ELV-00634, Responds to Generic Ltr 89-08 Re Erosion/Corrosion Induced Pipe Wall Thinning.Erosion/Corrosion Monitoring Program Implemented for Unit 1 & Will Be Developed for Unit 2.Insps for Unit 2 Will Be Performed During First Refueling Outage

From kanterella
(Redirected from ELV-00634)
Jump to navigation Jump to search
Responds to Generic Ltr 89-08 Re Erosion/Corrosion Induced Pipe Wall Thinning.Erosion/Corrosion Monitoring Program Implemented for Unit 1 & Will Be Developed for Unit 2.Insps for Unit 2 Will Be Performed During First Refueling Outage
ML20246J974
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/11/1989
From: Hairston W
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
ELV-00634, ELV-634, GL-89-08, GL-89-8, NUDOCS 8907180001
Download: ML20246J974 (2)


Text

,

p Cimq;h Ner Cry.g h V n om /< r py g,(

a. -

h w 3 can -

C f-Q t i 3.4i/.., r j

si i h^

PQ.? (~ ' r

~

5 De jl$

n y,

.um h <

m-_

w.'

ELVb0634' w amon, m s av.eno>

1489n u w, o;,,

July 11,1989 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C.

20555 PLANT V0GTLE - UNITS 1, 2 NRC 00CKETS 50-424, 50-425 OPERATING LICENSES NPF-68, NPF-81 GENERIC LETTER 89-08: EROSION / CORR 0SION-INDUCED PIPE WALL THINNING Gentlemen:

In Generic Letter 89-08, the NRC requested power reactor licensees and construction permit holders to provide 6nformation concerning erosion / corrosion monitoring. programs. Specifically, information was requested on whether a long term erosion / corrosion monitoring program equivalent to the NUMARC program has been implemented, including procedures or administrative controls, to assure that the structural integrity of all high-energy (two phase as well as single phase) carbon steel systems is maintained.

Georgia Power Company (GPC) has developed and implemented an erosion / corrosion monitoring program for Vogtle Unit 1.

This program is described in the document "Alvin W. Vogtle Nuclear Plant Unit 1 Erosion / Corrosion Program",

which is available for NRC review at the Vogtle site.

Baseline inspections for Unit I were performed during its first refueling outage. We have reviewed the Vogtle Unit 1 program and have concluded that the current program meets the intent of the NUMARC guidelines.

We have, however, identified a few areas where strengthening of the program is appropriate in light of Generic Letter 89 08.

Revisions addressing these areas will be implemented prior to the o

second Unit 1 refueling outage. We have also identified the need for further procedural controls addressing implementation oi the program.

It has been G?C's intent to implement the erosion / corrosion monitoring program on an on. going basis; however, procedures do not explicitly require continuing implementation. We will make the necessary procedural upgrades prior to the second (Jnit i refueling outage.

An erosion / corrosion monitoring program will be developed for Unit 2 prior to its first refueling outage. This program will be equivalent to the Unit 1 program and will be subject to formal procedural controls to assure continuing implementation.

Baseline inspections for Unit 2 will be performed during its first refueling outage.

8907180001 890711 PDR ADOCK 05000424 4

p PDC l \\

j e.

s e

l Georgia Power A U. S. Nuclear Regulatory Commission ELV-00634 Page Two Plant Vogtle will.be in compliance with Generic Letter 89-08'upon completion of the actions described above. As stated above, the required actions will be completed prior to the secoral refueling outage for Unit 1, and prior to the first refueling outage for Unit 2.

These outages are scheduled to begin in February,1990, and September,1990, respectively.

If you have any questions, please contact this office.

Mr. W. G. Hairston, III states that he is a Senior Vice President of Georgia Power Company and is authorized to execute this oath on behalf of Georgia Power Company and that, to the best of his knowledge and belief, the facts set forth in this letter are true.

GEORGIA POWER COMPANY By:

M

.d CT W. G. Hai rston, III Sworn to and subscribed before me this //b day of July,1989.

h/MLot$m?N$k Y Notary Public MY COMMISSION EXPlRES DEC.15.1992 WGH,III/JH/gm xc: Georgia Power Cmpany Mr. C. K. McCoy Mr. G. Bockhold, Jr.

Mr. J. P. Kane Mr. 1.. A. Wa rd NORMS U. S. Nuclear Regulatory Commission Mr. 5. D. Ebneter, Regional Administrator Mr. J. r. H pkins, Licensing Project Manager, NRR Mr. J. F. Rogge, Senior Resident Inspector, Vogtle

_