GO2-02-007, December 2001 Monthly Operating Report for Columbia Generating Station
| ML020450126 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 01/14/2002 |
| From: | Oxenford W Energy Northwest |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GO2-02-007 | |
| Download: ML020450126 (3) | |
Text
ENERGY NORTH WEST PO. Box 968
- Richland, Washington 99352-0968 January 14, 2002 G02-02-007 Docket No. 50-397 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 Gentlemen:
Subject:
COLUMBIA GENERATING STATION OPERATING LICENSE NPF-21 MONTHLY OPERATING REPORT DECEMBER 2001 Transmitted herewith is the Monthly Operating Report for the month of December 2001 as required by Technical Specification 5.6.4.
Respectfully, W.S. Oxenford (Mail Drop 927M)
Plant General Manager Attachment cc:
E.W. Merschoff - NRC RIV J.S. Cushing - NRR NRC Sr. Resident Inspector - 988C T.C. Poindexter - Winston & Strawn INPO ANI Library Utility Data Institute D.L. Williams - BPA 1399
OPERATING STATUS REPORT for Columbia Generating Station Date:
January 1, 2002 Docket: 50-397 Reporting Period: December 2001 Utility
Contact:
Patricia Campbell (509) 377-4664 Design Electrical Rating (Net MWe):
Maximum Dependable Capacity - summer (Net MWe):
Hours Reactor Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy (MWH)
MONTH 744.0 744.0 0.0 842,069 YEAR 7,714.4 7,563.1 0.0 8,250,429 CUMULATIVE 111,150.7 107,843.0 3,274.7 106,271,485
- 10.
Challenges to safety/relief valves:
- 1.
- 2.
- 3.
- 4.
5.
- 6.
- 7.
- 8.
9.
1153 1107 None
UNIT SHUTDOWNS DOCKET NO.: 50-397 UNIT NAME: Columbia Generating Station DATE: January 1, 2002 COMPLETED BY: P. Campbell TELEPHONE: (509) 377-4664 REPORT PERIOD: December, 2001
SUMMARY
- The plant began and ended the month at full power operation.
(1) REASON A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training &
License Examination F - Administration G - Operational Error H - Other (2) METHOD 1 - Manual 2 - Manual Trip/Scram 3 - Auto Trip/Scram 4 - Continuation 5 - Other (Explain)
Type Method of Cause / Corrective Actions F: Forced Duration Shutting No.
Date S: Scheduled (Hours)
Reason (1)
Down(2)
Comments N/A