MONTHYEAR2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN122202, Registration of Cask Use2022-12-21021 December 2022 Registration of Cask Use 0CAN122201, Reply to a Notice of Violation; EA-22-0992022-12-0808 December 2022 Reply to a Notice of Violation; EA-22-099 0CAN112201, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2022-11-10010 November 2022 Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 1CAN102203, Cycle 31 Core Operating Limits Report2022-10-24024 October 2022 Cycle 31 Core Operating Limits Report 1CAN102201, Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-10-13013 October 2022 Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 0CAN092201, Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-09-29029 September 2022 Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN092201, Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-09-0808 September 2022 Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 0CAN082201, License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-08-30030 August 2022 License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN082201, Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-08-24024 August 2022 Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 2CAN072201, Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods2022-07-20020 July 2022 Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods 0CAN072201, Registration of Cask Use2022-07-14014 July 2022 Registration of Cask Use 0CAN062202, Registration of Cask Use2022-06-0909 June 2022 Registration of Cask Use 1CAN062201, Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-06-0202 June 2022 Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 1CAN052201, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-0352022-05-31031 May 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-035 2024-01-17
[Table view] |
Text
Entergy Operations, Inc.
Entergy 1448 S.R. 333 Russeliville, AR 72802 Tel 479858-4888 Jeffery S. Forbes Vice President Operations ANO 2CAN030402 March 11, 2004 Ms. Annette L. Vietti-Cook, Secretary Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudications Staff Washington, DC 20555
SUBJECT:
Answer to Issuance of First Revised NRC Order (EA-03-009)
Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors Arkansas Nuclear One, Unit 2 Docket No. 50-368 License No. NPF-6
Dear Ms. Vietti-Cook,
In accordance with 10 C.F.R. § 2.202(a)(2), Entergy Operations, Inc. ("Entergy"), hereby submits for filing its answer to the February 20, 2004, First Revised NRC Order (EA-03-009)
Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors and a related Certificate of Service in the captioned matter.
Entergy does not request a hearing on the Order. Entergy consents to the Order modifying the license of Arkansas Nuclear One, Unit 2 (ANO-2) as delineated in Section IV thereof.
This letter contains no new commitments. If you have any questions or require additional information, please contact Steve Bennett at 479-858-4626.
Sincerely, JSF/sab
,4o/
1~ &(q(o4.
2CAN030402 Page 2 of 2 Attachments:
- 1. Licensee's Answer to February 20, 2004 First Revised Commission Order Modifying License Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors
- 2. Certificate of Service cc: Mr. James E. Dyer, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, DC 20555 Mr. Dennis C. Dambly Assistant General Counsel for Materials Litigation and Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555 Dr. Bruce S. Mallett, Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555
ATTACHMENT I 2CAN030402 LICENSEE'S ANSWER TO FEBRUARY 20, 2004 FIRST REVISED COMMISSION ORDER MODIFYING LICENSE ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS to 2CAN030402 Page 1 of 2 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
Entergy Operations, Inc. ) Docket No. 50-368
) License No. NPF-6 Arkansas Nuclear One, Unit 2 )
LICENSEE'S ANSWER TO FEBRUARY 20, 2004 FIRST REVISED COMMISSION ORDER MODIFYING LICENSE ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS On February 20, 2004, the Nuclear Regulatory Commission ('NRC" or Commission") issued an immediately effective order in the captioned matter entitled First Revised Order Modifying Licenses (Effective Immediately) ("Order") to, inter alia, Entergy Operations, Inc. ("Entergy").
This Order supercedes the original Order Modifying Licenses, which was issued on February 11, 2003. The Order stated that recent experience indicated that current inspection requirements in Section XI of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ("ASME Code") and related.NRC regulations do not provide adequate assurance that reactor coolant pressure boundary integrity will be maintained for all combinations of construction materials, operating conditions, and operating histories at pressurized water reactors ("PWRs"). The Commission stated that long-term resolution of reactor pressure vessel ("RPV") head penetration inspection requirements is expected to involve changes to the ASME Code and NRC regulations, specifically 10 C.F.R. § 50.55a.
Consequently, the Commission stated that it was necessary to establish a minimum set of RPV head inspection requirements, as a supplement to existing inspection and other requirements in the ASME Code and NRC regulations, through the issuance of the Order. Therefore, the Commission imposed interim inspection requirements set forth in Section IV of the Order to 2CAN030402 Page 2 of 2 pending the development of consensus standards and incorporation of revised inspection requirements into 10 C.F.R. § 50.55a, directly or through reference to a future version of the ASME Code.
Pursuant to 10 C.F.R. § 2.202(d), Entergy consents to the Order modifying the license as set forth in Section IV of the Order for performing inspections of the Arkansas Nuclear One, Unit 2, reactor pressure vessel head. Entergy does not request a hearing on the Order.
I declare under penalty of perjury that the foregoing is true and correct. Executed on March 11, 2004.
Respectfully submitted, Entergy Operations, Inc.
Jeffery S. Forbes Vice President, Operations Arkansas Nuclear One
ATTACHMENT 2 2CAN030402 CERTIFICATE OF SERVICE to 2CAN030402 Page 1 of 1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
Entergy Operations, Inc. ) Docket No. 50-368
) License No. NPF-6 Arkansas Nuclear One, Unit 2 )
CERTIFICATE OF SERVICE I hereby certify under penalty of perjury that copies of the ANSWER TO FEBRUARY 20, 2004, FIRST REVISED COMMISSION ORDER MODIFYING LICENSE ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS in the captioned action have been served on the following by deposit in the United States mail, first class, and in addition, by overnight delivery (as indicated by an asterisk "*"), by facsimile, or by e-mail as directed in Section V of the Order (as indicated by a double asterisk "**"), this 11th day of March 2004.
Ms. Annette L. Vietti-Cook, Secretary** Mr. James E. Dyer, Director*
Office of the Secretary of the Commission Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-5E7 ATTN: Rulemakings and One White Flint North Adjudications Staff 11555 Rockville Pike Washington, DC 20555-0001 Rockville, MD 20852-2738 Dr. Bruce S. Mallett, Regional Administrator Mr. Dennis C. Dambly**
U.S. Nuclear Regulatory Commission Assistant General Counsel for Materials Region IV Litigation and Enforcement 611 Ryan Plaza Drive, Suite 400 U.S. Nuclear Regulatory Commission Arlington, TX 76011 Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Jeffery S. Fdrbes Vice President, Operations Arkansas Nuclear One