Exek'n.
Exelon Generation Company, LLC www.exeloncorp.coin Nuclear Braidwood Station 35100 South Rt 53, Suite 84 Braceville, IL 60407-9619 Tel. 815-417-2000 February 10, 2006 BWO600)1 4 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457
Subject:
Regulatory Commitment Change Summary Report The purpose of this letter is to provide the "Regulatory Commitment Change Summary Report," for Braidwood Station. This report pertains to the time frame from January 1, 2005 through December 31, 2005.
Commitment changes involving revisions to docketed correspondence are processed using the Nuclear Energy Institute's (NEI) 99-04, Revision 0, "Guidelines for Managing NRC Commitment Changes," dated July 1999 and applicable procedures.
For the time frame in question, no commitment changes were revised utilizing this process.
Should you have any questions concerning this letter, please contact Mr. Dale Ambler, Regulatory Assurance Manager, at (815) 417-2800.
Respectfully, Keith J. Polson Site Vice President Braidwood Station KP/LD/vk cc:
Regional Administrator - NRC Region IlIl NRC Senior Resident Inspector - Braidwood Station
,4 Col