Category:Letter type:GO
MONTHYEARGO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments GO2-22-110, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor2022-10-17017 October 2022 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor GO2-22-096, Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-10-0404 October 2022 Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b 2024-09-24
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARGO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24047A0422024-03-0707 March 2024 Issuance of Amendment No. 273 Renewed Facility Operating License and Technical Specification Clean Up GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-22-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process2022-05-25025 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process GO2-22-001, License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-02-0303 February 2022 License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-21-133, License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2021-11-0909 November 2021 License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GO2-21-016, License Amendment Request to Change Technical Specification 3.4.11 Reactor Coolant System Pressure and Temperature Limits2021-10-13013 October 2021 License Amendment Request to Change Technical Specification 3.4.11 Reactor Coolant System Pressure and Temperature Limits GO2-21-042, License Amendment Request to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement2021-05-0808 May 2021 License Amendment Request to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement GO2-20-104, On-Site Cooling System Sediment Disposal2020-12-21021 December 2020 On-Site Cooling System Sediment Disposal GO2-20-108, License Amendment Request to Adopt TSTF-439, Elinate Second Completion Times Limitng Time from Discovery of Failure to Meet an LCO2020-12-0202 December 2020 License Amendment Request to Adopt TSTF-439, Elinate Second Completion Times Limitng Time from Discovery of Failure to Meet an LCO GO2-20-095, Application to Revise Technical Specifications to Adopt TSTF-582, 'Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-09-24024 September 2020 Application to Revise Technical Specifications to Adopt TSTF-582, 'Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements GO2-20-063, Exigent License Amendment Request for Extension of Implementation Period for Amendment 255 Change to Control Room Air Conditioning System2020-04-15015 April 2020 Exigent License Amendment Request for Extension of Implementation Period for Amendment 255 Change to Control Room Air Conditioning System GO2-20-052, Exigent License Amendment Request for One-Time Change to Completion Times for Inoperable Electrical Distribution Systems2020-04-15015 April 2020 Exigent License Amendment Request for One-Time Change to Completion Times for Inoperable Electrical Distribution Systems GO2-20-004, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR2020-01-27027 January 2020 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR GO2-20-008, License Amendment Request to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Using the Consolidated Line Item Improvement Process2020-01-27027 January 2020 License Amendment Request to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Using the Consolidated Line Item Improvement Process GO2-19-090, License Amendment Request to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-08-15015 August 2019 License Amendment Request to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program GO2-19-053, License Amendment Request to Remove Operating License Condition 2.C.(11) and Attachment 32019-03-27027 March 2019 License Amendment Request to Remove Operating License Condition 2.C.(11) and Attachment 3 GO2-19-027, License Amendment Request for Licensing Basis Change to Control Room Air Conditioning System2019-02-25025 February 2019 License Amendment Request for Licensing Basis Change to Control Room Air Conditioning System GO2-17-137, License Amendment Request to Update Appendix B to the Renewed Facility Operating License to Incorporate 2017 Biological Opinion2017-12-18018 December 2017 License Amendment Request to Update Appendix B to the Renewed Facility Operating License to Incorporate 2017 Biological Opinion GO2-17-181, License Amendment Request to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-12-12012 December 2017 License Amendment Request to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements GO2-17-038, License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-10-23023 October 2017 License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. GO2-17-028, License Amendment Request for Change to Technical Specification 3.5.1, ECCS-Operating.2017-07-25025 July 2017 License Amendment Request for Change to Technical Specification 3.5.1, ECCS-Operating. GO2-17-009, License Amendment Request - Revise Technical Specification 5.5.12 for Permanent Extension of Type a Test and Type C Leak Rate Test Frequencies2017-03-27027 March 2017 License Amendment Request - Revise Technical Specification 5.5.12 for Permanent Extension of Type a Test and Type C Leak Rate Test Frequencies GO2-17-062, License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 22017-03-27027 March 2017 License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2 GO2-16-119, License Amendment Request for One-Time 7 Day Extension of Completion Time for TS Condition 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A2016-11-0808 November 2016 License Amendment Request for One-Time 7 Day Extension of Completion Time for TS Condition 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A ML16243A5152016-08-30030 August 2016 License Amendment Request for Reclassifying Quality Group of Low Temperature Portions of Reactor Water Cleanup System ML16244A8332016-08-30030 August 2016 License