2CAN060306, Arkansas, Unit 2, License Amendment Request, to Revise Spent Fuel Pool Loading Pattern
ML031890737 | |
Person / Time | |
---|---|
Site: | Arkansas Nuclear |
Issue date: | 06/30/2003 |
From: | Anderson C Entergy Operations |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
2CAN060306 | |
Download: ML031890737 (2) | |
Similar Documents at Arkansas Nuclear | |
---|---|
Category:Letter type:
MONTHYEAR0CAN102401, Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzle2024-10-16016 October 2024
[Table view]Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 2CAN102401, Cycle 31 Core Operating Limits Report (COLR)2024-10-14014 October 2024 Cycle 31 Core Operating Limits Report (COLR) 1CAN082401, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R312024-08-13013 August 2024 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R31 2CAN072401, Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02)2024-07-19019 July 2024 Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) 0CAN072401, Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes2024-07-0808 July 2024 Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes 1CAN072401, Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply2024-07-0202 July 2024 Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply 0CAN062403, Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels2024-06-25025 June 2024 Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels 0CAN062402, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-06-0606 June 2024 Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 0CAN052401, – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 20232024-05-13013 May 2024 – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 2023 1CAN052401, Cycle 32 Core Operating Limits Report2024-05-0404 May 2024 Cycle 32 Core Operating Limits Report 2CAN042403, Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C2024-04-24024 April 2024 Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C 0CAN042402, Annual Occupational Radiation Exposure Report for 20232024-04-23023 April 2024 Annual Occupational Radiation Exposure Report for 2023 0CAN042401, Radioactive Effluent Release Report for the 2023 Calendar Year2024-04-15015 April 2024 Radioactive Effluent Release Report for the 2023 Calendar Year 2CAN042402, Special Report of Non-functional Main Steam Line Radiation Monitor2024-04-11011 April 2024 Special Report of Non-functional Main Steam Line Radiation Monitor 2CAN042401, Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications2024-04-0404 April 2024 Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications 2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 2024-08-13 Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50 MONTHYEARML23208A2112023-07-27027 July 2023
[Table view]Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN082201, License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-08-30030 August 2022 License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements ML21279A2312021-10-0606 October 2021 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements Using the Consolidated Line-Item Improvement 1CAN102101, SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2021-10-0606 October 2021 SAR Amendment 30, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report 1CAN092101, License Amendment Request Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2021-09-30030 September 2021 License Amendment Request Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations ML21266A1612021-09-23023 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated ML21182A1582021-07-0101 July 2021 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections 1CAN052102, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2021-05-26026 May 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors 2CAN052102, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2021-05-26026 May 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors 1CAN022102, Supplement Related to License Amendment Request to Replace the Reactor Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2021-02-22022 February 2021 Supplement Related to License Amendment Request to Replace the Reactor Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate 0CAN022102, Unit 2; License Amendment Request - One-Time Change to Support Proactive Upgrade of the Emergency - Cooling Pond Supply Piping2021-02-0808 February 2021 Unit 2; License Amendment Request - One-Time Change to Support Proactive Upgrade of the Emergency - Cooling Pond Supply Piping 2CAN112004, License Amendment Request - Application to Adopt a Safety Function Determination Program (SFDP)2020-11-17017 November 2020 License Amendment Request - Application to Adopt a Safety Function Determination Program (SFDP) 2CAN092003, License Amendment Request, Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2020-09-24024 September 2020 License Amendment Request, Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions 1CAN072001, Supplemental Information Related to License Amendment Request to Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2020-07-21021 July 2020 Supplemental Information Related to License Amendment Request to Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate 1CAN022001, License Amendment Request: Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate2020-02-24024 February 2020 License Amendment Request: Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent Sodium Tetraborate 1CAN012002, License Amendment Request: Revise Loss of Voltage Relay Allowable Values2020-01-24024 January 2020 License Amendment Request: Revise Loss of Voltage Relay Allowable Values 2CAN121903, License Amendment Request, Revise Control Element Assembly Drop Time2019-12-18018 December 2019 License Amendment Request, Revise Control Element Assembly Drop Time 2CAN121901, License Amendment Request Technical Specification Deletions, Additions, and Relocations2019-12-16016 December 2019 License Amendment Request Technical Specification Deletions, Additions, and Relocations 1CAN101903, Supplement to License Amendment Request: Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO2019-10-23023 October 2019 Supplement to License Amendment Request: Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO 0CAN091901, Unit 2: License Amendment Request - Change in Implementation Date for Amendments 263 and 3142019-09-0505 September 2019 Unit 2: License Amendment Request - Change in Implementation Date for Amendments 263 and 314 2CAN081903, License Amendment Request Technical Specification (TS) Change Related to Revised Fuel Handling Accident Analysis and Adoption of TS Improvements Consistent with NUREG-14322019-08-29029 August 2019 License Amendment Request Technical Specification (TS) Change Related to Revised Fuel Handling Accident Analysis and Adoption of TS Improvements Consistent with NUREG-1432 1CAN051901, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF 563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program.2019-05-29029 May 2019 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF 563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program. 