westinghouse Test Reactor, Fuels Remediation, MARRSIM, FSS, Facilities, Metal Facilities, Planning, Estimating, Licensing Brookhaven National Labs, GE Modifications and Interfaces, Vallecitos, Oak Ridge National Characterization, Building Labs Remediation, License Termination Strategic Waste Disposal Hanford - Plutonium Finishing Waste Management, Final Status Manager Plant, on site laboratory, Tank Survey, Laboratory Services, Farm High Level Waste Environmental Compliance management; Hanford Plateau -
RCRA groundwater monitoring, corrective action; Dounreay (UK)
Page 111 of 120
Attachment B Rev. 0 List of Subject Matter Experts Personnel Decommissioning Sites/Projects Scope of Work Characterization Lead Honeywell UF6 Conversion Plant, Characterization, FSS, RP Support, Flannery Building Radium Facility, License Termination Support, Vallecitos, Oak Ridge National Building Remediation, Waste Laboratory DOE Complex, Idaho Packaging and Shipping, Building National Engineering and Demo, Decommissioning License Environmental Laboratory DOE
- Support, Complex, RMI Ashtabula Site, Monsanto Plutonium Facility, Ottawa Illinois Radium Dial, Weldon Springs DOE Facility, Battelle Columbus Laboratory, Knolls Atomic Power Laboratory, Westinghouse Hematite Facility Scheduler Hematite Fuel Fabrication Facility, Scheduler, Tank Remediation, DID Vallecitos, University of Planning Washington, Training and Research Reactor, Brookhaven National L.ab, Global Nuclear Fuels, Wilmington NC, East Tennessee Technology Park (ETTP), Oak Ridge, INEL Site Closure Manager Connecticut Yankee, Hanford, Decommissioning planning, In-Yankee Rowe, Brookhaven vessel segmentation oversight, National Lab, San Onofre, Magnox Decommissioning Waste South (5 sites), Oyster Creek, Minimization, Decommissioning Three Mile Island Assessments, Contaminated lands evaluation, Radiological Consulting for 233-S and Hanford reactors decommissioning, MARSSIM Final Status Survey Data Analysis, Bid Specification development and ALARA planning for the decommissioning of highly contaminated radwaste building at Oyster Creek, oversight of recovery efforts at Three Mile Island.
Page 112 of 120
Attachment B Rev. 0 List of Subject Matter Experts Personnel Decommissioning Sites/Projects Scope of Work FSS Engineer ETTP Oak Ridge, Yankee Rowe, Project Manager, FSS Engineer, Fermi 1, Maine Yankee, SONGS, License Termination Manager, FSS Plum Brook, Conn Yankee, Manager, AutoCad Engineer KAPL/SPRU Page 113 of 120
HBPP Organizational Flow Chart PG&E Senior Vice President 10/29/2012 I
HBPP DecQmmlss[oning ftI nager 76 I
HB,Pp Projects Superinten dant 66 I
HBPP Engineering J SafetY' Manager 5
Attachment C Site Management
~"iot VIce Pr@$fdent
- Cllief NucJear 'Officer H BPP Director/Plant Ma nag., < "cfear I
HBPP' Site Sewl<:esJ Training Manager t
elUdES IS $ 1 Rev. 0 HBP'P 0.puty Director HBP,P RadJation Pl'otectli'o ",
Manag@ri
~,-
I HBPP.
Waste 0 strategic ISlPosal age:r Man 6 7 I
HBPP Sl Man
- te Closure age-I" Page 114 of 120
HBPP Organizational Flow Chart Decommission -ng 101291201 2 I
DecommlssJonlng Projects Superintendent Pfojoct Iii.mag1t/"
CritiCal Patn projects
- RV SQgm~.nta 'co
- Sf P ean Up
- Ce$k6
- B & c: Vlfasie Job Sup rvisor I
bocommissionlng proJect ASSistant R PV f LR'I,{ Contract AdmlniMf.ator ob erg;, Sclutions. RV lntemals Entf !;l), SOlutiOnS LRW Si pel kemp RV Shell Attachment D Decommissioning Department Hepp Oir ttoO' Plant M anag '~r-Nucl ear Decommlssionlng Manager I
Pro jed fII aoagement ContrOls S.UpmVisor S,;stom safoty engineer/Risk r"arHlg~ment (0.5)
$Ito Support SUrvlcos Conlrac:t Admlnlsfrator Job Suporvlsor Rev. 0 DifcOrnrnlSsloning SPfttial ProJl.lets CAPSTONElCPUC GAP AnCl!ysls I
S ts Support Serv'lce$
JRC
- NCF I
Procurement SuperviSOr j-Procurem~nt Specialists
- J ProcurBm~n1 Assls.tant sr. COtll act COiiStllfaril Page 115 of 120
HBPP Organizational Flow Chart Oecom. Projects Superintendent 10/2912012 f
RFB Area Supervisor I
- ACCe1S SIH:Jt
- Suppression Chamber
- IN eavltt
.Admlnlstratl va support Fluor Projects CMtrols Specialist f ltH)t
$ to Safety Man;jlger Space Ll),Qistfcsf Job Super..,\\sor Contrad *Technlcal ltepre5eman~
I Fluor SIl9 Manager Fluor Job StJpcrvisors J
KiJV Rfrm afflltl9 Wmll Arga$
- Off G35 nnfl
- Valve <Jelfery
- Sla ck [~ipment Attachment E Projects Department Dewmmlssloning Managof Projects Superintendent :
Andrew C~done I
I Site Constru4;1:lon Mlmagtlr I l.