Amendment Request for Reclassifying Quality Group of Low Temperature Portions of Reactor Water Cleanup System - Drawing M523-1-3, Revision 10, Flow Diagram Reactor Water Clean-up System Radwaste Bldg. ML16210A5282016-07-28028 July 2016 Request for Amendment to Emergency Plan GO2-16-087, License Amendment Request for Changes to Technical Specification 2.1.1, Reactor Core SLs2016-07-12012 July 2016 License Amendment Request for Changes to Technical Specification 2.1.1, Reactor Core SLs GO2-16-096, License Amendment Request to Revise Operating License and Technical Specifications for Measurement Uncertainty Recapture Power Uprate2016-06-28028 June 2016 License Amendment Request to Revise Operating License and Technical Specifications for Measurement Uncertainty Recapture Power Uprate GO2-16-079, Erratum for License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 and SR 3.4.4.1 Safety/Relief Valves (Srvs) Setpoint Lower Tolerance2016-05-18018 May 2016 Erratum for License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 and SR 3.4.4.1 Safety/Relief Valves (Srvs) Setpoint Lower Tolerance GO2-16-046, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 and SR 3.4.4.1 Safety/Relief Valves (Srvs) Setpoint Lower Tolerance2016-05-10010 May 2016 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 and SR 3.4.4.1 Safety/Relief Valves (Srvs) Setpoint Lower Tolerance GO2-16-047, License Amendment Request to Revise Technical Specifications to Adopt TSTF-522, Revision 02016-03-0303 March 2016 License Amendment Request to Revise Technical Specifications to Adopt TSTF-522, Revision 0 GO2-15-070, Application for Technical Specification Change (TSTF-427) to Add LCO 3.0.9 on the Unavailability of Barriers Using the Consolidated Line Item Improvement Process2015-09-0202 September 2015 Application for Technical Specification Change (TSTF-427) to Add LCO 3.0.9 on the Unavailability of Barriers Using the Consolidated Line Item Improvement Process GO2-16-112, License Amendment Request for Reclassifying Quality Group of Low Temperature Portions of Reactor Water Cleanup System - Drawing M523-3, Revision 10, Flow Diagram Reactor Water Clean-up System Radwaste Bldg.2015-06-17017 June 2015 License Amendment Request for Reclassifying Quality Group of Low Temperature Portions of Reactor Water Cleanup System - Drawing M523-3, Revision 10, Flow Diagram Reactor Water Clean-up System Radwaste Bldg. GO2-15-075, Exigent License Amendment Request - Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1 Function 7 Scram Discharge Volume Water Level-High.2015-05-15015 May 2015 Exigent License Amendment Request - Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1 Function 7 Scram Discharge Volume Water Level-High. GO2-15-007, License Amendment Request for Adoption of Technical Specification Task Force Traveler-425, Revision 32015-03-17017 March 2015 License Amendment Request for Adoption of Technical Specification Task Force Traveler-425, Revision 3 ML14336A0062014-11-17017 November 2014 License Amendment Request for Technical Specification Change to Safety Limit Minimum Critical Power Ratio ML14268A2332014-09-0404 September 2014 Erratum for License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-423, Revision 1, Using the Consolidated Line Item Improvement Process GO2-14-126, License Amendment Request to Revise Technical Specification Surveillance Requirement for the Ultimate Heat Sink2014-08-22022 August 2014 License Amendment Request to Revise Technical Specification Surveillance Requirement for the Ultimate Heat Sink ML14234A4572014-08-12012 August 2014 License Amendment Request for Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-423, Revision 1, Using the Consolidated Line Item Improvement Process GO2-14-103, Proposed Revision to License Amendment Request to Adopt TSTF-493, Revision 4, Option a, and Response to Request for Additional Information2014-06-19019 June 2014 Proposed Revision to License Amendment Request to Adopt TSTF-493, Revision 4, Option a, and Response to Request for Additional Information ML14086A3892014-03-18018 March 2014 License Amendment Request to Revise Technical Specifications to Adopt TSTF-535, Revision 0 ML13316A0092013-10-31031 October 2013 License Amendment Request for Change to Emergency Core Cooling Systems Surveillance Requirements GO2-13-138, License Amendment Request for Adoption of TSTF-493, Revision 4, Option a2013-10-0202 October 2013 License Amendment Request for Adoption of TSTF-493, Revision 4, Option a ML13247A6592013-07-25025 July 2013 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF 477, Revision 3 2024-09-23
[Table view] Category:Technical Specification
MONTHYEARGO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-22-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process2022-05-25025 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process GO2-21-016, License Amendment Request to Change Technical Specification 3.4.11 Reactor Coolant System Pressure and Temperature Limits2021-10-13013 October 2021 License Amendment Request to Change Technical Specification 3.4.11 Reactor Coolant System Pressure and Temperature Limits GO2-20-004, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR2020-01-27027 January 2020 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR ML19343C0352019-12-0505 December 2019 Rev. 111 to Licensee Controlled Specifications Manual - Part 2 of 2 GO2-19-098, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules2019-09-12012 September 2019 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules GO2-19-123, Supplemental Information Related to Exigent License Amendment Request for Change to Technical Specification 3.8.7 Distribution Systems-Operating2019-08-19019 August 2019 Supplemental Information Related to Exigent License Amendment Request for Change to Technical Specification 3.8.7 Distribution Systems-Operating GO2-19-119, Exigent