|
---|
Category:Letter type:
MONTHYEAR0CAN102401, Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzle2024-10-16016 October 2024 Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 2CAN102401, Cycle 31 Core Operating Limits Report (COLR)2024-10-14014 October 2024 Cycle 31 Core Operating Limits Report (COLR) 1CAN082401, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R312024-08-13013 August 2024 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R31 2CAN072401, Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02)2024-07-19019 July 2024 Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) 0CAN072401, Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes2024-07-0808 July 2024 Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes 1CAN072401, Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply2024-07-0202 July 2024 Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply 1CAN072402, Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications2024-07-0101 July 2024 Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications 0CAN062403, Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels2024-06-25025 June 2024 Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels 0CAN062402, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-06-0606 June 2024 Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 0CAN052401, – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 20232024-05-13013 May 2024 – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 2023 1CAN052401, Cycle 32 Core Operating Limits Report2024-05-0404 May 2024 Cycle 32 Core Operating Limits Report 2CAN042403, Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C2024-04-24024 April 2024 Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C 0CAN042402, Annual Occupational Radiation Exposure Report for 20232024-04-23023 April 2024 Annual Occupational Radiation Exposure Report for 2023 0CAN042401, Radioactive Effluent Release Report for the 2023 Calendar Year2024-04-15015 April 2024 Radioactive Effluent Release Report for the 2023 Calendar Year 2CAN042402, Special Report of Non-functional Main Steam Line Radiation Monitor2024-04-11011 April 2024 Special Report of Non-functional Main Steam Line Radiation Monitor 2CAN042401, Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications2024-04-0404 April 2024 Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications 2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2024-08-13
[Table view] |
Text
---Entergy Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Christopher J. Schwarz Vice President, Operations Arkansas Nuclear One 1CAN111202 November 27, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Flooding Walkdown Report - Entergy's Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Arkansas Nuclear One - Unit 1 Docket No. 50-313 License No. DPR-51
REFERENCES:
- 1. NRC letter to Entergy, RFI Pursuantto Title 10 of the Code of FederalRegulations 50.54(f) Regarding Recommendations 2. 1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichiAccident, dated March 12, 2012 (OCNA031208) (ML12053A340)
- 2. Entergy letter to NRC, Entergy's Response to NRC RFI Pursuant to 10 CFR 50.54(f) Regarding the FloodingAspects of Recommendations 2.1 and2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated June 8, 2012 (0CAN061202) (ML12164A567)
Dear Sir or Madam:
On March 12, 2012, the NRC issued Reference 1 to all power reactor licensees.
Enclosure 4 of the referenced letter contains specific requested actions, requested information, and required responses associated with Recommendation 2.3 for flooding walkdowns. Entergy Operations, Inc. (Entergy) confirmed in Reference 2 that it would use the flooding walkdown procedure (Nuclear Energy Institute 12-07, Guidelines for Performing Verification Walkdowns of Plant Flood ProtectionFeatures)as endorsed by the NRC as the basis to conduct the walkdowns and develop the needed information at Arkansas Nuclear One, Unit-1 (ANO-1).
Pursuant to Required Response 2 of Reference 1, Enclosure 4, Entergy is providing the Flooding Walkdown Report for ANO-1 in Attachment 1.
This letter contains a new regulatory commitment, which is identified in Attachment 2.
Should you have any questions concerning this submittal, please contact Stephenie Pyle at 479.858.4704.
1CAN111202 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on November 27, 2012.
Sincerely, CJS/nbm Attachments: 1. ANO-1 Flooding Walkdown Report
- 2. List of Regulatory Commitments cc: Mr. Elmo E. Collins Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 U. S. Nuclear Regulatory Commission Attn: Director, Office of Nuclear Reactor Regulation One White Flint North 11555 Rockville Pike Rockville, MD 20852 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Kaly Kalyanam One White Flint North, MS 0-8 B1 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Attn: Mr. Robert J. Fretz Jr.
One White Flint North, MS 4A15A 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Attn: Mr. Robert L. Dennig One White Flint North, MS 10E1 11555 Rockville Pike Rockville, MD 20852
Attachment 2 to 1CANl11202 List of Regulatory Commitments to 1CAN1112O2 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE SCHEDULED (Check One) COMPLETION COMMITMENT ONE- DATE TIME CONTINUING (If Required)
ACTION COMPLIANCE Entergy will perform walkdowns for x September 30, 2013 equipment that could not be inspected as identified in Section 7.4 (restricted access features only) of the Arkansas Nuclear One, Unit-1 Flooding Walkdown Report.