I
.* Umme uemD.
PrIme Contractor Administrative Support (O.:;,)
~VOI1t weeK Managers KI e\\'W1 NueloM POwilr Piant CIvil Worl(s Projec1s f luor SUe SUlp.erintendefit f lUOr "m~kl1lffpl)r Engineering ftJJ~ooll1.1 ed Engln~flng Ser\\*;ces c,
Asbe~tos Abatement C,*~L. Ille.
Decontamination FliJOt CQnsiruclJoJl Seryl (;eS Peahafl Inc.
Intake/Discharge Canal Rcmo,diaUon Nuclear Facllitv'Demo.
I--
Office Facllliy Demo.
I--
Stte Restor!'l.*,IQn Rev. 0 I
Document Control Spl)claiist VClCMt Civil WOrkS Cohtrac:t Admlnlslrator Subrnillals Te1:hnlcal R<!f)r(l-sol'lta1No I
E4lgrne ring Services Contractors URS WhlleliurCr.
Page 116 of 120
Engineering I Safety 10129/2012 I
Corr(lc;UlIf) Action I Dacums"l: Control SuperYisor I
ment Docu COni trt.ll SMlor Plarrt Clerk I
I Routing Clorll.s Rout ne prani Cll}rk Procedures lead Civll Engineering SUipe-rvJ sor Le ' QreI V~ it<:h ureh CMlfSlruclUrtll Engineers Englne'll'r Spechlilst Rigging OVllrslte Englneerlng Assistant Overhead
'" ocf'l3nita.1 Engillecdng I Work Control' Supervl$Of J2Ivaid Iqb!i,1
'" Otharue. 1 Eng-hour Work Contro! f Fle.ld Engineer Brett Muillns EJectr\\(;<'l1 Eng Inoo.r1 ng SUJ)ltMoor Ed Kahler E]oetri(;lll Ellgllleer Elsclrlcal field EngIneer Attachment F Engineering/Safety Department
!<IBPP Dlrectorl PI~Jl(
Manager - Nuclear Engln Ilorlngl Safety til anage r r-------,
PG&E PO'rmllUng II SUpport I
Fire & Safely Supervisor I
~~~
,~~~~""
Unit J SAFSTOR SuperYisor 1- --
Rev. 0 Decommissioning Operating facilltl8'S PM I
I I
I I
Discrete Offslia Supporl ContractQ.r~
Dceomllli stoning Shirt Specialist ~ I--
IndU$(rlal Hygl~nt~t I-Clearance CO (lrdlll~ f or
,--------Lr_
I I
t GWTSAccess ~
r---K-ahL'-or--'
Control dLRW<1 C~ *
- 00.. I EligihMrllig I
I WhltCllUrch Englne:eriog Administrative Supporl 1--
_ St. Control Operu1or Cilntrol Operator Control Techrllclan
~fta~~
I I L ___________ J l
I GTCCWclSfe Project L&ad GTCC Loadlllg Campaign Holtel:
Page 117 of 120
HBPP O rgan~zational Flow Chart Radi ati on Protection 10/29/2012 ACcess COntrOl OPS o PS RP Foroman I
OPS eattlott NEWEX. RP Technicians RP Teetitllclans HBPP Dlr&e.for J Pl an!
h1anager - Nuclear R.ad Prote--CtIQ" Managor RP COhSullants Attachment G -
Radiation Protection Department I
RPM Tren ding Proollctlol'l
$p(tclallm
- E llgi n (l~r (0,5)
RPGI!f1(1ral Foremari
- r----'l
___________ 1 RMC I
I foreman SAFSTOR RP ForemanlRP Tr~ill r OPSRP Deean Spv-cJalis1:
InV&llto,ry Control 1-----;
I OPS RP OPS RP Cooon Specialists L ____ I r r---=-........,
r l.J AdmltifHanVastel I
For(tman I
I -----.....