License Amendment Request for Change to Technical Specification 3.8.7 Distribution Systems - Operating2019-08-15015 August 2019 Exigent License Amendment Request for Change to Technical Specification 3.8.7 Distribution Systems - Operating ML17355A6562017-12-21021 December 2017 Technical Specification Bases GO2-17-181, License Amendment Request to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-12-12012 December 2017 License Amendment Request to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements GO2-17-194, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2017-11-15015 November 2017 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control GO2-17-022, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-522 Revision 02017-01-19019 January 2017 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-522 Revision 0 GO2-16-119, License Amendment Request for One-Time 7 Day Extension of Completion Time for TS Condition 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A2016-11-0808 November 2016 License Amendment Request for One-Time 7 Day Extension of Completion Time for TS Condition 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A GO2-16-086, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 32016-07-14014 July 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3 GO2-16-096, License Amendment Request to Revise Operating License and Technical Specifications for Measurement Uncertainty Recapture Power Uprate2016-06-28028 June 2016 License Amendment Request to Revise Operating License and Technical Specifications for Measurement Uncertainty Recapture Power Uprate ML15355A4812015-12-21021 December 2015 Revision 87 to Technical Specification Bases GO2-15-070, Application for Technical Specification Change (TSTF-427) to Add LCO 3.0.9 on the Unavailability of Barriers Using the Consolidated Line Item Improvement Process2015-09-0202 September 2015 Application for Technical Specification Change (TSTF-427) to Add LCO 3.0.9 on the Unavailability of Barriers Using the Consolidated Line Item Improvement Process GO2-15-108, Provides Affected Technical Specification Pages Supporting License Amendment Request for Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-423, Revision 1, Using the Consolidated Line Item Improvement Process2015-08-11011 August 2015 Provides Affected Technical Specification Pages Supporting License Amendment Request for Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-423, Revision 1, Using the Consolidated Line Item Improvement Process GO2-15-075, Exigent License Amendment Request - Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1 Function 7 Scram Discharge Volume Water Level-High.2015-05-15015 May 2015 Exigent License Amendment Request - Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1 Function 7 Scram Discharge Volume Water Level-High. GO2-15-007, License Amendment Request for Adoption of Technical Specification Task Force Traveler-425, Revision 32015-03-17017 March 2015 License Amendment Request for Adoption of Technical Specification Task Force Traveler-425, Revision 3 GO2-14-139, Attachment 6 - GNF-001N8896-R3-NP, Gnf Additional Information Regarding the Requested Changes to the Technical Specification SLMCPR, Columbia Cycle 232014-10-31031 October 2014 Attachment 6 - GNF-001N8896-R3-NP, Gnf Additional Information Regarding the Requested Changes to the Technical Specification SLMCPR, Columbia Cycle 23 GO2-14-126, License Amendment Request to Revise Technical Specification Surveillance Requirement for the Ultimate Heat Sink2014-08-22022 August 2014 License Amendment Request to Revise Technical Specification Surveillance Requirement for the Ultimate Heat Sink ML14010A0302014-02-11011 February 2014 Issuance of Amendment No. 227, Request to Adopt Technical Specification Task Force (TSTF)-477, Revision 3, Adding an Action Statement for Two Inoperable Control Room Air Conditioning Subsystem ML14010A2902013-12-30030 December 2013 Columbia, 10 CFR 50.71 Maintenance of Records Licensing Basis Document Update ML13247A6592013-07-25025 July 2013 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF 477, Revision 3 GO2-13-043, Request for Technical Specification Interpretation Regarding the Offsite Power Supplies to the Onsite Class 1E AC Power Distribution System2013-03-13013 March 2013 Request for Technical Specification Interpretation Regarding the Offsite Power Supplies to the Onsite Class 1E AC Power Distribution System ML12011A1492011-12-14014 December 2011 Columbia, Technical Specification (TS) Basis, Rev. 69, Licensee Controlled Specifications (LCS) Rev. 67 and Operational Quality Assurance Program Description (Oqapd), Rev. 44 ML1013903692010-05-11011 May 2010 Columbia Generating Station, License Amendment Request to Change Technical Specifications in Support of Prnm/Arts/Mella Implementation GO2-09-011, License Amendment Request to Revise Control Rod Notch Testing Frequency Using the Consolidated Line Item Improvement Process (CLIIP) for TSTF-4752009-01-14014 January 2009 License Amendment Request to Revise Control Rod Notch Testing Frequency Using the Consolidated Line Item Improvement Process (CLIIP) for TSTF-475 ML0826100562008-09-30030 September 2008 Tech Spec Pages for Amendment No. 210 Revised TS 3.3.5.2 RCIC System Instrumentation, and TS 3.5.2 ECCS-Shotdown to Increase Storage Tank Level GO2-08-124, License Amendment Request for Proposed Changes to Columbia Technical Specification 3.3.3.1; Change Group 1 Primary Containment Isolation Valves Reactor Water Level Isolation Signal from Level 2 to Level 12008-09-0909 September 2008 License Amendment Request for Proposed Changes to Columbia Technical Specification 3.3.3.1; Change Group 1 Primary Containment Isolation Valves Reactor Water Level Isolation Signal from Level 2 to Level 1 ML0822506802008-07-16016 July 2008 Columbia - License Amendment Request for Changes to Technical