GNRO-2003/00074, November 2003 Monthly Operating Report for Grand Gulf

From kanterella
Jump to navigation Jump to search
November 2003 Monthly Operating Report for Grand Gulf
ML033510675
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 12/09/2003
From: Bottemiller C
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GNRO-2003/00074
Download: ML033510675 (5)


Text

Waterloo Road P.O. Box 756 Port Gibson, MS 39150 Tel 601 437 6299 rles er Manager Plant Licensing December 9,2003 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555

Subject:

Monthly Operating Report Grand Gulf Nuclear Station Docket No. 50-416 License No. NPF-29 GN RO-2003/000-/4 Ladies and Gentlemen:

In accordance with the requiremen. of Tec,,nice Specification 5.6.d Entergy Operations, Inc. is providing the Monthly Operating Report for Grand Gulf Nuclear Station Unit 1 for November 2003.

This letter does not contain any commitments.

If you have any questions or require additional information, please contact this office.

Yours truly, CAB/AMT:amt attachments:

1. Operating Status
2. Average Daily Power Level
3. Unit Shutdown and Power Reductions cc:

(See Next Page)

GO30074

December 9,2003 Page 2 of 2 GN RO-2003/00074 cc:

Hoeg T. L.

(GGNS Senior Resident) (w/a)

Levanway D. E.

(Wise Carter)

(wja)

Reynolds N. S.

(WW Smith L. J.

(Wise Carter)

(wla)

Thomas H. L.

(WlO)

U.S. Nuclear Regulatory Commission ATTN: Mr. Bruce S. Mallett (w/2)

Regional Administrator, Region IV 61 1 Ryan Plaza Drive, Suite 400 Arlington, TX 7601 1-4005 U.S. Nuclear Regulatory Commission ATTN: Mr. Bhalchandra Vaidya, NRR/DLPM (w/2)

ATTN: ADDRESSEE ONLY ATTN: U.S. Postal Delivery Address Only Mail Stop OWFN/7D-1 Washington, D.C. 20555-0001 GO30074 to GNRO-2003l00074 DOCKET NO 50-416 DATE 12/02/2003 COMPLETED BY J. Charboneau TELEPHONE (601) 437-6797 OPERATING STATUS

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.

Unit Name: GGNS UNIT 1 Reporting Period: November 2003 Licensed Thermal Power (MWt): 3898 MWT Nameplate Rating (Gross MWe): 1372.5 MWE Design Electrical Rating (Net MWe): 1250 MWE Maximum Dependable Capacity (Gross MWe): 1257 MWE Maximum Dependable Capacity (Net MWe):

1207 MWE If changes occur in Capacity Ratings (Items 3 through 7) Since Last Report. Give Reason: N/A Power Level To Which Restricted, If Any (Net MWe):

Reasons For Restrictions, If Any: N/A None This Month Yr to Date Cumulative*

Hours in Reporting Period 720 8,016 167,560 Number of Hours Reactor was Critical 720.0 7,897.7 144,622.1 Reactor Reserve Shutdown Hours 0

0 0

Hours Generator On-Line 720.0 7,83 1.1 140,872.4 Unit Reserve Shutdown Hours 0

0 0

Gross Thermal Energy Generated (MWH) 2,793,614 30,283, I32 514,754,317 Gross Electrical Energy Generated (MWH) 955,868 10.35 1,616 169,100,195 Net Electrical Energy Generated (MWH) 9 18,863 9,947.216 162,286,392 Unit Service Factor 100.0 97.7 85.4 Unit Availability Factor 100.0 97.7 85.4 Unit Capacity Factor (Using MDC Net) 105.7 102.8 85.3 Unit Capacity Factor (Using DER Net) 102.1 99.3 79.5 Unit Forced Outage Rate 0.0 2.3 4.9 Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

If Shut Down At End of Report Period. Estimated Date of Startup: N/A Units in Test Status (Prior to Commercial Operation):

RF013,02/23/03,30 days Forecast Achieved INITIAL CRITICALITY 0811 8/82 INITIAL ELECTRICITY 10/20/84 COMMERCIAL OPERATION 07/01/85

  • Items 1 1 through 18 are cumulative results since initial electricity GO30074 to GNRO-2003100074 50-416 DOCKET NO DATE 12/02/2003 COMPLETED BY J. Charboneau TELEPHONE (601) 437-6797 MONTH: November 2003 DAY 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 AVERAGE DAILY POWER LEVEL (MWe-Net) 1276 1276 1278 1276 1273 1277 1287 I126 1283 1281 1276 1271 1288 1289 1281 1277 DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1274 1277 1286 1286 1283 1277 1278 1291 1288 1283 1276 1290 1291 1289 31 GO30074 to GNRO-2003/00074 No.

Date Type (1)

Duration Reason Method Of Licensee Event System Code Component Cause & Corrective Action To Prevent Hours (2)

Shutting Down Report #

(4)

Code (5)

Recurrence (C&CA)

Reactor (3) 1

, 11/08/2003,

S

, 17.5 B

5 C11 Surveillance UNIT SHUTDOWNS AND POWER REDUCTIONS 1

2 F: Forced Reason:

S: Scheduled A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training &

Licensing Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3 4

5 Method:

1 -Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Reduced load 6-Other Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0 16 1)

Exhibit 1 - Same Source GO30074