CAC:MF5447
From kanterella
Jump to navigation
Jump to search
Request for: Open | |
Initiation
Questions Answers | |
From | |
MONTHYEARML0816803172008-07-23023 July 2008
[table view]Title: Approval of Request for Relief No. ANO 1-ISI-010 for the Third 10-Year Inservice Inspection Interval Site: Arkansas Nuclear DCL-14-111, American Society of Mechanical Engineers Section Xl Lnservice Inspection Program Relief Request NDE-RCS-SE-2R19 - Use of Alternate Sizing Qualification Criteria Through a Protective Clad Layer2014-12-0202 December 2014 Title: American Society of Mechanical Engineers Section Xl Lnservice Inspection Program Relief Request NDE-RCS-SE-2R19 - Use of Alternate Sizing Qualification Criteria Through a Protective Clad Layer Site: Diablo Canyon ML14352A0172014-12-17017 December 2014 Title: NRR E-mail Capture - Diablo Canyon Power Plant, Unit 2 - Acceptance Review for ASME Section XI ISI Program Relief Request NDE-RCS-SE-2R19 Site: Diablo Canyon 1CAN041603, Request for Relief from ASME Section XI, Table IWB-2500-1 Requirements2016-04-22022 April 2016 Title: Request for Relief from ASME Section XI, Table IWB-2500-1 Requirements Site: Arkansas Nuclear 1CAN071601, Request for Relief from ASME Section XI Table IWB-2500-1 Requirements2016-07-13013 July 2016 Title: Request for Relief from ASME Section XI Table IWB-2500-1 Requirements Site: Arkansas Nuclear 2014-12-02 |
Retrieved from "https://kanterella.com/w/index.php?title=CAC:MF5447&oldid=482615"