0CAN120505, Demand for Information Extension Request
| ML053570269 | |
| Person / Time | |
|---|---|
| Site: | Arkansas Nuclear |
| Issue date: | 12/13/2005 |
| From: | Marlow T Entergy Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 0CAN120505 | |
| Download: ML053570269 (2) | |
Text
..
Admokk ss-:
Entergy Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 501 858 5000 OCAN120505 December 13, 2005 U.S. Nuclear Regulatory Co'mmission-Attn: Docurment Contiol Dbesk Washington, DC 20555-0001
Subject:
Drahd f6&Inf6rmation'Extension Request Arkin'sa' Nucletar On'e -Jrnits1 and 2
'Docket Nos 50-313 and 50-368 License N6os'. bPR-51 and NPF-6
.r Sir.,.or. Ma
Dear Sir or Madam:
..I I
By letter dated December 2, 2005 (OCNA120501), Entergy received a 'Demand for Information" pertaining to Arkansas Nuclear One, Units 1 and 2. Pursuant to the etter, Entergy is required to file an answer, under oath or affirmation, within thirty-five days, i.e.,
on or before January 6, 2006.
Developing responses to the Demand for Information will require the collection of information from, and verification by, numerous sources, as well as analyses. This, coupled with the intervening holidays, will make compliance with the schedule extremely difficult.
Accordingly, Entergy requests a'riadditiohnaI two weeks within which to respond, i.e., until January 20, 2006. 'Granting of the extension of time will not delay the substantive adoption of strategies and,:therefore, will ha'ie' noradverse impact on safety. In addition, efforts directed at ideritifyirig additiohal'strategies under ongoing Phase 3 activities will not be affected.
There are no WWW cobmmitmenets contained in this submittal. Should you have any questions cobncerning'this submittal,"please contact Ms. Natalie Mosher at (479) 858-4635.
Sincerely,'
Thomas A. Marlow Director, Nuclear Safety Assurance, TAM/nbm SUDI
i F-'
OCAN120505 Page 2 cc:
Dr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Drew Holland Mail Stop 0-7 D1 Washington, DC 20555-0001