VERMONT YANKEE NUCLEAR POwen CORPORATION l
l RD 5, Box 169, Ferry Road. 3rattleboro, VT 05301 g
ENGINEERING OFFICE j
580 MAIN STREET BOLTON, M A 01740 December 5, 1988 csoe3 num FVY 88-100 United States Nuclear Regulatory Comission Washington, DC 20555 Attention:
Document Control Desk
References:
(a) License No. DPR-28 (Docket No. 50-271)
(b) Letter, VYNPC to USNRC, FVY 87-120, dated December 21, 1987 (c) Letter, VYNPC to USNRC, EVY 88-33, dated May 2,1988
Subject:
Transmittal of Vermont Yankee SPDS Isolator Test Results
Dear Sir:
By letters dated December 21, 1987 and May 2, 1988 (References (b) and (c)], Vermont Yankee transmitted information concerning the criteria to be utilized in the design and manufacture of isolators for the Safety Paramater Display System (SPDS) which will be installed at the Vermont Yankee Station.
Subsequently, on August 30, 1988, these submittals were discussed with the NRC staff during r. telephone conversation, and more detailed information concerning the results of testing to be performed on the isolators was requested.
At the present time, prototype and production testing of the isolators has been completed. This testing has conclusively deinenstrated that the isolators will perform the required isolation function when subjected to the maximum credible conditions postulated for Vermont Yankee.
In accordance with the staff's request, Fnclosure 1 to this letter provides a sumary of the testing performed by EI International for qualification of the isolators being supplied for Vermont Yankee.
i GG12090306 881205 EDR ADOCK 05000271
?
O E
4 United States Nuclear Regulatory Commisalon December 5,1988 l
Attention: Document Control Desk Pago 2 We trust this !nformation is responsive to your request.
In the event you should *.re any further questions or require additional information regarding this matter, please do not hesitate to contact Mr. Robert Sojka, ERFIS Program Manager.
i Very truly yours,
[
I VERMONT YANKEE NUC EAR F0WER CORPORATION i
(
R. W. Ca tick Licensing Engineer l
RWC/0037w l
Enclosure I