Forwards Evaluation of ANO-2 HPSI Pump Operability W/O Water Cooling, Revision 1,per 810715 Commitment
ML20011A809
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 10/21/1981
From: Trimble D
ARKANSAS POWER & LIGHT CO.
To: Clark R
Office of Nuclear Reactor Regulation
Shared Package
ML20011A810 List:
References
2CAN108109, NUDOCS 8111030241
Download: ML20011A809 (1)


Text

-

(.

ARKANSAS POWER & LIGHT COMPANY POST OFFICE BOX 551 LITTLE ROCK. ARKANSAS 72203 (501)371-4000 October 21, 1981 hib 2CAN108109 g

Director of Nuclear Reactor Regulation

- : kl l)crn r2 j j'h d,.

ATTN: Mr. Robert A. Clark, Chief g.

Operating Reactors Branch #3 N O V 0 2 ;g g y.3 Division of Licensing

" *Ap C,

~

U. S. Nuclear Regulatory Commission V

p Washington, D. C.

20555

SUBJECT:

Arkansas Nuclear One - Unit 2 Docket No. 50-368 License No. NPF-6 Evaluation of HPSI Operability Without Service Water Cooling Report Revision (File:

2-0510.5)

Gentlemen:

In a conference call on July 15, 1981, AP&L committed to submit a revised report discussing testing and analysis performed to determine the effect of service water flow blockage on the Unit 2 HPSI pump bearings and seal water coolers.

This report has been completed and is attached.

Very truly yours, bY f.

David C. Trimble Manager, Licensing DCT:MCS: sc M

Attachment l