L---:.J r-....J---,
r-I Rr., C R P I
I RMC I
I 00(00 I
I RP Tethhlcian*!; I I
SpeGlalists I I
I I
I I
I OPS BarneU RP Decoo Techs SAFSTOR RP Technicians SAFSTOR RP Decon Specialists OPSRP Tecfmlclan Rev. 0 RP Engtneer
$u.f)l)rint~d('n l
-, I I
I I
Instrumentation iRP~ilN' u-r '
Do~ ml)lr)'
Respiratory RPALARA C()I1'Sultanl
$upervi$lor Pfot~ellon P l anfl~r Supervfsor lRW" Off Gas Tlitmel. &
I-I Outsi(loAlcas Dosimetry Field Insburnentatlon Turbine Bldg., Embedded Assistani s RlI'splratQIY Piping. Cleaning & Grouting Ptotu(;t lotl foreman R ~fyEtI Byl!d.lng I
I I
Ffeld Field IhslrUi1i&ntafion Instrlirli tmtation RP T6c:hnlclall s RP OOCOIm frl Specialist Page 118 of 120
HBPP Organizational Flow Chart Waste Disposal 10/29/2012 Radwasle Planner I'hdlologfcal engineer r
Tr"ansportaJIOll Supervisor Contract Adm!nlstrator &
Senior Techliical Adlilsor 1
__ I Admlllsirattvo Support Tralnlng/Admlnl Emorg0rit Fiil2d SUPPIHt I
NCF SUo M. nagor Job Supervisor Radwaste packaging Specialist r Shlp.plr'1g Speciall~t Shlp!,)lng II<
Materla!s Coordinator Jr. 'f.ochrl1clan J
t-Glove B" g
$upCfVlsor G'ove Bag Fabricator
. Rad Wor1<erJ Oper at or ($.
Unit 3 Attachment H Rev. 0 Radiological Materials Control, Count Room, and Environmental Departments I
Flnancl ~J Analyst
{ D.5 }
Engineering Support.
I en'llironm(Jnt~1 RemediaUon fllllJlagor I
environmental Speci<W1lst
'\\Iecanl I
if'nmdtn9 engineer W.S)
---L--l I
Interim I EnvlronmCll1al I I
R{!m~Cl I:3I i on I M<!n~ger I
l iiiiiiii....... liiiiiiiI ___ ___
IIHI "-'
En'llirohmental Coordinator (0.5)
(0.5) field Support Contractor Reps*INCf.
QSC M!rk rJicbols HBPP OlrectorT Plam Manag r - Nuclear Environmental Asslstanf I
Waste r.1anagcment Waste Specialist N!'IC3r}.CY)
Environ me-nf al Assistant asp n on" FlP DtJcon Specialists Waste Consull llr.ts RMC Foreman I AomJnlHaz WasU~
Foroman Rrlle RP TechhldailS count Room I eIJiu4iflts Sup~TVjSt:lr Silo Closuro Manager I License Termlnatlonl r- - I Engl neer I
J
'-_--.,.....-_---1
______ J Count Room
'QJ8ffiOln Count Room RP Tocllnlcians Count Room RP De<eon Specialist I
FSS&L.TP Consu!tin~
Englnoo.r FSS Englne!!r FSS R"port Writer 1";:';:'
Admin A$~ts'ant o
FSS Technician FSS Fomman FSS Labor Support De ~onner Page 119 of 120
Site Serv*ces ITrain"ng 10129/2012 Security Sysfem i-
$p~(;i3list Access r--, Autll OJ"'~atl onlFFO
~~
I-----
Security Trainer Procedure Wri!e-r V".;ant I
I J$rSI Shift ISFSI Shift Ma lia~e r ril anag(Jli' I
I ISFSI ISfSI Security ()ffic ers Sftc<urlfy Off1cers Attachment I Site Services/Training Department HBPP C I(~cIOf I Plant
~'arlage:r -
NLlI;I~ar Site ServicesJTrainlng M anager I SFSI' Shift Manager ISFst Security Officers I
ISFSI Shlft
,nanagf1irfEP I
ISfSi SeCiUrily Officers Rev. 0 I
.SFSI Shift Managur r-I ISF'SI I-Security Officers f--
I SUe Tralnlng Coordinator Tralnln!.J Asslstanf rn 5tf'Uc to~
RP Tr.alner
, Licensing Supervisor (PG&E Gene.a:1 om e)
L 1<: onslng support OCP!='
Page 120 of 120