MONTHYEARDCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-055, Nuclear Material Transaction Report for New Fuel2023-07-0606 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-042, Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 02023-05-24024 May 2023 Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 0 DCL-23-032, Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program2023-05-22022 May 2023 Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program DCL-23-041, 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20222023-05-22022 May 2023 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2022 DCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule DCL-23-034, 2022 Annual Nonradiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Nonradiological Environmental Operating Report DCL-23-036, 2022 Annual Radiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Radiological Environmental Operating Report DCL-23-025, 2022 Annual Radioactive Effluent Release Report2023-05-0101 May 2023 2022 Annual Radioactive Effluent Release Report DCL-2023-512, Submittal of Receiving Water Monitoring Program 2022 Annual Report2023-04-27027 April 2023 Submittal of Receiving Water Monitoring Program 2022 Annual Report DCL-23-035, Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application2023-04-24024 April 2023 Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application DCL-23-028, Technical Specification Bases, Revision 142023-04-24024 April 2023 Technical Specification Bases, Revision 14 DCL-2023-511, Report on Discharge Monitoring for the First Quarter of 20232023-04-20020 April 2023 Report on Discharge Monitoring for the First Quarter of 2023 DCL-23-031, Submittal of Annual Report of Occupational Radiation Exposure for 20222023-04-19019 April 2023 Submittal of Annual Report of Occupational Radiation Exposure for 2022 DCL-23-024, Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System2023-04-0404 April 2023 Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System DCL-23-022, 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant2023-03-29029 March 2023 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-23-021, Independent Spent Fuel Storage Installation, Emergency Plan Update2023-03-23023 March 2023 Independent Spent Fuel Storage Installation, Emergency Plan Update DCL-23-020, Responses to NRC Questions Regarding License Renewal Efforts2023-03-17017 March 2023 Responses to NRC Questions Regarding License Renewal Efforts DCL-23-009, Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage2023-02-22022 February 2023 Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage DCL-23-008, Request Regarding Senior Reactor Operator License Application2023-02-22022 February 2023 Request Regarding Senior Reactor Operator License Application DCL-2023-503, Annual Sea Turtle Report2023-01-26026 January 2023 Annual Sea Turtle Report DCL-2023-502, (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring2023-01-18018 January 2023 (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring DCL-22-091, Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage2022-12-20020 December 2022 Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage DCL-22-089, Core Operating Limits Report for Unit 2 Cycle 242022-12-20020 December 2022 Core Operating Limits Report for Unit 2 Cycle 24 DCL-22-085, Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application2022-10-31031 October 2022 Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 2024-01-29
[Table view] |
Text
Pacific Gas and Electric Company' James R. Becker Diablo Canyon Power Plant Vice President P.0. Box 56 September 29, 2006 Diablo Canyon Operations and Avila Beach, CA 93424 Station Director 805.545.3462 PG&E Letter DCL-06-114 Fax: 805.545.4234 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Docket No. 50-323, OL-DPR-82 Diablo Canyon Unit 2 Response to Request for Additional Information Reqarding License Amendment Request 06-02, "Revision to Technical Specification 5.6.5, 'Core Operatinq Limits Report (COLR)"
Dear Commissioners and Staff:
Pacific Gas and Electric Company Letter DCL-06-006, dated January 13, 2006, submitted License Amendment Request (LAR) 06-02, "Revision to Technical Specification 5.6.5, 'Core Operating Limits Report (COLR)."' LAR 06-02 proposes to revise Technical Specification (TS) 5.6.5, "Core Operating Limits Report (COLR),"
by adding WCAP-1 6009-P-A, "Realistic Large-Break LOCA Evaluation Methodology Using the Automated Statistical Treatment of Uncertainty Method (ASTRUM)," dated January 2005, as an approved analytical method for determining core operating limits for Unit 2.
On July 14, 2006, the NRC staff requested additional information required to complete the review of LAR 06-02. The enclosure provides the requested information.
The response provided in this submittal does not affect the results of the technical evaluation or the no significant hazards consideration determination previously transmitted in DCL-06-006.
