MONTHYEARDCL-22-077, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2022-09-28028 September 2022 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update DCL-19-093, Independent Spent Fuel Storage Installation - Emergency Plan Facilities and Equipment Update, Section 72019-11-18018 November 2019 Independent Spent Fuel Storage Installation - Emergency Plan Facilities and Equipment Update, Section 7 DCL-19-068, Independent Spent Fuel Storage Installation, Emergency Plan Implementing Procedure Update2019-09-12012 September 2019 Independent Spent Fuel Storage Installation, Emergency Plan Implementing Procedure Update DCL-19-014, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2019-02-14014 February 2019 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update DCL-19-002, Emergency Plan Implementing Procedure Update2019-01-15015 January 2019 Emergency Plan Implementing Procedure Update DCL-18-095, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2018-11-14014 November 2018 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update DCL-18-094, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2018-11-13013 November 2018 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update DCL-18-082, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2018-10-15015 October 2018 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update DCL-18-077, Independent Spent Fuel Storage Installation - Appendix D, Revision 5.00, Emergency Action Level Technical Basis Manual2018-10-0404 October 2018 Independent Spent Fuel Storage Installation - Appendix D, Revision 5.00, Emergency Action Level Technical Basis Manual ML18276A2492018-09-26026 September 2018 Enclosure 1 - Diablo Canyon Power Plant Emergency Plan Revision Numbers for Emergency Plan Sections and Appendices DCL-18-063, Emergency Plan Implementing Procedure Update2018-08-23023 August 2018 Emergency Plan Implementing Procedure Update DCL-18-056, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2018-07-25025 July 2018 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update DCL-18-029, Independent Spent Fuel Storage Installation - Emergency Plan Implementing Procedure Update2018-04-11011 April 2018 Independent Spent Fuel Storage Installation - Emergency Plan Implementing Procedure Update L-17-014, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2017-12-21021 December 2017 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update L-17-008, ISFSI - Emergency Plan Implementing Procedure Update2017-09-0707 September 2017 ISFSI - Emergency Plan Implementing Procedure Update DCL-17-016, Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Implementing Procedures Update2017-03-0101 March 2017 Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Implementing Procedures Update ML17047A5442017-02-16016 February 2017 Diablo Canyon Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedures Update DCL-16-120, Independent Spent Fuel Storage Installation - Emergency Plan Implementing Procedures Updates2016-11-17017 November 2016 Independent Spent Fuel Storage Installation - Emergency Plan Implementing Procedures Updates DCL-16-109, Independent Spent Fuel Storage Installation - Revision to Emergency Plan Implementing Procedure Updates2016-10-19019 October 2016 Independent Spent Fuel Storage Installation - Revision to Emergency Plan Implementing Procedure Updates DCL-16-092, ISFSI Emergency Plan Implementing Procedure Update2016-09-21021 September 2016 ISFSI Emergency Plan Implementing Procedure Update DCL-16-076, Submittal of ISFSI Emergency Plan Implementing Procedure Update2016-07-26026 July 2016 Submittal of ISFSI Emergency Plan Implementing Procedure Update DCL-16-026, ISFSI - Emergency Plan Implementing Procedure Update, Including Revision 33 to EP R-2, Release of Airborne Radioactive Materials Initial Assessment2016-03-0303 March 2016 ISFSI - Emergency Plan Implementing Procedure Update, Including Revision 33 to EP R-2, Release of Airborne Radioactive Materials Initial Assessment DCL-16-004, Diablo Canyon, Units 1 and 2 - Submittal of Emergency Plan and Emergency Plan Implementing Procedure Updates (Enclosures 1, 2 & 3)2016-01-0606 January 2016 Diablo Canyon, Units 1 and 2 - Submittal of Emergency Plan and Emergency Plan Implementing Procedure Updates (Enclosures 1, 2 & 3) DCL-16-004, Submittal of Emergency Plan and Emergency Plan Implementing Procedure Updates (Enclosures 1, 2 & 3)2016-01-0606 January 2016 Submittal of Emergency Plan and Emergency Plan Implementing Procedure Updates (Enclosures 1, 2 & 3) ML16021A2812016-01-0606 January 2016 Revisions to Emergency Plan Implementing Procedure Updates (Enclosures 11 and 12) DCL-09-020, Updated Emergency Plan Implementing Procedures2009-03-30030 March 2009 Updated Emergency Plan Implementing Procedures DCL-08-096, Emergency Plan Implementing Procedure Update2008-11-19019 November 2008 Emergency Plan Implementing Procedure Update DCL-08-097, Submittal of Revision 4 to Emergency Plan Update2008-11-19019 November 2008 Submittal of Revision 4 to Emergency Plan Update DCL-04-032, Emergency Plan Implementing Procedure Update2004-03-29029 March 2004 Emergency Plan Implementing Procedure Update DCL-03-145, Emergency Plan Implementing Procedure Update2003-11-10010 November 2003 Emergency Plan Implementing Procedure Update DCL-03-128, Emergency Plan Implementing Procedure Update2003-10-13013 October 2003 Emergency Plan Implementing Procedure Update DCL-03-073, Emergency Plan Implementing Procedure Update2003-06-19019 June 2003 Emergency Plan Implementing Procedure Update DCL-03-024, Emergency Plan Implementing Procedure Update2003-03-0505 March 2003 Emergency Plan Implementing Procedure Update DCL-02-140, Emergency Plan Implementing Procedure Update2002-12-0606 December 2002 Emergency Plan Implementing Procedure Update DCL-02-130, Emergency Plan Implementing Procedure Update2002-11-0808 November 2002 Emergency Plan Implementing Procedure Update DCL-02-122, Emergency Plan Implementing Procedure Update2002-10-14014 October 2002 Emergency Plan Implementing Procedure Update DCL-02-056, Revision 31 to EP G-1, Emergency Classification and Emergency Plan Activation.2002-05-0303 May 2002 Revision 31 to EP G-1, Emergency Classification and Emergency Plan Activation. DCL-02-013, Emergency Plan Implementing Procedure Update2002-02-0808 February 2002 Emergency Plan Implementing Procedure Update DCL-00-124, Units I and 2 - Emergency Plan Implementing Procedure Update2000-09-29029 September 2000 Units I and 2 - Emergency Plan Implementing Procedure Update 2022-09-28
[Table view] |
Text
N' I Electric Company PacificGas and Diablo Canyon Power Plant P0 Box 56 Avila Beach. CA 93424 October 14, 2002 800545 6000 PG&E Letter DCL-02-122 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Emer-gency Plan Implementing Procedure Update
Dear Commissioners and Staff:
In accordance with Section V, "Implementing Procedures," of 10 CFR 50, Appendix E, enclosed is an update to the emergency plan (EP) implementing procedures for Diablo Canyon Power Plant, Units 1 and 2.