0CAN041904, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into the Licensing Basis2019-04-29029 April 2019 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into the Licensing Basis 1CAN031901, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco.2019-03-25025 March 2019 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an Lco. CNRO-2019-00003, Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 42019-01-31031 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 4 1CAN121801, Application to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues2018-12-19019 December 2018 Application to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues 2CAN121801, License Amendment Request, Add Actions to Address Inoperability of the Containment Building Sump2018-12-19019 December 2018 License Amendment Request, Add Actions to Address Inoperability of the Containment Building Sump 2CAN051801, License Renewal Pressurizer Surge Line and Safety Injection Nozzle Inspection2018-05-24024 May 2018 License Renewal Pressurizer Surge Line and Safety Injection Nozzle Inspection ML18094A1552018-03-29029 March 2018 Enclosures 2 - 6: Proposed EAL Technical Basis Document, NEI 99-01. Rev. 6., Proposed EAL Matrix Chart/Review Table and Supporting Referenced Document Pages 0CAN031801, Unit 2 - License Amendment Request - Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 62018-03-29029 March 2018 Unit 2 - License Amendment Request - Adoption of Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6 1CAN031801, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2018-03-12012 March 2018 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) 2CAN121702, License Amendment Request Post-Accident Instrumentation Technical Specification Revision2017-12-14014 December 2017 License Amendment Request Post-Accident Instrumentation Technical Specification Revision 2CAN111702, License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits2017-11-20020 November 2017 License Amendment Request - Updating the Reactor Coolant System Pressure-Temperature Limits 1CAN101701, License Amendment Request Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves2017-10-0202 October 2017 License Amendment Request Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves ML17268A2132017-09-21021 September 2017 ISFSI, River Bend Station Unit 1 & ISFSI, Waterford 3 Steam Electric Station & ISFSI, Grand Gulf Nuclear Station & ISFSI, Application for Order Approving Transfers of Licenses and Conforming License Amendments 1CAN081701, Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability.2017-08-14014 August 2017 Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability. 2CAN081701, Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability.2017-08-14014 August 2017 Application to Revise Technical Specifications to Adopt TSTF-427, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability. 2CAN071701, License Amendment Request, Application for Technical Specification Improvement to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-14322017-07-17017 July 2017 License Amendment Request, Application for Technical Specification Improvement to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-1432 1CAN071701, License Amendment Request, Application for Technical Specification Improvement to Revise Actions for Inoperable Using the Consolidated Line Item Improvement Process2017-07-17017 July 2017 License Amendment Request, Application for Technical Specification Improvement to Revise Actions for Inoperable Using the Consolidated Line Item Improvement Process 1CAN061701, Amendment 27 of the SAR, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report2017-06-0707 June 2017 Amendment 27 of the SAR, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report 1CAN041702, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line.2017-04-24024 April 2017 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line. 2CAN041702, License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection.2017-04-24024 April 2017 License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection. 2CAN101601, License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications2016-10-27027 October 2016 License Amendment Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications 1CAN051602, Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-8052016-05-19019 May 2016 Update to Tables S-1 and S-2 - Adoption of National Fire Protection Association Standard NFPA-805 2CAN031602, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme..2016-03-25025 March 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, and to Request an Alternative to the Asme.. 2023-07-27 |
Text
Entergy Operations, Inc.
E nte s 1448 SR. 333 En tergy ~ ~~~~~~~~~~~~~~~~~~~~~~~
AR 72801 Tel501-858-4888 Craig Anderson Vice President Operations ANO 2CAN060306 June 30, 2003 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
License Amendment Request To Revise the Spent Fuel Pool Loading Pattern Arkansas Nuclear One, Unit 2 Docket No. 50-368 License No. NPF-6
Dear Sir or Madam:
Pursuant to 10 CFR 50.90, Entergy Operations, Inc. (Entergy) hereby requests an amendment for Arkansas Nuclear One, Unit 2 (ANO-2). The proposed amendment will: 1) eliminate credit for the Boraflex neutron absorbing material used for reactivity control in Region 1 of the Spent Fuel Pool (SFP); 2) credit a combination of soluble boron and several defined fuel loading patterns within the storage racks to maintain SFP reactivity within the effective neutron multiplication factor (keff) limits of 10 CFR 50.68; 3) increase the minimum boron concentration in the SFP to 2000 parts per million; and 4) reduce the fresh fuel assembly initial enrichment to less than or equal to 4.55+0.05 weight percent (wt%) uranium-235 (U-235).
The proposed change has been evaluated in accordance with 10 CFR 50.91(a)(1) using criteria in 10 CFR 50.92(c) and it has been determined that this change involves no significant hazards considerations. The bases for these determinations are included in the attached submittal.
The proposed change includes a new commitment which is summarized in Attachment 4.
Entergy requests approval of the proposed amendment by September 3, 2003 in order to support a full core offload during the ANO-2 fall 2003 refueling outage. Once approved, the amendment shall be implemented within 30 days. Although this request is neither exigent nor emergency, your prompt review is requested.
2CAN060306 Page 2 of 2 If you have any questions or require additional information, please contact Dana Millar at 601-368-5445.
I declare under penalty of perjury that the foregoing is true and correct. Executed on June 30, 2003.
Sincerely, CGA/dm Attachments:
- 1. Analysis of Proposed Technical Specification Change
- 2. Proposed Technical Specification Changes (mark-up)
- 3. Changes to Technical Specification Bases Pages - For Information Only
- 4. List of Regulatory Commitments
- 5. Holtec License Amendment Report cc: Mr. Thomas P. Gwynn Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P. O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Thomas W. Alexion MS O-7D1 Washington, DC 20555-0001 Mr. Bemard R. Bevill Director Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street Little Rock, AR 72205