Specifications Involving Core Operating Limits Report and Scram Time Testing GO2-08-071, License Amendment Request for Adoption of TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities2008-05-0707 May 2008 License Amendment Request for Adoption of TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities GO2-07-123, License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level2007-08-0808 August 2007 License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level GO2-07-111, License Amendment Request for Proposed Changes to Columbia Technical Specifications: Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves2007-07-30030 July 2007 License Amendment Request for Proposed Changes to Columbia Technical Specifications: Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves GO2-07-112, License Amendment Request for Proposed Changes to Technical Specifications: Miscellaneous Administrative Changes Including Adoption of Approved TSTF Travelers 284, 479, and 4852007-07-30030 July 2007 License Amendment Request for Proposed Changes to Technical Specifications: Miscellaneous Administrative Changes Including Adoption of Approved TSTF Travelers 284, 479, and 485 GO2-07-116, Request for Amendment to Technical Specification to Modify Requirements Regarding Control Room Envelope Habitability Using the Consolidated Line Item Improvement Process (CLIIP)2007-07-30030 July 2007 Request for Amendment to Technical Specification to Modify Requirements Regarding Control Room Envelope Habitability Using the Consolidated Line Item Improvement Process (CLIIP) GO2-07-109, License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level2007-07-26026 July 2007 License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level ML0709204712007-05-0101 May 2007 Technical Specification Pages - Issuance of Amendment No. 204 AC and DC Electrical Power ML0706400652007-03-23023 March 2007 Technical Specification, AC Sources - Operating 3.8.1 GO2-07-024, GO2-07-024 - Columbia Generating Station - Exigent License Amendment Request - Amend Operating License to Revise TS 3.6.1.7 Suppression Chamber-to-Drywell Vacuum Breakers2007-02-0202 February 2007 GO2-07-024 - Columbia Generating Station - Exigent License Amendment Request - Amend Operating License to Revise TS 3.6.1.7 Suppression Chamber-to-Drywell Vacuum Breakers GO2-06-061, Request for Amendment to Technical Specifications Surveillance Requirements for the Suppression Chamber-to-Drywell Vacuum Breakers and the Drywell-to-Suppression Chamber Bypass Leakage Test2006-04-18018 April 2006 Request for Amendment to Technical Specifications Surveillance Requirements for the Suppression Chamber-to-Drywell Vacuum Breakers and the Drywell-to-Suppression Chamber Bypass Leakage Test GO2-06-042, Revised Technical Specification Bases Change (for Information) and Summary of Commitments Associated with the License Amendment Requests for Extension of Diesel Generator Completion Time2006-03-20020 March 2006 Revised Technical Specification Bases Change (for Information) and Summary of Commitments Associated with the License Amendment Requests for Extension of Diesel Generator Completion Time GO2-05-184, Supplement to the License Amendment Request for a One-Time Extension to Technical Specification 3.7.12005-11-15015 November 2005 Supplement to the License Amendment Request for a One-Time Extension to Technical Specification 3.7.1 ML0507000912005-03-0909 March 2005 Technical Specification Pages (Amd. 190) Re Elimination of Requirements to Provide Monthly Operating Reports & Annual Occupational Radiation Exposure Reports GO2-04-137, Request for Amendment to Technical Specifications for One-Time Extension of Containment Leak Rate Test Interval2004-08-0505 August 2004 Request for Amendment to Technical Specifications for One-Time Extension of Containment Leak Rate Test Interval ML0415405452004-05-19019 May 2004 Application for Amendment of Facility Operating for Extension of Diesel Generator Completion Time 2024-09-23
[Table view] Category:Amendment
MONTHYEARGO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-22-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process2022-05-25025 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process GO2-20-004, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR2020-01-27027 January 2020 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR GO2-19-098, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules2019-09-12012 September 2019 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules GO2-19-119, Exigent License Amendment Request for Change to Technical Specification 3.8.7 Distribution Systems - Operating2019-08-15015 August 2019 Exigent License Amendment Request for Change to Technical Specification 3.8.7 Distribution Systems - Operating GO2-17-181, License Amendment Request to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-12-12012 December 2017 License Amendment Request to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements GO2-17-194, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2017-11-15015 November 2017 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control GO2-17-022, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-522 Revision 02017-01-19019 January 2017 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-522 Revision 0 GO2-16-119, License Amendment Request for One-Time 7 Day Extension of Completion Time for TS Condition 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A2016-11-0808 November 2016 License Amendment Request for One-Time 7 Day Extension of Completion Time for TS Condition 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A GO2-15-108, Provides Affected Technical Specification Pages Supporting License Amendment Request for Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-423, Revision 1, Using the Consolidated Line Item Improvement Process2015-08-11011 August 