ASLBP 24-986-01-LA-BD01, NRC Staff Answer to Intervention Petition from Beyond Nuclear, Dont Waste Michigan, Michigan Safe Energy Future, Three Mile Island Alert, and Nuclear Energy Information Service in Palisades Restart Amendments Proceeding | 4 November 2024 | Palisades | NRC Staff Answer to Intervention Petition from Beyond Nuclear, Dont Waste Michigan, Michigan Safe Energy Future, Three Mile Island Alert, and Nuclear Energy Information Service in Palisades Restart Amendments Proceeding |
ML24226A025 | 12 August 2024 | Kemmerer | Comment (964) E-mail Regarding Terrapower CP EIS Scoping |
ML23304A348 | 31 October 2023 | 05200050 | LLC Revision 1 to Standard Design Approval Application, Part 2, Chapter 7, Instrumentation and Controls |
ML23283A104 | 31 October 2023 | | Post Comment Resolution Draft - DANU-ISG-2022-01, Advanced Reactor Content of Application Project, Review of Risk-Informed, Technology-Inclusive Advanced Reactor Applications - Roadmap for Advisory Committee on Reactor Safeguards Review |
ML23202A132 | 14 July 2023 | HI-STORE | 7-14-23 Fasken Statement of Underlying Decisions from Which Petition Arises (DC Cir.)(Case No. 20-1187) |
ML23158A276 | 7 June 2023 | Comanche Peak | Memorandum and Order (Denying Intervention Petition and Terminating Proceeding) (LBP-23-06) |
ML23118A253 | 20 April 2023 | | M230420: Transcript - Strategic Programmatic Overview of the Fuel Facilities and the Spent Fuel Storage and Transportation Business Lines |
ML23111A175 | 19 April 2023 | Comanche Peak | Transcript of April 19, 2023 Hearing for Vistra Operations Company, LLC, Pages 1-79 |
ML23062A466 | 8 March 2023 | North Anna | License Renewal Second Environmental Site Audit Plan Regarding the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application |
ML22365A024 | 31 December 2022 | 99902078 05200050 | LLC Submittal of the NuScale Standard Design Approval Application Part 2 - Final Safety Analysis Report, Chapter 7, Instrumentation and Controls, Revision 0 |