Category:Decommissioning Funding Plan DKTs 30
MONTHYEARGO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-21-149, Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates2021-12-16016 December 2021 Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates GO2-19-073, Supplemental Information for Plant Decommissioning Fund Status Report2019-04-16016 April 2019 Supplemental Information for Plant Decommissioning Fund Status Report GO2-17-065, Plant Decommissioning Fund Status Report2017-03-20020 March 2017 Plant Decommissioning Fund Status Report GO2-15-049, Submittal of Decommissioning Fund Status Report2015-03-26026 March 2015 Submittal of Decommissioning Fund Status Report GO2-13-051, Decommissioning Fund Status Report2013-03-28028 March 2013 Decommissioning Fund Status Report GO2-12-183, & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan2012-12-17017 December 2012 & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan GO2-09-059, Decommissioning Fund Status Report2009-03-31031 March 2009 Decommissioning Fund Status Report GO2-07-057, Decommissioning Fund Status Report2007-03-27027 March 2007 Decommissioning Fund Status Report ML0309806432003-03-31031 March 2003 Docket No. 50-397, Decommissioning Fund Status Report 2023-03-15
[Table view] Category:40
MONTHYEARGO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-21-149, Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates2021-12-16016 December 2021 Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates GO2-21-012, License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35)2021-04-28028 April 2021 License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) GO2-19-073, Supplemental Information for Plant Decommissioning Fund Status Report2019-04-16016 April 2019 Supplemental Information for Plant Decommissioning Fund Status Report GO2-17-065, Plant Decommissioning Fund Status Report2017-03-20020 March 2017 Plant Decommissioning Fund Status Report GO2-15-049, Submittal of Decommissioning Fund Status Report2015-03-26026 March 2015 Submittal of Decommissioning Fund Status Report GO2-13-051, Decommissioning Fund Status Report2013-03-28028 March 2013 Decommissioning Fund Status Report GO2-12-183, & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan2012-12-17017 December 2012 & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan GO2-12-026, License Renewal Application Third Annual Update2012-02-16016 February 2012 License Renewal Application Third Annual Update GO2-10-094, License Renewal Application First Annual Update2010-07-16016 July 2010 License Renewal Application First Annual Update ML1011600952010-04-21021 April 2010 State of Wa Ship Ape Letter CGS License Renewal GO2-09-153, Submittal of an Amendment Request for Approval of Cyber Security Plan2009-11-16016 November 2009 Submittal of an Amendment Request for Approval of Cyber Security Plan GO2-09-059, Decommissioning Fund Status Report2009-03-31031 March 2009 Decommissioning Fund Status Report GO2-07-057, Decommissioning Fund Status Report2007-03-27027 March 2007 Decommissioning Fund Status Report ML0309806432003-03-31031 March 2003 Docket No. 50-397, Decommissioning Fund Status Report 2023-03-15
[Table view] Category:50
MONTHYEARGO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-21-149, Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates2021-12-16016 December 2021 Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates GO2-19-073, Supplemental Information for Plant Decommissioning Fund Status Report2019-04-16016 April 2019 Supplemental Information for Plant Decommissioning Fund Status Report GO2-17-065, Plant Decommissioning Fund Status Report2017-03-20020 March 2017 Plant Decommissioning Fund Status Report GO2-15-049, Submittal of Decommissioning Fund Status Report2015-03-26026 March 2015 Submittal of Decommissioning Fund Status Report GO2-13-051, Decommissioning Fund Status Report2013-03-28028 March 2013 Decommissioning Fund Status Report GO2-12-183, & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan2012-12-17017 December 2012 & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan GO2-09-059, Decommissioning Fund Status Report2009-03-31031 March 2009 Decommissioning Fund Status Report GO2-07-057, Decommissioning Fund Status Report2007-03-27027 March 2007 Decommissioning Fund Status Report ML0309806432003-03-31031 March 2003 Docket No. 50-397, Decommissioning Fund Status Report 2023-03-15
[Table view] Category:70
MONTHYEARGO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-21-149, Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates2021-12-16016 December 2021 Independent Spent Fuel Storage Installation - Decommissioning Cost Estimate and Decommissioning Funding Plan - 2021 Updates GO2-21-012, License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35)2021-04-28028 April 2021 License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) GO2-19-073, Supplemental Information for Plant Decommissioning Fund Status Report2019-04-16016 April 2019 Supplemental Information for Plant Decommissioning Fund Status Report GO2-17-065, Plant Decommissioning Fund Status Report2017-03-20020 March 2017 Plant Decommissioning Fund Status Report GO2-15-049, Submittal of Decommissioning Fund Status Report2015-03-26026 March 2015 Submittal of Decommissioning Fund Status Report GO2-13-051, Decommissioning Fund Status Report2013-03-28028 March 2013 Decommissioning Fund Status