MONTHYEARAEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report AEP-NRC-2021-50, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2021-08-25025 August 2021 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2021-27, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report AEP-NRC-2020-58, Transmittal of Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2020-08-26026 August 2020 Transmittal of Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2020-29, Submittal of Annual Radiological Environmental Operating Report2020-05-14014 May 2020 Submittal of Annual Radiological Environmental Operating Report AEP-NRC-2019-43, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2019-08-29029 August 2019 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2019-16, Annual Radiological Environmental Operating Report2019-04-29029 April 2019 Annual Radiological Environmental Operating Report AEP-NRC-2018-62, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2018-08-21021 August 2018 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes ML18123A3482018-04-30030 April 2018 Donald C. Cook, Units 1 and 2, Submittal of 2017 Annual Radioactive Effluent Release Report AEP-NRC-2018-35, Annual Radioactive Effluent Release Report - Off-Site Dose Calculation Manual2018-04-30030 April 2018 Annual Radioactive Effluent Release Report - Off-Site Dose Calculation Manual AEP-NRC-2017-47, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2017-08-30030 August 2017 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2016-73, Submittal of Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2016-08-26026 August 2016 Submittal of Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2013-32, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2013-08-30030 August 2013 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2012-69, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2012-08-31031 August 2012 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2012-22, Annual Radiological Environmental Operating Report for 20112012-05-0909 May 2012 Annual Radiological Environmental Operating Report for 2011 AEP-NRC-2011-32, Annual Radiological Environmental Operating Report2011-05-13013 May 2011 Annual Radiological Environmental Operating Report AEP-NRC-2011-27, Annual Radioactive Effluent Release Report, January 1, 2010, Through December 31, 20102011-04-29029 April 2011 Annual Radioactive Effluent Release Report, January 1, 2010, Through December 31, 2010 AEP-NRC-2010-37, Submittal of 2009 Annual Environmental Operating Report2010-04-30030 April 2010 Submittal of 2009 Annual Environmental Operating Report AEP-NRC-2009-54, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2009-08-28028 August 2009 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2009-29, Submittal of Annual Radioactive Effluent Release Report for 20082009-04-29029 April 2009 Submittal of Annual Radioactive Effluent Release Report for 2008 ML0913405232009-04-29029 April 2009 Enclosure to AEP-NRC-2009-32 - Donald C. Cook, Units 1 and 2 - 2008 Annual Environmental Operating Report, Cover Through Appendix Iv AEP-NRC-2009-32, Enclosure to AEP-NRC-2009-32 - Donald C. Cook, Units 1 and 2 - 2008 Annual Environmental Operating Report, Appendix V Through End2009-04-29029 April 2009 Enclosure to AEP-NRC-2009-32 - Donald C. Cook, Units 1 and 2 - 2008 Annual Environmental Operating Report, Appendix V Through End AEP-NRC-2008-27, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2008-08-29029 August 2008 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes ML0506302372005-02-25025 February 2005 2004 Annual Operating Report ML0425300392004-08-26026 August 2004 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes ML0407009102004-03-0101 March 2004 Transmittal of 2003 Annual Operating Report ML0313606492003-04-30030 April 2003 Annual Environmental Operating Report ML0312606062003-04-30030 April 2003 Annual Radiological Environmental Operating Report, Appendix D and E, Pages D-101 Through E-3 ML0312606482003-04-30030 April 2003 Annual Radiological Environmental Operating Report, Table of Contents Through Appendix D, Pages D-1 - 100 GNRO-2003/00026, South Mississippi Electric Power Association (Smep) Annual Report for 20022003-04-28028 April 2003 South Mississippi Electric Power Association (Smep) Annual Report for 2002 ML0307005302003-02-28028 February 2003 Annual Operating Report ML0214202912002-04-25025 April 2002 Part a - Donald C. Cook Nuclear Plant, Units 1 & 2 - Annual Environmental Operating Report ML0213002702002-04-25025 April 2002 Part B - Donald C. Cook Nuclear Plant, Units 1 & 2 - Annual Environmental Operating Report ML0206001322002-02-26026 February 2002 Annual Operating Report for Donald C. Cook Nuclear Plant, Units 1 & 2 for 2001 2024-08-28
