September 6, 2007 BW070067 U. S. Nuclear Regulatory Commission Region Ill 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Attn: Operator Licensing Branch Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. 50-456 and 50-457

Subject:

Updated Braidwood Future Initial License Training Schedule Dates

Reference:

Letter from D. M. Benyak (Exelon Generation Company, LLC and AmerGen Energy Company, LLC) to U. S. NRC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations, dated August 13, 2007 The purpose of this letter is to provide revised operator license examination dates in response to NRC Regulatory Issue Summary (RIS) 2007-17, Preparation and Scheduling of Operator Licensing Examinations for Braidwood Station. This updated information revises the proposed operator license examination dates originally provided in the referenced letter.

The revised operator license examination dates are provided in the attached NRC Form 536.

If you have any questions about this letter, please contact Mr. David Guflott at (815) 417-2800.

Thomas Coutu Site Vice President Braidwood Nuclear Power Station.

TC/DG/vk

Attachment:

Revised NRC Form 536 - Braidwood Station Page 1 of 1 NRC FORM 536 LS NLCLEAR REGULATORY COMMISSION (8-20(15)

OPERATOR LICENSING EXANII1ATION DATA APPROVED BY 0MB: NO. 3150-0131 EXPiRES: 0813t12))08 Estimated burden per response toe oeply wuh this duntary information cii)ection request: I h inc this mtormation collection is used to plan budgets and resources In perati r examiuati sos. Send comments re~ardm~

burden eslimateto the Records and FOIA/Pris acySers soes Br inch ~T-5 F~3).US Nuclear Reeulatory Comntission, Washingt Sn, DC 20555 (5)01 orby iomatl to ini~ici(lects@nrcgov, and to the Desk Ofitcer, Office oftntormutn n and Regulatory Affairs, NEOB 0202, (3t50 0131). Offices) Management and Budget. Washington. DC20503. if a means used to impose an nformation coltectum does not display a currently saud 0MB centre number, the NRC may m t condnct orsp nior. and a person is not required to respond to, the mformatis n collection.

FACILITY Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 NRC REGION III A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2008 CY 2009 CY 2010 CY 2011 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS 0

1 0

1 ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS 0

0 0

0 B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2008 CY 2009 CY 2010 CY 2011 NUMBER OF REACTOR OPERATORS 0

1 0

6 NUMBER OF SENIOR REACTOR OPERATORS-INSTANT 0

13 0

12 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0

1 0

2 NUMBER OF SENIOR REACTOR OPERATORS-LIMITED 0

0 0

0 PROPOSED DATES PRIMARY DATE 10/5/09 6/27/2011

7/15/2011 ALTERNATE DATE 10/19/09 7/05/2011

7/22/2011 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER cY2008 cY2009 MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBEROF CANDIDATES 0

14 0

0 0

0 0

18