GO2-05-025, January 2005 Monthly Operating Report for Columbia Generating Station

From kanterella
Jump to navigation Jump to search
January 2005 Monthly Operating Report for Columbia Generating Station
ML050470124
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 02/09/2005
From: Lynch T
Energy Northwest
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GO2-05-025
Download: ML050470124 (3)


Text

I I

ENERGY SA NORTHWEST People *Vision *Solutions P.O. Box 968

  • Richland, WA
  • 99352-0968 February 9, 2005 G02-05-025 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 MONTHLY OPERATING REPORT JANUARY 2005

Dear Sir or Madam:

Transmitted herewith is the Monthly Operating Report for the month of January 2005 as required by Technical Specification 5.6.4.

Respectfully, TA Lynch Plant General Manager Mail Drop 927M Attachment cc:

BS Mallett-NRC RIV BJ Benney-NRC NRR NRC Senior Resident Inspector - 988C TC Poindexter - Winston & Strawn INPO ANI Library Utility Data Institute RN Sherman - BPA /1399

~

j i

1

OPERATING STATUS REPORT for Columbia Generating Station Date: February 1, 2005 1.

2.

3.

4.

5.

Docket: 50-397 Reporting Period: January 2005 Utility

Contact:

Patricia Campbell (509) 377-4664 Design Electrical Rating (Net MWe): 1153 Maximum Dependable Capacity - summer (Net MWe): 1107 7.

8.

9.

MONTH YEAR HoursReactor-Critical

_ _744.0

_-.744.0 Hours Generator On-Line 744.0 744.0 Unit Reserve Shutdown Hours 0.0 0.0 Net Electrical Energy (MWH) 829,313 829,313 CUMULATIVE 1__

35,911.6_

132,380.4 3,274.7 132,678,548

UNIT SHUTDOWNS dNI DOCKET NO.: 50-397 NIT NAME:

Columbia Generating Station I

DATE: February 1, 2005 COMPLETED BY: P. Campbell I

TELEPHONE: (509) 377-4664

.i I'

l REPORT PERIOD: January, 2005 Type Method of Cause / Corrective Actions F: Forced

} Duration Shutting No.

Date S: Scheduled 11 (Hours)

Reason (I)

Down (2)

Comments I

N/A

SUMMARY

Columbia Generating Station began and ended the mO]

reactor power.

l ith of January 2005 at full (1) REASON A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training &

License Examination F - Administration G - Operational Error H - Other(

,I (2) METHOD 1 - Manual 2 - Manual Trip/Scram 3 - Auto Trip/Scram 4 - Continuation 5 - Other (Explain)

I iII i