[Table view] Category:Letter type:AEP
MONTHYEARAEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-19, Annual Report of Property Insurance2024-04-0101 April 2024 Annual Report of Property Insurance AEP-NRC-2024-04, License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System2024-03-0606 March 2024 License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System AEP-NRC-2024-11, Unit 2 - Response to Request for Additional Information on Requested Change Regarding Neutron Flux Instrumentation2024-02-27027 February 2024 Unit 2 - Response to Request for Additional Information on Requested Change Regarding Neutron Flux Instrumentation AEP-NRC-2024-10, Form OAR-1, Owners Activity Report2024-02-0707 February 2024 Form OAR-1, Owners Activity Report AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report AEP-NRC-2023-11, Form OAR-1, Owners Activity Report2023-01-31031 January 2023 Form OAR-1, Owners Activity Report AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 AEP-NRC-2022-56, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2022-10-12012 October 2022 Unit 2 - Transmittal of Report of Changes to the Emergency Plan 2024-09-09
[Table view] |
Text
INDIANA MICHIGAN Indiana Michigan Power POWER One Cook Place Bridgman, MI 49106 A upit of American Electric Power India naMichiganPower.com August 31, 2012 AEP-NRC-2012-69 10 CFR 50.46 Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 ANNUAL REPORT OF LOSS-OF-COOLANT ACCIDENT EVALUATION MODEL CHANGES Pursuant to 10 CFR 50.46, Indiana Michigan Power Company (I&M), the licensee for Donald C. Cook Nuclear Plant (CNP), is transmitting an annual report of loss-of-coolant accident (LOCA) evaluation model changes affecting the peak cladding temperature (PCT) for CNP Unit 1 and Unit 2. CNP is providing, as an enclosure to this letter, the Unit 1 and Unit 2 Large Break and Small Break LOCA Analyses-of-Record PCT values and error assessments for calendar year 2011.
There are no new or revised commitments in this letter. Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.
Sincerely, Joel P. Gebbie Site Vice President JRW/kmh Enclosure Donald C. Cook Nuclear Plant Units 1-and 2,, Large and Small Break Loss-of-Coolant Accident Peak Clad Temperature Summary c: C. A. Casto, NRC Region III J. T. King, MPSC S. MW Krawec, AEP Ft. Wayne, w/o enclosures MDEQ - RMD/RPS NRC Resident Inspector P. S. Tam, NRC Washington, DC
ENCLOSURE TO AEP-NRC-2012-69 DONALD C. COOK NUCLEAR PLANT UNITS 1 AND 2 LARGE AND SMALL BREAK LOSS-OF-COOLANT ACCIDENT PEAK CLAD TEMPERATURE
SUMMARY
Abbreviations CNP Donald C. Cook Nuclear Plant OF degrees Fahrenheit FAH nuclear enthalpy rise hot channel factor FQ heat flux hot channel factor HHSI high head safety injection (Safety Injection System at CNP)
I&M Indiana Michigan Power Company LOCA loss of coolant accident MWt megawatts - thermal NRC Nuclear Regulatory Commission PCT peak cladding temperature RHR Residual Heat Removal SGTP steam generator tube plugging SI Safety Injection
Enclosure to AEP-NRC-2012-69 Page 1 CNP UNIT 1 LARGE BREAK LOCA Evaluation Model: ASTRUM (2004) 0 FQ= 2.15 FAH = 1.55 SGTP = 10% Break Size: Split Operational Parameters: 3304 MWt (plus 0.34% uncertainty) Reactor Power LICENSING BASIS Analysis-of-Record, November 20071 PCT = 2128°F MARGIN ALLOCATIONS (Delta PCT)
A. PREVIOUS 10 CFR 50.46 ASSESSMENTS
- 1. None 0OF B. PLANNED PLANT MODIFICATION EVALUATIONS
- 1. None 0OF 2
C. NEW 10 CFR 50.46 ASSESSMENTS
- 1. None 0°F D. OTHER
- 1. None 0°F LICENSING BASIS PCT + MARGIN ALLOCATIONS PCT = 2128°F The CNP Unit 1 Large Break LOCA Analysis-of-Record identified in this report is the same as the Analysis-of-Record identified in the annual report submitted in 2011 (ML11252B081). However, the designated analysis date has been changed to reflect the date that the analysis was performed.
2 Letter from J. P. Gebbie, I&M, to the NRC Document Control Desk, "Response to Information Request Pursuant to 10 CFR 50.54(f) Related to the Estimated Effect on Peak Cladding Temperature Resulting from Thermal .Conductivity Degradation in the Westinghouse-Furnished Realistic Emergency Core Cooling System Evaluation (TAC No. M99899)," AEP-NRC-2012-13, dated March 19, 2012, (ML12088A104) provided the estimated impact on the CNP Unit 1 and Unit 2 Large Break LOCA Evaluation Model from fuel thermal conductivity degradation. This impact will be addressed in the 10 CFR 50.46 annual report submitted for calendar year 2012.