2015 Provides Affected Technical Specification Pages Supporting License Amendment Request for Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-423, Revision 1, Using the Consolidated Line Item Improvement Process GO2-15-075, Exigent License Amendment Request - Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1 Function 7 Scram Discharge Volume Water Level-High.2015-05-15015 May 2015 Exigent License Amendment Request - Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1 Function 7 Scram Discharge Volume Water Level-High. ML14010A0302014-02-11011 February 2014 Issuance of Amendment No. 227, Request to Adopt Technical Specification Task Force (TSTF)-477, Revision 3, Adding an Action Statement for Two Inoperable Control Room Air Conditioning Subsystem ML13247A6592013-07-25025 July 2013 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF 477, Revision 3 GO2-09-011, License Amendment Request to Revise Control Rod Notch Testing Frequency Using the Consolidated Line Item Improvement Process (CLIIP) for TSTF-4752009-01-14014 January 2009 License Amendment Request to Revise Control Rod Notch Testing Frequency Using the Consolidated Line Item Improvement Process (CLIIP) for TSTF-475 ML0826100562008-09-30030 September 2008 Tech Spec Pages for Amendment No. 210 Revised TS 3.3.5.2 RCIC System Instrumentation, and TS 3.5.2 ECCS-Shotdown to Increase Storage Tank Level GO2-08-124, License Amendment Request for Proposed Changes to Columbia Technical Specification 3.3.3.1; Change Group 1 Primary Containment Isolation Valves Reactor Water Level Isolation Signal from Level 2 to Level 12008-09-0909 September 2008 License Amendment Request for Proposed Changes to Columbia Technical Specification 3.3.3.1; Change Group 1 Primary Containment Isolation Valves Reactor Water Level Isolation Signal from Level 2 to Level 1 ML0822506802008-07-16016 July 2008 Columbia - License Amendment Request for Changes to Technical Specifications Involving Core Operating Limits Report and Scram Time Testing GO2-08-071, License Amendment Request for Adoption of TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities2008-05-0707 May 2008 License Amendment Request for Adoption of TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities GO2-07-123, License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level2007-08-0808 August 2007 License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level GO2-07-111, License Amendment Request for Proposed Changes to Columbia Technical Specifications: Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves2007-07-30030 July 2007 License Amendment Request for Proposed Changes to Columbia Technical Specifications: Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves GO2-07-116, Request for Amendment to Technical Specification to Modify Requirements Regarding Control Room Envelope Habitability Using the Consolidated Line Item Improvement Process (CLIIP)2007-07-30030 July 2007 Request for Amendment to Technical Specification to Modify Requirements Regarding Control Room Envelope Habitability Using the Consolidated Line Item Improvement Process (CLIIP) GO2-07-109, License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level2007-07-26026 July 2007 License Amendment Request to Technical Specifications Associated with Condensate Storage Tank Level ML0709204712007-05-0101 May 2007 Technical Specification Pages - Issuance of Amendment No. 204 AC and DC Electrical Power ML0706400652007-03-23023 March 2007 Technical Specification, AC Sources - Operating 3.8.1 GO2-06-061, Request for Amendment to Technical Specifications Surveillance Requirements for the Suppression Chamber-to-Drywell Vacuum Breakers and the Drywell-to-Suppression Chamber Bypass Leakage Test2006-04-18018 April 2006 Request for Amendment to Technical Specifications Surveillance Requirements for the Suppression Chamber-to-Drywell Vacuum Breakers and the Drywell-to-Suppression Chamber Bypass Leakage Test GO2-05-184, Supplement to the License Amendment Request for a One-Time Extension to Technical Specification 3.7.12005-11-15015 November 2005 Supplement to the License Amendment Request for a One-Time Extension to Technical Specification 3.7.1 ML0507000912005-03-0909 March 2005 Technical Specification Pages (Amd. 190) Re Elimination of Requirements to Provide Monthly Operating Reports & Annual Occupational Radiation Exposure Reports GO2-04-137, Request for Amendment to Technical Specifications for One-Time Extension of Containment Leak Rate Test Interval2004-08-0505 August 2004 Request for Amendment to Technical Specifications for One-Time Extension of Containment Leak Rate Test Interval ML0415405452004-05-19019 May 2004 Application for Amendment of Facility Operating for Extension of Diesel Generator Completion Time GO2-02-192, Request for Amendment to TS 4.2.1 and 5.6.5.b, Corrections to Original Submittal2002-11-27027 November 2002 Request for Amendment to TS 4.2.1 and 5.6.5.b, Corrections to Original Submittal GO2-02-111, Amendment Request to Revise Minimum Emergency Diesel Generator Output Voltage Specified in Technical Specification Limiting Condition for Operation 3.8.12002-07-16016 July 2002 Amendment Request to Revise Minimum Emergency Diesel Generator Output Voltage Specified in Technical Specification Limiting Condition for Operation 3.8.1 2024-09-23
[Table view] |
Text
Alex L. Javorik Columbia Generating Station P.O. Box 968, PE04 Richland, WA 99352-0968 Ph. 509.377.8555 l F. 509.377.2354 aljavorik@energy-northwest.com December 12, 2017 GO2-17-181 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397 LICENSE AMENDMENT REQUEST TO REVISE TECHNICAL SPECIFICATIONS TO ADOPT TSTF-551, "REVISE SECONDARY CONTAINMENT SURVEILLANCE REQUIREMENTS"
Dear Sir or Madam:
Pursuant to 10 CFR 50.90, Energy Northwest is submitting a request for an amendment to the Technical Specifications (TS) for Columbia Generating Station.
