MONTHYEARBVY 24-028, Pre-Notice of Disbursement from Decommissioning Trust2024-10-31031 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-10-30030 October 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust 2024-07-30
[Table view] |
Text
Entergy Nuclear Operations, Inc.
Vermont Yankee E ergy 320 Governor Hunt Road Vernon, Vermont 05354 Tel: (802) 257-7711 Christopher J. Wamser Site Vice President BVY 12-080 November 27, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Seismic Walkdown Report - Entergy's Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28
REFERENCES:
- 1. NRC Letter to Entergy, Request for Information Pursuantto Title 10 of the Code of FederalRegulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012
- 2. Entergy Letter to NRC, Entergy's 120-Day Response to NRC Request for Information (RFI) Pursuantto 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichiAccident, BVY 12-049, dated July 10, 2012
Dear Sir or Madam:
On March 12, 2012, the NRC issued Reference 1 to all power reactor licensees. of Reference 1 contains specific requested actions, requested information, and required responses associated with Recommendation 2.3 for seismic walkdowns.
Entergy Nuclear Operations, Inc., (Entergy) confirmed in Reference 2 that it would use the seismic walkdown procedure (EPRI Report 1025286, Seismic Walkdown Guidance For Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic) as endorsed by the NRC as the basis to conduct the walkdowns and develop the needed information at Vermont Yankee.
Pursuant to Required Response 2 in Enclosure 3 of Reference 1, Entergy is providing the Seismic Walkdown Report for Vermont Yankee in Attachment 2. All potentially adverse seismic conditions identified in the report have been evaluated in the Corrective Action Program (CAP) for operability concerns and no immediate operability concerns have been identified.
BVY 12-080 / Page 2 of 3 Should you have any questions regarding this submittal, please contact Mr. Robert J.
Wanczyk at (802) 451-3166.
This letter contains new regulatory commitments, which are identified in Attachment 1.
I declare under penalty of perjury that the foregoing is true and correct; executed on November 27, 2012.
Sincerely, CJW/JTM Attachments: 1. List of Regulatory Commitments
- 2. Vermont Yankee Seismic Walkdown Submittal Report cc: Mr. William M. Dean (with Attachment 2 on CD)
Regional Administrator U. S. Nuclear Regulatory Commission, Region 1 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 U. S. Nuclear Regulatory Commission (with Attachment 2 on CD)
Attn: Director, Office of Nuclear Reactor Regulation One White Flint North 11555 Rockville Pike Rockville, MD 20852 NRC Senior Resident Inspector (with Attachment 2 on CD)
Vermont Yankee 320 Governor Hunt Road.
Vernon, Vermont 05354 U. S. Nuclear Regulatory Commission (with Attachment 2 on CD)
ATTN: Richard V. Guzman Mailstop 08C2 11555 Rockville Pike Rockville, MD 20852-2378 U. S. Nuclear Regulatory Commission (with Attachment 2 on CD)
ATTN: Robert J. Fretz Jr.
OWFN - Mailstop 4A15A 11555 Rockville Pike Rockville, MD 20852-2378
BVY 12-080 / Page 3 of 3 cc list continued:
U. S. Nuclear Regulatory Commission (with Attachment 2 on CD)
ATTN: Robert L. Dennig OWFN - Mailstop 1OE1 11555 Rockville Pike Rockville, MD 20852-2378 Ms. Elizabeth Miller, Commissioner (with Attachment 2 on CD)
VT Department of Public Service 112 State Street, Drawer 20 Montpelier, VT 05620-2601
ATTACHMENT 1 BVY 12-080 LIST OF REGULATORY COMMITMENTS
BVY 12-080 / Attachment 1 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE (Check One) SCHEDULED COMMITMENT ONE-ONE CONTINUING COMPLETION DATE (If Required)
TIME ACTION COMPLIANCE Entergy will perform walkdowns for equipment By the conclusion of that could not be inspected as identified in [,/] RFO-30 Section 6.4 of the Seismic Walkdown Report. (Spring 2013)
Within 90 days from the Entergy will submit an updated Seismic conclusion of RFO-30 Walkdown Report.
Within 6 months from Entergy will resolve the potentially adverse the conclusion of seismic conditions as identified in Section 8.2 [ RFO-30 of the Seismic Walkdown Report.