Enclosure to AEP-NRC-2012-69 Page 2 CNP UNIT 1 SMALL BREAK LOCA Evaluation Model: NOTRUMP FQ=2.32 FAH=1.55 SGTP=30% 3" cold leg break Operational Parameters: SI System Cross-Tie Valves Closed, 3250 MWt (plus 2% uncertainty) Reactor Power' LICENSING BASIS Analysis-of-Record, June 20002.3 PCT= 1720'F MARGIN ALLOCATIONS (Delta PCT)
A. PREVIOUS 10 CFR 50.46 ASSESSMENTS
- 1. Asymmetric HHSI Delivery +50°F
- 2. Reduction in Turbine Driven Auxiliary Feedwater Flow +109 0 F
- 3. Burst and Blockage / Time in Life +111 0F B. PLANNED PLANT MODIFICATION EVALUATIONS
- 1. None 00 F C. NEW 10 CFR 50.46 ASSESSMENTS
- 1. None O0 F D. OTHER
- 1. None 0°F LICENSING BASIS PCT+ MARGIN ALLOCATIONS PCT= 1990'F The 3250 MWt power level used in this analysis bounds the Unit 1 3304 MWt steady state power limit in the operating license after adjusting for recapture of feedwater flow measurement and power calorimetric uncertainty.
2 The CNP Unit 1 Small Break LOCA Analysis-of-Record identified in this report is the same as the Analysis-of-Record identified in the annual report submitted in 2011 (ML11252B081). However, the designated analysis date has been changed to reflect the date that the analysis was performed.
3 Letter from R. A. Hruby, I&M, to the NRC Document Control Desk, "Donald C. Cook Nuclear Plant Unit 1 and Unit 2, Docket Nos. 50-315 and 50-316, Schedule for Submittal of Revised Unit 1 and Unit 2 Small Break Loss of Coolant Accident Analyses Addressing Residual Heat Removal System Spray Issue," AEP-NRC-2010-30, dated March 29, 2010, (ML100960423) informed the NRC staff that a revised Unit 1 Small Break LOCA analysis would be transmitted no later then August 31, 2012.
The revised analysis is being transmitted via separate correspondence, and will be reflected in the 10 CFR 50.46 annual report submitted for calendar year 2012.
Enclosure to AEP-NRC-2012-69 Page 3 CNP UNIT 2 LARGE BREAK LOCA Evaluation Model: ASTRUM (2004)
FQ= 2.3 3 5 FAH = 1.644 SGTP = 10% Break Size: Split Operational Parameters: 3468 MWt (plus 0.34% uncertainty) Reactor Power LICENSING BASIS Analysis-of-Record, February 2009 PCT = 2107'F A. PREVIOUS 10 CFR 50.46 ASSESSMENTS
- 1. None 00 F B. PLANNED PLANT MODIFICATION EVALUATIONS
- 1. None 00 F C. NEW 10 CFR 50.46 ASSESSMENTS1 I. None 00 F D. OTHER
- 1. None 00 F LICENSING BASIS PCT + MARGIN ALLOCATIONS PCT = 2107'F Letter from J. P. Gebbie, I&M, to the NRC Document Control Desk, "Response to Information Request Pursuant to 10 CFR 50.54(f) Related to the Estimated Effect on Peak Cladding Temperature Resulting from Thermal Conductivity Degradation in the Westinghouse-Furnished Realistic Emergency Core Cooling System Evaluation (TAC No. M99899)," AEP-NRC-2012-13, dated March 19, 2012, (ML12088A104) provided the estimated impact on the CNP Unit 1 and Unit 2 Large Break LOCA Evaluation Model from fuel thermal conductivity degradation. This impact will be addressed in the 10 CFR 50.46 annual report submitted for calendar year 2012.
Enclosure to AEP-NRC-2012-69 Page 4 CNP UNIT 2 SMALL BREAK LOCA Evaluation Model: NOTRUMP FQ= 2.32 FAH= 1.62 SGTP= 10% 4inch cold leg break Operational Parameters: RHR injection flow diversion to RHR spray and HHSI tram cross-tie valves open, 3600 MWt (plus 0.34% uncertainty) Reactor Power' LICENSING BASIS Analysis-of-Record, April 2011 PCT= 1274 0 F A. PREVIOUS 10 CFR 50.46 ASSESSMENTS
- 1. None 00 F B. PLANNED PLANT MODIFICATION EVALUATIONS
- 1. None 0°F C. NEW 10 CFR 50.46 ASSESSMENTS
- 1. None 00 F D. OTHER
- 1. None 00 F LICENSING BASIS PCT + MARGIN ALLOCATIONS PCT= 1274°F The 3600 MWt power level used in this analysis bounds the Unit 1 3468 MWt steady state power limit in the operating license.