PG&E makes no regulatory commitments or revisions to regulatory commitments in this letter. If you have any questions or require additional information, please contact Stan Ketelsen at (805) 545-4720.
I declare under pena erjury that the foregoing is true and correct.
Exe uted on Fp. 920 James R. Becker A member of the STARS (Strategic Teaming and Resource Sharing) Alliance 7)/
Callaway o Comanche Peak
Document Control Desk PG&E Letter DCL-06-114 IPJ.
E-I September 29, 2006 Page 2 jerl /3664 Enclosure cc: Edgar Bailey, DHS Terry W. Jackson Bruce S. Mallett Diablo Distribution cc/enc: Alan B. Wang A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
Enclosure PG&E Letter DCL-6-114 Response to Request for Additional Information Regarding License Amendment Request 06-02, "Revision to Technical Specification 5.6.5,
'Core Operating Limits Report (COLR)"'
NRC Question No. I Confirm that performing the Unit 2 BELOCA [best estimate loss of coolant loss-of-coolant accident]analysis with an assumed nominal core power level of 3468 MWt [megawatt, thermal]and an associateduncertaintyof 0.3 percent is conservatively bounding.
PG&E Response to Question No. I The BELOCA methodology used in WCAP-1 6009-P-A, "Realistic Large-Break LOCA Evaluation Methodology Using the Automated Statistical Treatment of Uncertainty Method (ASTRUM)," performs a statistical treatment of key parameter uncertainties in order to calculate a ninety fifth percentile peak cladding temperature (PCT) value. The core power level is one of the key input parameters, which is randomly sampled for each of the 124 WCOBRA/TRAC cases, which are analyzed to establish the ninety fifth percentile PCT result. A greater core power level results in increased initial fuel temperatures and decay heat for a given case analysis and thus generates a more limiting PCT result. In order to conservatively bound any future potential increase in the licensed maximum core power level associated with a measurement uncertainty recapture (MUR) power uprate, the Unit 2 BELOCA analysis was performed with an assumed core power level of 3468 MWt. This analyzed core power level represents a 1.7 percent increase with respect to the current Unit 2 licensed maximum core power level of 3411 megawatt, thermal (MWt). The ASTRUM BELOCA statistical analysis was then performed based on a uniform probability distribution corresponding to 0.3 percent uncertainty about the assumed value of 3468 MWt.
Figure 1 shows example plots of the uniform probability distribution for a core power level of 3411 MWt analyzed with a 2 percent uncertainty, and the Unit 2 ASTRUM BELOCA assumed core power level of 3468 MWt with a 0.3 percent analyzed uncertainty. The figure shows the core power probability distribution analyzed for the Unit 2 ASTRUM BELOCA results in a significant shift and increase in the probabilistic power level compared to the 3411 MWt case with a 2 percent uncertainty. Since an increase in the analyzed core power level results in a larger PCT value, the Unit 2 ASTRUM BELOCA analyzed a more limiting core power level probability distribution and generated PCT results that are conservatively bounding for the current Unit 2 licensed maximum core power level of 3411 MWt with a 2 percent uncertainty.
1
Enclosure PG&E Letter DCL-6-114 NRC Question No. 2 Confirm that PG&E is not implementing any core power level changes for Unit 2 as part of this COLR amendment and any such core power uprate will only be implemented in a separatelicense amendment.
PG&E Response to Question No. 2 PG&E is not implementing any core power level changes as part of this COLR license amendment. The assumed nominal core power level for the ASTRUM BELOCA analysis was increased to preclude having to perform a BELOCA re-analysis should a MUR power uprate be implemented for Unit 2. Any such calorimetric power uprate would only be implemented following NRC approval of a separate license amendment request that evaluates the applicable license and design basis changes.
Figure 1: Examples of Uniform Probability Distributions for Assumed for BELOCA Power Levels 0.05 3411 MWt wI 2% uncertainty
- 3468 MWt w/ 0.3% uncertainty 0.03 0.02 0 0.02 0.01-3300 3350 3400 3450 3500 Power Level 2