As provided under 10 CFR 50.54(q), the changes have been made without prior NRC approval since they do not decrease the effectiveness of the EP. The EP, as changed, continues to meet the standards of 10 CFR 50.47(b) and 10 CFR 50, Appendix E.
This update contains privacy/proprietary information that has been bracketed in accordance with NRC Generic Letter 81-27.
If there are any questions regarding this update, please contact Mr. Mark Lemke of my staff at\(805) 545-4787.
Grant C. Gillies Director,Site Services bafi1 345 Enclosures cc: David L. Proulx Girija S. Shukla cclenc: Ellis W. Merschoff (2) yU45 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway e Comanche Peak
- Diablo Canyon a Palo Verde 9 South Texas Project
Enclosure 1 PG&E Letter DCL-02-122 LOCATION OF PRIVACY/PROPRIETARY INFORMATION IN EMERGENCY PLAN IMPLEMENTING PROCEDURES FOR DIABLO CANYON POWER PLANT, UNITS 1 AND 2 Privacy/
Procedure Proprietary Number Information Title/Location of Privacy/Proprietary Information EP G-3 Yes Notification of Off-Site Agencies and Emergency Rev. 39 Response Organization Personnel Attachment 7.1 Page 1 of 4 Attachment 7.2 Page 2 of 2 Attachment 7.3 Page 1 of 1 EP G-4 Yes Assembly and Accountability Rev. 19 Page 6 of 8 Attachment 7.2 Page 1 of 1 EP RB-8 Yes Instructions for Field Monitoring Teams Rev. 16 Attachment 7.2 Page 1 of 3 Attachment 7.2 Page 2 of 3 Attachment 7.2 Page 3 of 3 Attachment 7.4 Page 1 of 1 Attachment 7.5 Page 1 of 1 Attachment 7.6 Page 1 of 1
Enclosure 2 "PG&ELetter DCL-02-122 DIABLO CANYON POWER PLANT EMERGENCY PLAN IMPLEMENTING PROCEDURES Table of Contents - Emergency Plan Implementing Procedures Volume 1A (OM10.1D3 only), Volume 1B (OM10.DC1 only), and Volume 3B Proc. ,No. Rev. Title OM10.1D3 6 Emergency Plan Training OMI0.DCI 2 Emergency Preparedness Drills and Exercises EP G-1 31 Emergency Classification and Emergency Plan Activation EP G-2 25 Activation and Operation of the Interim Site Emergency Organization (Control Room)
EP G-3* 39 Notification of Off-Site Agencies and Emergency Response Organization Personnel EP G-4* 19 Personnel Assembly, Accountability and Site Access Control During Emergencies EP G-5 9A Evacuation of Nonessential Site Personnel EP R-2 20 Release of Airborne Radioactive Materials Initial Assessment EP R-3 8C Release of Radioactive Liquids EP R-7 13 Off-Site Transportation Accidents EP OR-3 6A Emergency Recovery EP RB-1 5B Personnel Dosimetry EP RB-2 4B Emergency Exposure Guides EP RB-3 4 Stable Iodine Thyroid Blocking EP RB-4 4A Access to and Establishment of Controlled Areas Under Emergency Conditions EP RB-5 4C Personnel Decontamination EP RB-8* 16 Instructions for Field Monitoring Teams EP RB-9 11 Calculation of Release Rate EP RB-10 8 Protective Action Recommendations EP RB-1I 12 Emergency Offsite Dose Calculations EP RB-12 6 Plant Vent Iodine and Particulate Sampling During Accident Conditions EP RB-14 7 Core Damage Assessment Procedure EP RB-15 11 Post Accident Sampling System EP EF-1 29 Activation and Operation of the Technical Support Center EP EF-2 26 Activation and Operation of the Operational Support Center EP EF-3 22 Activation and Operation of the Emergency Operations Facility EP EF-4 14 Activation of the Off-Site Emergency Laboratory EP EF-9 8 Backup Emergency Response Facilities EP EF-10 5 Joint Media Center Activation and Operation
- Procedure included in this submittal