ELV-01211, Responds to NRC 891206 Transmittal of SALP & Discussion at 891214 Meeting W/Nrc at Site.Disagrees W/Nrc Evaluation as Stated in SALP Ltr & Transmittal Ltr Re Overall Level of Performance During SALP Period.Reasons Listed

From kanterella
(Redirected from ELV-01211)
Jump to navigation Jump to search
Responds to NRC 891206 Transmittal of SALP & Discussion at 891214 Meeting W/Nrc at Site.Disagrees W/Nrc Evaluation as Stated in SALP Ltr & Transmittal Ltr Re Overall Level of Performance During SALP Period.Reasons Listed
ML20005G111
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 01/08/1990
From: Hairston W
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
ELV-01211, ELV-1211, NUDOCS 9001180142
Download: ML20005G111 (2)


Text

dW, J M

  • /

dQf 6' (Georg5 ' ower Company -

P fCMc

  • 1.333 Piedmont Avenue -

h I' <

4:

= Atlanta G3orgia 30308'-

4 j

~ielerkne 404 6263195 '

Ij p Mailing Address s

T 4 ' si 40 inverness Center Parkway.

Post Ofice Box 1295 '

o Birmingham, Alabama 35201 1

Teiepnone 20s ecs 5581 January 8,.1990

=%

the soorten ekoc spfem

=$

W G. Hairston,111 -

ELV-01211-

' Serwor Vcc President

. Nuclear Operations Q}9}.

t

>Do'cket Nos.- 50-424

'50-425-U U.- S. Nuclear Regulatory Commission ATTN: : Document Control Desk

Washington, D. C.

20555 Gentlemen:

V0GTLE ELECTRIC GENERATING PLANT RESPONSE TO SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE-

-Georgia Power Company'(GPC) has reviewed the>information presented in the 9

-Systematic Assessment of Licensee Performance (SALP) Re) ort transmitted'by your letter dated December 6,1989, and at the meeting held aetween GPC and the'NRC-P at the Vogtle Electric Generating Plant site on December 14, 1989.

. e: appreciate the constructive comments made in the SALP evaluation, as well as-W your recognition of-GPC'.s-efforts and successes in improving our performance.

GPC.is> fully committed to the safe and efficient operation of its nuclear plants. We take the SALP Board recommendations-seriously and will use this information in the continuing process of improving our performance.

However, GPC does not agree with the NRC's evaluation as stated in the SALP

' Report and the ' transmittal letter, that the overall level of performance during this SALP period is comparable to that of the last SALP period.

Some~of the reasons.for~this disagreement are:

o the number of unplanned reactor trips during this period was significantly lower when compared to the last period, o

the number and severity level of violations has been significantly

reduced, o

the Plant Review Board membership has been upgraded to include department managers, which provides a higher level of review of safety '

issues brought before this board, o

during this period the reliability and availability of the units was greater than during the last evaluation period which can be attributed to a more experienced and disciplined operating staff.

9001100142 900108 PDR ADOCK 05000424

.p PDC P

Y

, 2:y..

Georgia Power b F

U. S. ' Nuclear Regulatory Commission-

-t

.ELV-01211

.Paae Two It should also_ be noted that 'during this evaluation period, Unit I successfully completed-it's first refueling outage and Unit 2 successfully completed construction,- loaded fuel, completed power ascension and was placed into operation.

This is as opposed to one unit in operation for the previous evaluation period.

GPC requests'these comments be taken into consideration and a revision of the SALP Report be made to note that the overall performance has

-improved since the last evaluation period.

Should you have any questions, please inquire.

Sincerely, 6% C g W. G. Hairston, III L

WGH,III/ JAB /gm l

xc:

Georaia Power Company 1.

Mr..C. K. McCoy L

Mr. G. Bockhold, Jr.

Mr. P. D. Rushton Mr. R. M. Odom l

NORMS l.-

U. S. Nuclear Reaulatory Commission Mr. S. D. Ebneter, Regional Administrator p

Mr. J. B. Hopkins, Licensing Project Manager, NRR l

Mr. J. F. Rogge, Senior Resident Inspector, Vogtle l

1.