The proposed change revises TS 3.6.4.1, "Secondary Containment," Surveillance Requirement (SR) 3.6.4.1.1. The SR is revised to address conditions during which the secondary containment pressure may not meet the SR pressure requirements. In addition, SR 3.6.4.1.3 is modified to acknowledge that secondary containment access openings may be open for entry and exit. provides a description and assessment of the proposed changes. provides the existing TS pages marked up to show the proposed changes. Attachment 3 provides revised (clean) TS pages. Attachment 4 provides TS Bases pages marked up to show the associated TS Bases changes and is provided for information only.
Approval of the proposed amendment is requested one year from the date of this letter.
Once approved, the amendment shall be implemented within 60 days.
In accordance with 10 CFR 50.91, a copy of this application, with attachments, is being provided to the designated Washington Official.
If you should have any questions regarding this submittal, please contact Ms. L. L.
Williams, Licensing Supervisor, at 509-377-8148.
G02-17-181 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct.
Executed this 12 "('It, day of December, 2017.
A L. Javorik Vice President, Engineering Attachments: 1. Description and Assessment
- 2. Proposed Technical Specification Changes (Mark-Up)
- 3. Revised Technical Specification Pages
- 4. Proposed Technical Specification Bases Changes (Mark-Up) -
Information Only cc: NRC RIV Regional Administrator NRC NRR Project Manager NRC Senior Resident lnspector/988C CD Sonoda - BPA/1399 (email)
EFSECutc.wa.gov - EFSEC (email)
RR Cowley - WDOH (email)
WA Horin - Winston & Strawn
GO2-17-181 Page 1 of 4 DESCRIPTION AND ASSESSMENT
1.0 DESCRIPTION
The proposed change revises Technical Specification (TS) 3.6.4.1, "Secondary Containment," Surveillance Requirement (SR) 3.6.4.1.1. The SR is revised to allow conditions during which the secondary containment pressure may not meet the SR pressure requirements. In addition, SR 3.6.4.1.3 is modified to acknowledge that secondary containment access openings may be open for entry and exit.
2.0 ASSESSMENT 2.1 Applicability of Safety Evaluation Energy Northwest has reviewed the safety evaluation for TSTF-551 provided to the Technical Specifications Task Force in a letter dated September 21, 2017. This review included a review of the NRC staffs evaluation, as well as the information provided in TSTF-551. Energy Northwest has concluded that the justifications presented in TSTF-551 and the safety evaluation prepared by the NRC staff are applicable to Columbia Generating Station (Columbia) and justify this amendment for the incorporation of the changes to the Columbia TS.
The radiological consequence analysis for Columbia was approved by the NRC on November 27, 2006 (Accession No. ML062610440), and is documented in FSAR Section 15.6.5. Energy Northwest has confirmed that the brief, inadvertent, simultaneous opening of both an inner and outer personnel access door during normal entry and exit conditions, and their prompt closure by normal means, is bounded by the radiological dose consequence analysis. In the unlikely event that an accident would occur when both personnel access doors are open for entry or exit, the brief time required to close one of the doors is small compared to the 1200 seconds assumed in the accident analysis for reducing the post-accident secondary containment pressure to 0.25 inch of vacuum water gauge, and will not result in an increase in any onsite or offsite dose. Although, the Standby Gas Treatment (SGT) System is not required to draw down secondary containment until the time stated in SR 3.6.4.1.4, the average time it takes SGT System to draw down secondary containment at Columbia when tested for SR 3.6.4.1.4 is 44.9 seconds.
2.2 Variations Energy Northwest is proposing the following variations from the TS changes described in the TSTF-551 or the applicable parts of the NRC staffs safety evaluation. These variations do not affect the applicability of TSTF-551 or the NRC staff's safety evaluation to the proposed license amendment.
GO2-17-181 Page 2 of 4 The Columbia TS wording for SR 3.6.4.1.3 is different than NUREG-1433. The Columbia SR 3.6.4.1.3 states: Verify each secondary containment access inner door or each secondary containment access outer door in each access opening is closed compared with the NUREG-1433 wording: Verify one [secondary] containment access door in each access opening is closed. Both wordings are functionally equivalent, so applying the TSTF-551 exception is an administrative variation.
The Columbia TS wording for SR 3.6.4.1.4 is different than NUREG-1433. The Columbia SR 3.6.4.1.4 states: Verify each standby gas treatment (SGT) subsystem will draw down the secondary containment to 0.25 inch of vacuum water gauge in 120 seconds compared with the NUREG-1433 wording: [Verify [secondary]
containment can be drawn down to [0.25] inch of vacuum water gauge in [120]
seconds using one standby gas treatment (SGT)subsystem. Both wordings are functionally equivalent, so applying the TSTF-551 exception is an administrative variation.