Report GO2-12-183, & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan2012-12-17017 December 2012 & Independent Fuel Storage Installation, Submittal of Decommissioning Cost Estimate and Decommissioning Funding Plan GO2-12-026, License Renewal Application Third Annual Update2012-02-16016 February 2012 License Renewal Application Third Annual Update GO2-10-094, License Renewal Application First Annual Update2010-07-16016 July 2010 License Renewal Application First Annual Update ML1011600952010-04-21021 April 2010 State of Wa Ship Ape Letter CGS License Renewal GO2-09-153, Submittal of an Amendment Request for Approval of Cyber Security Plan2009-11-16016 November 2009 Submittal of an Amendment Request for Approval of Cyber Security Plan GO2-09-059, Decommissioning Fund Status Report2009-03-31031 March 2009 Decommissioning Fund Status Report GO2-07-057, Decommissioning Fund Status Report2007-03-27027 March 2007 Decommissioning Fund Status Report ML0309806432003-03-31031 March 2003 Docket No. 50-397, Decommissioning Fund Status Report 2023-03-15
[Table view] Category:Letter type:GO
MONTHYEARGO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments GO2-22-110, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor2022-10-17017 October 2022 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor GO2-22-096, Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-10-0404 October 2022 Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-085, Docket No. 50-397, Evacuation Time Estimate Analysis2022-08-30030 August 2022 Docket No. 50-397, Evacuation Time Estimate Analysis GO2-22-075, Response to Request for Additional Information Related to Revised Pressure-Temperature Limit Curves2022-07-11011 July 2022 Response to Request for Additional Information Related to Revised Pressure-Temperature Limit Curves GO2-22-072, Summary of Changes and Analysis for Revision 57 of PPM 13.14.4 - Emergency Equipment Maintenance and Testing2022-07-11011 July 2022 Summary of Changes and Analysis for Revision 57 of PPM 13.14.4 - Emergency Equipment Maintenance and Testing GO2-22-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process2022-05-25025 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process 2024-07-30
[Table view] |
Text
ENERGY Donald W. Gregoire Columbia Generating Station NORTHWEST P.O. Box 968, PE20 Richland, WA 99352-0968 Ph. 509-377-86161 F. 509-377-4674 dwgregoire@energy-northwest.com April 16, 2019 GO2-19-073 10 CFR 50.75(f)(1)
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397 SUPPLEMENTAL INFORMATION FOR PLANT DECOMMISSIONING FUND STATUS REPORT
Reference:
Letter from D.W. Gregoire, Energy Northwest, to U.S. Nuclear Regulatory Commission, "Plant Decommissioning Fund Status Report," GO2-19-052, ADAMS ML19079A209, dated March 10, 2019.
Dear Sir or Madam:
In response to a request for additional information regarding the original submittal of Columbia Generating Station's Plant Decommissioning Fund Status Report (Reference), Energy Northwest is submitting an updated Decommissioning Funding Schedule (Attachment 1).
The withdrawal from the account in FY 2019 was to pay TLG Services, Inc., to create an updated Decommissioning Cost Analysis for Columbia Generating Station.
There are no commitments being made to the Nuclear Regulatory Commission by this letter. Should you have any questions or require additional information pertaining to this report, please contact S.A. Nappi at (509) 377-4598.
Executed on the Jfi!:._ day of A,r; f ,2019.
Respectfu ly,
~
D.W. Gregoire Manager, Regulatory Affairs : Columbia Generating Station - Updated Decommissioning Funding Schedule cc: NRC Region IV Administrator C.D. Sonoda - BPA/1399 NRC NRR Project Manager W.A. Horin - Winston & Strawn NRC Sr. Resident Inspector - 988C
GO2-19-073 Page 1 of 1 Columbia Generating Station - Updated Decommissioning Funding Schedule Payments Fiscal From Sub-Account Year* Payment Interest Earned Account Balance FY 2019 $ 3,741,208 $ 17,427,760 $(150,000)1 $ 311,481,627 FY 2020 $ 3,890,856 $ 18,688,898 $ - $ 334,061,381 FY 2021 $ 4,046,490 $ 20,043,683 $ - $ 358,151,554 FY 2022 $ 4,208,350 $ 21,489,093 $ - $ 383,848,997 FY 2023 $ 4,376,684 $ 23,030,940 $ - $ 411,256,621 FY 2024 $ 4,551,751 $ 24,675,397 $ - $ 440,483,769 FY 2025 $ 4,733,821 $ 26,429,026 $ - $ 471,646,616 FY 2026 $ 4,923,174 $ 28,298,797 $ - $ 504,868,587 FY 2027 $ 5,120,101 $ 30,292,115 $ - $ 540,280,803 FY 2028 $ 5,324,905 $ 32,416,848 $ - $ 578,022,556 FY 2029 $ 5,537,901 $ 34,681,353 $ - $ 618,241,811 FY 2030 $ 5,759,417 $ 37,094,509 $ - $ 661,095,736 FY 2031 $ 5,989,794 $ 39,665,744 $ - $ 706,751,274 FY 2032 $ 6,229,386 $ 42,405,076 $ - $ 755,385,737 FY 2033 $ 6,478,561 $ 45,323,144 $ - $ 807,187,442 FY 2034 $ 6,737,704 $ 48,431,247 $ - $ 862,356,393 FY 2035 $ 7,007,212 $ 51,741,384 $ - $ 921,104,988 FY 2036 $ 7,287,500 $ 55,266,299 $ - $ 983,658,788 FY 2037 $ 7,579,000 $ 59,019,527 $ - $ 1,050,257,315 FY 2038 $ 7,882,160 $ 63,015,439 $ - $ 1,121,154,914 FY 2039 $ 8,197,447 $ 67,269,295 $ - $ 1,196,621,655 FY 2040 $ 8,525,345 $ 71,797,299 $ - $ 1,276,944,300 FY 2041 $ 8,866,358 $ 76,616,658 $ - $ 1,362,427,316 FY 2042 $ 9,221,013 $ 81,745,639 $ - $ 1,453,393,968 FY 2043 $ 9,589,853 $ 87,203,638 $ - $ 1,550,187,459 FY 2044 $ 9,973,447 $ 93,011,248 $ - $ 1,653,172,153
- Energy Northwest's Fiscal Year ends June 30 1
Estimated cost of updated Decommissioning Cost Analysis paid in FY 2019