MONTHYEARCNL-22-027, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 40 - Annual Update and Proposed Changes to Revision 402022-04-28028 April 2022 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 40 - Annual Update and Proposed Changes to Revision 40 CNL-22-019, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Reduction in Commitment2022-02-0404 February 2022 Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Reduction in Commitment CNL-21-045, Bellefonte Nuclear Plant, Units 1 and 2; Browns Ferry Nuclear Plant, Units 1, 2, and 3; Clinch River Nuclear Site; Sequoyah Nuclear Plant, Units 1 and 2; Watts Bar Nuclear Plant, Unit 1 and 2 - Nuclear Quality Assurance Plan, TVA-NQA-PLN82021-04-29029 April 2021 Bellefonte Nuclear Plant, Units 1 and 2; Browns Ferry Nuclear Plant, Units 1, 2, and 3; Clinch River Nuclear Site; Sequoyah Nuclear Plant, Units 1 and 2; Watts Bar Nuclear Plant, Unit 1 and 2 - Nuclear Quality Assurance Plan, TVA-NQA-PLN89- CNL-20-039, Bellefonte Nuclear Plant, 1 & 2; Browns Ferry Nuclear Plant, 1 & 2; Clinch River Site; Sequoyah Nuclear Plant, 1 & 2; and Watts Bar Nuclear Station, Units 1 & 2 - Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 382020-04-30030 April 2020 Bellefonte Nuclear Plant, 1 & 2; Browns Ferry Nuclear Plant, 1 & 2; Clinch River Site; Sequoyah Nuclear Plant, 1 & 2; and Watts Bar Nuclear Station, Units 1 & 2 - Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 38 CNL-19-043, Bellefont Nuclear Plant, Units 1 & 2; Browns Ferry Nuclear Plan, Units 1, 2 & 3; Clinch River Nuclear Site; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, R2019-05-0808 May 2019 Bellefont Nuclear Plant, Units 1 & 2; Browns Ferry Nuclear Plan, Units 1, 2 & 3; Clinch River Nuclear Site; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Rev CNL-19-037, Clinch River, Response to Request for Supplemental Information Regarding Changes Made in Revision 2 of the Application for Early Site Permit2019-03-25025 March 2019 Clinch River, Response to Request for Supplemental Information Regarding Changes Made in Revision 2 of the Application for Early Site Permit CNL-19-018, Resubmittal of Clinch River Nuclear Site Early Permit Application, Revision 22019-01-18018 January 2019 Resubmittal of Clinch River Nuclear Site Early Permit Application, Revision 2 CNL-18-126, Response to Request for Additional Information, Erai 9602, Related to EIS Postulated Accidents in Support of Early Site Permit Application for Clinch River Nuclear Site2018-10-0505 October 2018 Response to Request for Additional Information, Erai 9602, Related to EIS Postulated Accidents in Support of Early Site Permit Application for Clinch River Nuclear Site CNL-18-115, Status of Clinch River Breeder Reactor Project Wells2018-09-0707 September 2018 Status of Clinch River Breeder Reactor Project Wells CNL-18-069, Tennessee Valley Authority - Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revisions 35 and 362018-05-0808 May 2018 Tennessee Valley Authority - Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revisions 35 and 36 CNL-18-076, Update to Site Safety Analysis Report Section 17.5, Quality Assurance, in Support of Early Site Permit Application for Clinch River Nuclear Site2018-05-0404 May 2018 Update to Site Safety Analysis Report Section 17.5, Quality Assurance, in Support of Early Site Permit Application for Clinch River Nuclear Site CNL-18-059, Submittal of Revised Site Safety Analysis Report Subsection 2.4.2.2, Flood Design Considerations, and Subsection 2.4.3.5, Probable Maximum Flood Flow, and Figure 2.4.3-3 in Support of Early Site Permit Application for Clinch River Nuclear2018-04-27027 April 2018 Submittal of Revised Site Safety Analysis Report Subsection 2.4.2.2, Flood Design Considerations, and Subsection 2.4.3.5, Probable Maximum Flood Flow, and Figure 2.4.3-3 in Support of Early Site Permit Application for Clinch River Nuclear S CNL-18-072, Comments on Safety Evaluations2018-04-27027 April 2018 Comments on Safety Evaluations CNL-18-071, Supplemental Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application for Clinch River Nuclear Site2018-04-27027 April 2018 Supplemental Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application for Clinch River Nuclear Site CNL-18-049, Clinch River Nuclear Site, Response to NRC Request for Additional Information 12 in Support of Early Site Permit Application for Clinch River Nuclear Site2018-04-0909 April 2018 Clinch River Nuclear Site, Response to NRC Request for Additional Information 12 in Support of Early Site Permit Application for Clinch River Nuclear Site CNL-18-045, Clinch River, Voluntary Submittal Comparing Offsite Atmospheric Dispersion Using Vector and Scalar Wind Direction in Support of Early Site Permit Application2018-04-0909 April 2018 Clinch River, Voluntary Submittal Comparing Offsite Atmospheric Dispersion Using Vector and Scalar Wind Direction in Support of Early Site Permit Application CNL-18-046, Clinch River, Response to Portion of Request for Additional Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application2018-03-30030 March 2018 Clinch River, Response to Portion of Request for Additional Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application CNL-18-043, Clinch River - Submittal of Revised Site Safety Analysis Report Subsection 2.4.3.2, Probable Maximum Precipitation, in Support of Early Site Permit Application2018-03-16016 March 2018 Clinch River - Submittal of Revised Site Safety Analysis Report Subsection 2.4.3.2, Probable Maximum Precipitation, in Support of Early Site Permit Application CNL-18-020, Clinch River, Response to Portion of Request for Additional Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application2018-03-0909 