The NUREG-1433 TS 3.6.4.1 APPLICABILITY (for which the as-modified SRs are required) includes During the movement of [recently] irradiated fuel assemblies in the
[secondary] containment. Similarly Section 3.2.2 of the TSTF-551 Model Safety Evaluation describes the effects of TSTF-551 on the radiological dose consequences of the Fuel Handling Accident (FHA). However, with License Amendment 199, the requirement for Secondary Containment operability during the movement of irradiated fuel was removed from the Columbia TS. Since this previous license amendment does not invalidate any of the conclusions of the TSTF-551 Safety Evaluation, this is considered to be an administrative variation.
3.0 REGULATORY ANALYSIS
3.1 No Significant Hazards Consideration Determination Analysis Energy Northwest requests adoption of TSTF-551, "Revise Secondary Containment Surveillance Requirements," which is an approved change to the standard technical specifications (STS), into the Columbia Generating Station Technical Specifications (TS). The proposed change revises Technical Specification (TS) Surveillance Requirement (SR) 3.6.4.1.1. The SR is revised to permit conditions during which the secondary containment may not meet the SR acceptance criterion for a period of up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> if an analysis demonstrates that one standby gas treatment (SGT) subsystem remains capable of establishing the required secondary containment vacuum. In addition, SR 3.6.4.1.3 is modified to acknowledge that secondary containment access openings may be open for entry and exit.
Energy Northwest has evaluated the proposed change against the criteria of 10 CFR 50.92(c) to determine if the proposed change results in any significant hazards.
The following is the evaluation of each of the 10 CFR 50.92(c) criteria:
GO2-17-181 Page 3 of 4
- 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No The proposed change addresses conditions during which the secondary containment SRs are not met. The secondary containment is not an initiator of any accident previously evaluated. As a result, the probability of any accident previously evaluated is not increased. The consequences of an accident previously evaluated while utilizing the proposed changes are no different than the consequences of an accident while utilizing the existing four hour Completion Time for an inoperable secondary containment. In addition, the proposed Note for SR 3.6.4.1.1 provides an alternative means to ensure the secondary containment safety function is met. As a result, the consequences of an accident previously evaluated are not significantly increased.
Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does the proposed change create the possibility of a new or different kind of accident from any previously evaluated?
Response: No The proposed change does not alter the protection system design, create new failure modes, or change any modes of operation. The proposed change does not involve a physical alteration of the plant; and no new or different kind of equipment will be installed. Consequently, there are no new initiators that could result in a new or different kind of accident.
Therefore, the proposed change does not create the possibility of a new or different kind of accident from any previously evaluated.
- 3. Does the proposed change involve a significant reduction in a margin of safety?
Response: No The proposed change addresses conditions during which the secondary containment SRs are not met. Conditions in which the secondary containment vacuum is less than the required vacuum are acceptable provided the conditions do not affect the ability of the SGT System to establish the required secondary containment vacuum under post-accident conditions within the time assumed in the accident analysis. This condition is incorporated in the proposed change by requiring an analysis of actual environmental and secondary containment pressure conditions to confirm the capability of the SGT System is maintained within the assumptions of the accident analysis. Therefore, the safety function of
GO2-17-181 Page 4 of 4 the secondary containment is not affected. The allowance for both an inner and outer secondary containment door to be open simultaneously for entry and exit does not affect the safety function of the secondary containment as the doors are promptly closed after entry or exit, thereby restoring the secondary containment boundary.
Therefore, the proposed change does not involve a significant reduction in a margin of safety.
Based on the above, Energy Northwest concludes that the proposed amendment presents no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), and, accordingly, a finding of "no significant hazards consideration" is justified.
3.2 Conclusions In conclusion, based on the considerations discussed above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
4.0 ENVIRONMENTAL EVALUATION The proposed amendment would change a requirement with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR 20, or would change an inspection or surveillance requirement. However, the proposed amendment does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure. Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed amendment.
GO2-17-181 Attachment 2 Proposed Technical Specification Changes (Mark-Up)
Secondary Containment 3.6.4.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.4.1.1 --------------------------NOTE--------------------------------
Not required to be met for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> if analysis demonstrates one standby gas treatment (SGT) subsystem is capable of establishing the required secondary containment vacuum.
