Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802 Tel 479-858-4601 Thomas A. Marlow Director, Nuclear Safety OCAN 100602 October 18, 2006 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Generic Letter 2004-02 Commitment Revision Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6

Dear Sir or Madam:

By letters dated August 31, 2005 (0CAN080501) and December 15, 2005 (OCAN 120504), Entergy provided a response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors" (OCNA090401), for Arkansas Nuclear One (ANO). In the August 31, 2005, correspondence, Entergy committed to plant modifications to install new sump strainers and resolve chemical effects, downstream effects, and the resulting effects on the final head-loss during the fall of 2006 for ANO-2 and the spring of 2007 for ANO-1 refueling outages.

As outlined in correspondence dated August 23, 2006 (0CAN080602), the above commitment requires revision. Entergy is proceeding with current plans to install strainer modifications in the sumps for both of the ANO units during the ongoing refueling outage for ANO-2 and the upcoming spring of 2007 refueling outage for ANO-1. These modifications may resolve chemical effects, downstream effects, and the resulting effects on the final head-loss for both of the ANO units by December 31, 2007; however, given the uncertainties delineated in the August 23, 2006, correspondence, this may not be feasible. If it is determined that additional time will be required to resolve these issues, Entergy will inform the NRC of the need at that time.

New commitments contained in this submittal are summarized in Attachment 1. Should you have any questions concerning this submittal, please contact Ms. Natalie Mosher at (479) 858-4635.

6' OCAN 100602 Page 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on October 18, 2006.

Sincerely, TAM/nbm Attachment cc:

Dr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Drew Holland Mail Stop O-7D1 Washington, DC 20555-0001 OCAN 100602 List of Regulatory Commitments to OCAN 100602 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.

TYPE (Check One)

SCHEDULED ONE-COMPLETION TIME CONTINUING DATE COMMITMENT ACTION COMPLIANCE (If Required)

Entergy plans to resolve chemical X

December 31, 2007 effects, downstream effects, and the resulting effects on the head-loss for both of the ANO units.