March 2018 Clinch River, Response to Portion of Request for Additional Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application CNL-18-019, Replacement Pages for Response to Request for Additional Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application for Clinch River Nuclear Site2018-02-20020 February 2018 Replacement Pages for Response to Request for Additional Information Related to Emergency Planning Exemption Requests in Support of Early Site Permit Application for Clinch River Nuclear Site CNL-17-151, of Application for Early Site Permit for Clinch River Nuclear Site2017-12-15015 December 2017 of Application for Early Site Permit for Clinch River Nuclear Site CNL-17-118, Supplemental Information Related to Environmental Report Figures in Support of Early Site Permit Application for Clinch River Nuclear Site2017-09-0505 September 2017 Supplemental Information Related to Environmental Report Figures in Support of Early Site Permit Application for Clinch River Nuclear Site CNL-17-094, Submittal of Supplemental Information Associated with Hydrologic Engineering in Support of the Clinch River Nuclear Site Early Site Permit Application2017-07-18018 July 2017 Submittal of Supplemental Information Associated with Hydrologic Engineering in Support of the Clinch River Nuclear Site Early Site Permit Application CNL-17-081, Clinch River - Submittal of Hydrology Calculation Input Files in Response to the Hydrology Audit of Plant Early Site Permit Application2017-06-15015 June 2017 Clinch River - Submittal of Hydrology Calculation Input Files in Response to the Hydrology Audit of Plant Early Site Permit Application CNL-17-074, Submittal of Supplemental Information Related to the Hydrologic Engineering in Support of the Clinch River Nuclear Site Early Site Permit Application - Groundwater2017-06-0707 June 2017 Submittal of Supplemental Information Related to the Hydrologic Engineering in Support of the Clinch River Nuclear Site Early Site Permit Application - Groundwater CNL-17-070, Clinch River Nuclear Site - Submittal of Supplemental Information Associated with Hydrologic Engineering in Support of the Clinch River Nuclear Site Early Site Permit Application2017-06-0505 June 2017 Clinch River Nuclear Site - Submittal of Supplemental Information Associated with Hydrologic Engineering in Support of the Clinch River Nuclear Site Early Site Permit Application 2022-04-28
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, TN 37402 CNL-18-115 September 7, 2018 10 CFR 52, Subpart A ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Clinch River Nuclear Site NRC Docket No.52-047
Subject:
Status of Clinch River Breeder Reactor Project Wells
Reference:
Letter from TVA to NRC, CNL-17-151, Revision 1 of Application for Early Site Permit for Clinch River Nuclear Site, dated December 15, 2017 By letter dated December 15, 2017 (Reference), Tennessee Valley Authority (TVA) submitted Revision 1 of the application for an early site permit (ESPA) for the Clinch River Nuclear (CRN)
Site in Oak Ridge, TN. As stated in Part 2, Site Safety Analysis Report (SSAR), Subsection 2.4.12.1.4.1, CRBRP Investigation, and Part 3, Environmental Report (ER), Subsection 2.3.1.2.1.4.1, CRBRP Investigation, TVA identified no abandoned wells in the area adjacent to the Clinch River Breeder Reactor Project (CRBRP) excavation while performing the well drilling associated with the CRN Site subsurface investigation. These ESPA subsections further state that it is likely that the wells were destroyed and/or removed during site excavation and subsequent site redress.
During a routine site walk-down in April 2018, one CRBRP groundwater well was found open.
TVA subsequently performed two searches of the site in an effort to identify other CRBRP wells.
During the searches two additional groundwater wells were found. The statements in SSAR Subsection 2.4.12.1.4.1 and ER Subsection 2.3.1.2.1.4.1 will be changed in a future revision of the CRN ESPA to state, Abandoned wells from the CRBRP were identified on site. The identified CRBRP wells will be evaluated for closure in accordance with applicable TVA and TDEC [Tennessee Department of Environment and Conservation] requirements.
TVA has evaluated the effects of the CRBRP groundwater wells on the assumptions made in the CRN ESPA regarding the potential for transport to groundwater. As described in SSAR Subsection 2.4.13.1, Accident Source, no credit is taken for the time that radionuclides may take (and the associated radioactive decay) to travel from the ruptured tank to the saturated zone. Therefore, the existence of CRBRP groundwater wells on the CRN Site has no impact on the analyses results and does not change the conclusion in the CRN ESPA regarding the potential for transport to groundwater.
U.S. Nuclear Regulatory Commission CNL-18-115 Page 2 September 7, 2018 There are no new regulatory commitments associated with this submittal. If any additional information is needed, please contact Dan Stout at (423) 751-7642.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 7th day of September 2018.
Respectfully,
(}~
J.J_Shea
\/if *~resident, Nuclear Regulatory Affairs and Support Services cc:
A. Fetter, Project Manager, Division of New Reactor Licensing, USNRC M. Sutton, Project Manager, Division of New Reactor Licensing, USNRC C. Haney, Regional Administrator, Region II, USNRC R. Taylor, Director, Division of New Reactor Licensing, USNRC J. Rankin, Branch Chief, Division of New Reactor Licensing, USNRC T. Dozier, Project Manager, Division of New Reactor Licensing, USNRC M. M. McIntosh, Regulatory Specialist, Eastern Regulatory Field Office, Nashville District, USACE