Verify secondary containment vacuum is 0.25 inch In accordance of vacuum water gauge. with the Surveillance Frequency Control Program SR 3.6.4.1.2 Verify all secondary containment equipment hatches In accordance are closed and sealed. with the Surveillance Frequency Control Program SR 3.6.4.1.3 Verify each secondary containment access inner In accordance door or each secondary containment access outer with the door in each access opening is closed, except when Surveillance the access opening is being used for entry and exit. Frequency Control Program SR 3.6.4.1.4 Verify each standby gas treatment (SGT) subsystem In accordance will draw down the secondary containment to with the 0.25 inch of vacuum water gauge in Surveillance 120 seconds. Frequency Control Program SR 3.6.4.1.5 Verify each SGT subsystem can maintain In accordance 0.25 inch of vacuum water gauge in the secondary with the containment for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at a flow rate 2240 cfm. Surveillance Frequency Control Program Columbia Generating Station 3.6.4.1-2 Amendment No. 169,199 225 238
GO2-17-181 Attachment 3 Revised Technical Specification Pages
Secondary Containment 3.6.4.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.4.1.1 --------------------------NOTE--------------------------------
Not required to be met for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> if analysis demonstrates one standby gas treatment (SGT) subsystem is capable of establishing the required secondary containment vacuum.
Verify secondary containment vacuum is 0.25 inch In accordance of vacuum water gauge. with the Surveillance Frequency Control Program SR 3.6.4.1.2 Verify all secondary containment equipment hatches In accordance are closed and sealed. with the Surveillance Frequency Control Program SR 3.6.4.1.3 Verify each secondary containment access inner In accordance door or each secondary containment access outer with the door in each access opening is closed, except when Surveillance the access opening is being used for entry and exit. Frequency Control Program SR 3.6.4.1.4 Verify each SGT subsystem will draw down the In accordance secondary containment to 0.25 inch of vacuum with the water gauge in 120 seconds. Surveillance Frequency Control Program SR 3.6.4.1.5 Verify each SGT subsystem can maintain In accordance 0.25 inch of vacuum water gauge in the secondary with the containment for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at a flow rate 2240 cfm. Surveillance Frequency Control Program Columbia Generating Station 3.6.4.1-2 Amendment No. 169,199 225 238
GO2-17-181 Attachment 4 Proposed Technical Specification Bases Changes (Mark-Up) - Information Only
Secondary Containment B 3.6.4.1 BASES SURVEILLANCE REQUIREMENTS (continued) area that has open communication with the rest of the secondary containment volume. The use of 0.25 inches of vacuum water gauge includes margin to account for uncertainties.
The SR is modified by a Note which states the SR is not required to be met for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> if an analysis demonstrates that one SGT subsystem remains capable of establishing the required secondary containment vacuum. Use of the Note is expected to be infrequent but may be necessitated by situations in which secondary containment vacuum may be less than the required containment vacuum, such as, but not limited to, wind gusts or failure or change of operating normal ventilation subsystems. These conditions do not indicate any change in the leak tightness of the secondary containment boundary. The analysis should consider the actual conditions (equipment configuration, temperature, atmospheric pressure, wind conditions, measured secondary containment vacuum, etc.) to determine whether, if an accident requiring secondary containment to be OPERABLE were to occur, one train of SGT could establish the assumed secondary containment vacuum within the time assumed in the accident analysis. If so, the SR may be considered met for a period up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> limit is based on the expected short duration of the situations when the Note would be applied.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.6.4.1.2 and SR 3.6.4.1.3 Verifying that secondary containment equipment hatches and each inner access door or each outer access door in each access opening are closed at all times when secondary containment is required ensures that the infiltration of outside air of such a magnitude as to prevent maintaining the desired negative pressure does not occur and.
Verifying that all such openings are closed provides adequate assurance that exfiltration from the secondary containment will not occur.
SR 3.6.4.1.2 also requires equipment hatches to be sealed. In this application, the term "sealed" has no connotation of leak tightness.
Maintaining secondary containment OPERABILITY requires verifying either all inner doors or all outer doors in the access opening are closed at all times when secondary containment is required. However, each secondary containment access door is normally kept closed, except when the access opening is being used for entry and exit or when maintenance is being performed on an access. The Surveillance Frequencies are controlled under the Surveillance Frequency Control Program.
Columbia Generating Station B 3.6.4.1-4 Revision 93
Secondary Containment B 3.6.4.1 SR 3.6.4.1.3 Verifying that each inner access door or each outer access door in each access opening is closed provides adequate assurance that exfiltration from the secondary containment will not occur. An access opening contains at least one inner and one outer door. The intent is to not breach the secondary containment, which is achieved by maintaining the inner or outer portion of the barrier closed except when the access opening is being used for entry and exit.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.6.4.1.4 and SR 3.6.4.1.5 The SGT System exhausts the secondary containment atmosphere to the environment through appropriate treatment equipment. To ensure that all fission products are treated, SR 3.6.4.1.4 verifies that the SGT System will rapidly establish and maintain a pressure in the secondary containment that is less than the pressure external to the secondary containment boundary. This is accomplished by verifying the secondary containment can be drawn down to an indicated pressure of greater than or equal to 0.25 inches of vacuum water gauge in less than or equal to 120 seconds, following the start of a single SGT fan.
SR 3.6.4.1.5 demonstrates that each SGT subsystem can maintain an indicated secondary containment pressure of 0.25 inches of vacuum water gauge for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at an indicated flow rate 2240 cfm. The 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Columbia Generating Station B 3.6.4.1-5 Revision 93