At 1505 EST, it was determined by an engineering analysis that a leak on a 3/4 inch vent line of the
Residual Heat Removal Service Water (
RHRSW) System common discharge line would prevent continuous operation of the system for 30 days as required by the Unit 2
FSAR.
Specifically, if the line were to completely shear, the resulting leak would have exceeded the capacity of the building sumps and over a prolonged period of operation would have resulted in the excessive water levels in the Reactor Building Torus room area. In order to mitigate the condition, supplemental pumping capacity would be needed in the building sumps or the RHRSW system would have to be temporarily secured.
The RHRSW system has been tagged out for repair of the line. The appropriate 8-hour RAS in Tech Spec has been entered. The line will be repaired and the system returned to service.
The licensee identified the crack in the socket weld during a system walkdown and anticipates completion of repairs in approximately 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
The licensee informed the NRC Resident Inspector.
- * * UPDATE AT 2140 EST ON 02/20/08 FROM BILL DUVALL TO S. SANDIN * * *
At 2120 EST on 02/20/08 the RHR SW System was declared OPERABLE after completion of repairs and testing. The failure of the socket weld at 2E11-FV001 is preliminarily attributed to fatigue cracking caused by vibration. A root cause investigation is ongoing. A system walkdown did not identify any additional deficiencies.
The licensee informed the NRC Resident Inspector. Notified R2DO(Robert Haag).